Citation : 2018 Latest Caselaw 34 Bom
Judgement Date : 4 January, 2018
(1) 33-CA 15408 of 2017 & Ors.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
33 CIVIL APPLICATION NO. 15408 OF 2017
IN FAST/37772/2017 WITH CA/15409/2017 IN FAST/37772/2017
1) The State of Maharashtra
Through: Collector, Latur.
2) The Executive Engineer,
Minor Irrigation Division,
Local Sector, Latur,
District Latur. ..Applicants
Versus
Bharat s/o Tulshiram Nade
Age: 52 years, Occu.: Agriculture,
R/o. Murud, Tq. & Dist.Latur. ..Respondent
...
AGP for Applicants : Mr.A.M.Phule
Advocate for Respondents : Mr.R.D.Raut
...
...
WITH
CA/15410/2017 IN FAST/37826/2017 WITH CA/15411/2017 IN
FAST/37826/2017
WITH
CA/15413/2017 IN FAST/37837/2017 WITH CA/15414/2017 IN
FAST/37837/2017
WITH
CA/15415/2017 IN FAST/37841/2017 WITH CA/15416/2017 IN
FAST/37841/2017
WITH
CA/15417/2017 IN FAST/37830/2017 WITH CA/15418/2017 IN
FAST/37830/2017
::: Uploaded on - 11/01/2018 ::: Downloaded on - 12/01/2018 00:54:13 :::
(2) 33-CA 15408 of 2017 & Ors.
WITH
CA/15419/2017 IN FAST/37833/2017 WITH CA/15420/2017 IN
FAST/37833/2017
...
CORAM : M.S.SONAK, J.
DATE : 4th JANUARY, 2018
ORAL JUDGMENT:-
1) Heard Mr.A.M.Phule, learned AGP for the applicants
and Mr.R.D.Raut, learned counsel for the respondents in
all these Civil Applications.
2) By these Civil Applications, which are virtually
identical in nature, the State seeks condonation of delay
in instituting appeals against Judgment and Award dated
31.3.2012. The delay in each of these matters is of 1972
days i.e. more than five years.
3) Mr.Phule, learned AGP submits that in these cases,
the Reference Court has enhanced the compensation almost
12 times without there being any material on record to
justify such enhancement. He submits that the delay was
(3) 33-CA 15408 of 2017 & Ors.
because files had to move from table to table and
decisions had to be taken by several authorities before
the appeals could actually be instituted. He points out
that the certified copy of the Judgment and Award dated
31.3.2012 was applied for on 13.8.2013 and after the
same was ready, the matter was referred to the office of
Government Pleader for legal opinion. After securing
such opinion, the matter was referred to the Joint
Secretary, Law and Judiciary Department, who recommended
filing of the appeals and ultimately on 24.9.2015, the
papers were forwarded to the office of Government Pleader
and soon thereafter, the Government Pleader prepared the
appeal papers. However, there was some delay in securing
certified copies, Demand Drafts for Court fees and legal
expenses and therefore, the appeals alongwith application
for condonation of delay could be instituted only on
21.11.2017.
4) Mr.Phule, learned AGP submits that all this is
(4) 33-CA 15408 of 2017 & Ors.
sufficient cause and therefore, the delay in instituting
all appeals may be condoned.
5) Mr.Phule, learned AGP relying upon decision of the
Supreme Court in the case of N.Balakrishnan vs. M.
1998 (7) SCC 123] submits Krishnamurthy, reported in [
that in such matters, the length of delay is not
significant but the acceptability of the explanation is
the only criteria. Mr.Phule also relied upon the
decision of the Supreme Court in the case of Collector
Land Acquisition vs Mst. Katiji & Ors., reported in
[ 1987 (2) SCC 107 ] to submit that refusing to condone
delay can result in a meritorious matter being thrown out
at the very threshold and cause of justice being
defeated. He submits that in case the delay is condoned,
at the highest the appeals can be decided on merits. For
all these reasons, Mr.Phule, learned AGP submits that
this is a fit case for condonation of delay.
(5) 33-CA 15408 of 2017 & Ors. 6) Mr.R.D.Raut, learned counsel for the respondents
submits that the delay in the present case is quite
inordinate and there is absolutely no explanation for the
same. He submits that the applications seeking
condonation of delay are quite vague and in all cases it
is not sufficient merely to state that decisions had to
be taken at different levels and therefore, more time was
spent for filing the appeals. He points out that there
are no details in the Civil Applications and the
explanation offered is entirely vague and can never
constitute sufficient cause. He submits that the
respondents' lands have been acquired and it is quite
unjust and unfair that the compensation awarded in their
favour should be revisited at this point of time. For
all these reasons, Mr.Raut, learned counsel submits that
these Civil Applications may be dismissed.
7) In order to appreciate the rival contentions, it is
necessary to make a reference to the cause as indicated
(6) 33-CA 15408 of 2017 & Ors.
in the Civil Applications. The impugned Judgment and
Award was made on 31.3.2012 and the applicants admit that
the certified copy was applied for only on 13.8.2013.
There is absolutely no explanation in the applications as
to why there was such inordinate delay in even applying
for certified copies of the Judgment and Award,
particularly, since it is now the case of the applicants
that there was manifold increase in the compensation
amount awarded by the Land Acquisition Officer. The
statement that some time was spent to obtain opinion from
Assistant Government Pleader and Joint Secretary, Law and
Judiciary Department, is again, quite vague and backed by
no particulars. In any case, the Officers are expected
to act within some reasonable period. There is no point
in seeking condonation of delay virtually as a matter of
right on the ground that the Assistant Government
Pleader's office or the Joint Secretary, Law and
Judiciary Department, took some time to furnish a legal
opinion.
(7) 33-CA 15408 of 2017 & Ors. 8) In this case, the legal opinion and recommendation
for filing of appeal was taken on 24.9.2015. Thereafter,
the Office of the Government Pleader also prepared the
appeal memos in the month of September 2015 itself. The
appeals and applications for condonation of delay are
instituted on 22.11.2017. Again, the delay between
September 2015 and November 2017 is both inordinate and
unexplained. The vague statement that the memos of
appeal were incomplete or that the Demand Draft for
payment of Court fees and legal expenses, was not
enclosed alongwith proposal can hardly be said to
constitute sufficient cause. Inspite the delay being of
more than five years, the applications merely state that
there is 'some delay' in institution of appeals. This is
hardly the proper manner to explain the delay. It is true
that every day's delay is not required to be explained.
However, that does not mean that delay which is of over
five years can be explained in such a casual manner. In
(8) 33-CA 15408 of 2017 & Ors.
such circumstances, it cannot be said that any sufficient
cause has been made out to condone the delay.
9) Normally, the applications seeking condonation of
delay are liberally considered. This is more so when
impersonal agency like the Government or Public Sector
Acquiring Bodies are concerned. Mr.Phule, learned AGP
is quite right in his submission that quantum of delay is
not decisive but it is the quality of explanation, which
determines the matter. In the present case, the quality
of explanation is simply lacking. On the basis of the
vague pleadings of procedural delay, it will not be
appropriate to condone such inordinate delay of over five
years in instituting all the appeals.
10) Ultimately, the plight of the land losers cannot be
totally forgotten. They have lost their lands several
years ago. They have been litigating to secure some
compensation, since according to them, what was awarded
(9) 33-CA 15408 of 2017 & Ors.
by the Land Acquisition Officer was mere pittance.
Despite the determination by the reference Court, almost
five years ago, as pointed out by learned counsel for
respondents, the enhanced compensation has not infact
been paid to the land losers. There is no clarity as to
whether the land losers have levied execution or not.
Learned counsel for respondents submits that in most
cases, the land losers have no means to levy execution,
since, the experience has shown that the mighty State
which has acquired their lands is often successful in
delaying the execution process as well. Respondents have
thus suffered enough prejudice on account of denial of
enhanced compensation despite the award made by the
reference Court almost five years ago. To permit the
applicant at this stage to re-visit the issue of
compensation and that too, without there being any
sufficient cause shown to explain the inordinate delay,
will only amount to grant of undeserved indulgence to the
applicant, in the facts and circumstances of the case.
( 10 ) 33-CA 15408 of 2017 & Ors.
The possibility of these appeals having been instituted
only to seek some ex-post facto justification for non-
payment of enhanced compensation to the land losers,
cannot be ruled out. In such circumstances, it will not
be appropriate to exercise discretion in favour of the
applicants.
11) The decision in N. Balkrishnan (supra) case requires
the applicant to demonstrate good faith before claiming
exercise of discretion. The decision, no doubt, states
that the length of delay is not decisive but the quality
of explanation is the determinative factor. In this
case, quality of explanation is too poor to constitute
any sufficient cause. Mst. Katiji (supra), no doubt,
absolves explanation of each day's delay. However, the
observation does not mean that delay of over five years
is to be condoned as a matter of routine in the absence
of any sufficient cause.
( 11 ) 33-CA 15408 of 2017 & Ors.
12) The averments in the application seeking
condonation, are quite casual and unverifiable. On basis
of such routine averments, the State, cannot, in every
case, plead that delay should be condoned, because it is
an impersonal agency, which is required to act through
its officers. The statements that files had to be moved
from table to table or that pressure of work or that some
time is always required for decisions, which have to be
taken at different levels are reasons too vague to merit
any acceptance, particularly when we are dealing with
case of land losers, who have been deprived of
compensation for several years.
13) In Pundlik Jalam Patil (Dead) By Lrs. vs. Executive
Engineer, Jalgaon, Medium Project and anr ., reported in
[(2008) 17 SCC 448], the Hon'ble Supreme Court has held
that pursing stale claims and multiplicity of proceedings
in no manner subserves public interest. These public
( 12 ) 33-CA 15408 of 2017 & Ors.
interest parameters ought to be kept in mind by the
courts while exercising the discretion dealing with the
application filed under section 5 of the Limitation Act.
Dragging the land-losers to courts of law years after the
termination of legal proceedings would not serve any
public interest. Settled rights cannot be lightly
interfered with by condoning inordinate delay without
there being any proper explanation of such delay on the
ground of involvement of public revenue. This serves no
public interest. Though, the State or its
instrumentalities seeking condonation of delay may be
entitled to certain amount of latitude but the law of
limitation is same for citizens and for governmental
authorities. It would be a different matter where the
Government makes out a case where public interest was
shown to have suffered owing to acts of fraud or
collusion on the part of its officers or agents and where
the officers were clearly at cross purposes with it. In
a given case, if any, such facts are pleaded and proved
( 13 ) 33-CA 15408 of 2017 & Ors.
they cannot be excluded from consideration. In cases
with which we are concerned, no such facts have been
either pleaded or proved.
14) In Registrar of Companies vs. Rajshree Sugar &
Chemicals Ltd. and ors reported in ., [ 2(2000) 6 SCC 133],
the Hon'ble Supreme Court held that though some latitude
has to be shown to the Government in deciding the
question of delay, that does not give a licence to the
officers of the Government to shirk their responsibility
to act with reasonable expedition.
15) In Esha Bhattacharjee vs. Managing Committee of
Raghunathpur afar Academy & ors ., reported in 3(2013) 12 [
SCC 649], the Hon'ble Supreme Court has held that an
application for condonation of delay should be drafted
with careful concern and not in a haphazard manner
harbouring the notion that the courts are required to
condone delay on the bedrock of the principle that
( 14 ) 33-CA 15408 of 2017 & Ors.
adjudication of a lis on merits is seminal to justice
dispensation system. Further, the Hon'ble Supreme Court
has held that an application for condonation of delay
should not be dealt with in a routine manner on the basis
of individual philosophy which is basically subjective.
The increasing tendency to perceive delay as a non-
serious matter and, hence, lackadaisical propensity can
be exhibited in a nonchalant manner requires to be
curbed, of course, within legal parameters.
16) In Postmaster General and Ors. vs. Living Media
India Limited and anr. reported in , [ 4(2012) 3 SCC 563],
the Hon'ble Supreme Court declined to condone the delay
of 427 days in filing the special leave petition by
observing that department cannot take advantage of
various earlier decisions where a very liberal approach
was adopted when it came to condone delay on the part of
Government agencies. The Hon'ble Supreme Court observed
that the claim on account of impersonal machinery and
( 15 ) 33-CA 15408 of 2017 & Ors.
inherited bureaucratic methodology of making several
notes cannot be accepted in view of the modern
technologies being used and available. The law of
limitation undoubtedly binds everybody including the
Government. It is the right time to inform all the
government bodies, their agencies and instrumentalities
that unless they have reasonable and acceptable
explanation for the delay and there was bonafide effort,
there is no need to accept the usual explanation that the
file was kept pending for several months/years due to
considerable degree of procedural red-tape in the
process. The government departments are under a special
obligation to ensure that they perform their duties with
diligence and commitment. Condonation of delay is an
exception and should not be used as an anticipated
benefit for government department. The law shelters
everyone under the same light and should not be swirled
for the benefit of a few. Considering the fact that
there was no proper explanation offered by the Department
( 16 ) 33-CA 15408 of 2017 & Ors.
for the delay except mentioning of various dates, the
Hon'ble Supreme Court held that, the Department has
miserably failed to give any acceptable and cogent
reasons sufficient to condone such a huge delay.
17) In Basawaraj and anr. vs. Special Land Acquisition
(2013) 14 SCC 81] the Hon'ble Officer, reported in [
Supreme Court went on to observe that the law on the
issue can be summarised to the effect that where a case
has been presented in the court beyond limitation, the
applicant has to explain the court as to what was the
"sufficient cause" which means an adequate and enough
reason which prevented him to approach the court within
limitation. In case a party is found to be negligent, or
for want of bona fide on his part in the facts and
circumstances of the case, or found to have not acted
diligently or remained inactive, there cannot be a
justified ground to condone the delay. No court could be
justified in condoning such an inordinate delay by
( 17 ) 33-CA 15408 of 2017 & Ors.
imposing any condition whatsoever. The application is to
be decided only within the parameters laid down by this
Court in regard to the condonation of delay. In case
there was no sufficient cause to prevent a litigant to
approach the court on time condoning the delay without
any justification, putting any condition whatsoever,
amounts to passing an order in violation of the statutory
provisions and it tantamounts to showing utter disregard
to the legislature.
18) The Division Bench of this Court in State of
Maharashtra and ors. vs. Vithu Kalya Govari and ors.,
reported in [ 2008(6) Mh.L.J.239] has observed that the
State is not expected to be negligent or to take no
action for years and let the matters become time barred
on account of its negligence and inaction. The usual
reason of "official hassle" or "approval at different
levels" is hardly sufficient to justify condonation of
delay of about two years. In law, advantage has accrued
( 18 ) 33-CA 15408 of 2017 & Ors.
to the non-applicants claimants and the same cannot be
withdrawn in a mechanical manner and that too without any
sufficient cause being shown by the applicants. Despite,
awards/judgments of the Courts, which have attained
finality, the claimants are not permitted to receive
compensation in respect of their lands, which came to be
compulsorily acquired, is itself, sufficient prejudice to
them. Therefore, before any delay can be condoned and
the claimants subjected to further prolonged litigation,
the onus to show sufficient cause lies upon the
applicant-State.
19) Applying the aforesaid principles to the facts of
the present case, it will not be proper to indulge the
applicants and condone delay of four or five years in
instituting these appeals, particularly, when no
sufficient cause has been shown.
20) For the aforesaid reasons, these civil applications
( 19 ) 33-CA 15408 of 2017 & Ors.
are dismissed. There shall be no order as to costs. As
a consequence of dismissal of civil applications, the
appeals and civil applications seeking stay also stand
disposed of.
[M.S.SONAK, J.]
SPT/33-CA 15408 of 2017 & Ors.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!