Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Western Coalfields Ltd., Through ... vs P.G. Gupta, Prop. Machine India, ...
2018 Latest Caselaw 311 Bom

Citation : 2018 Latest Caselaw 311 Bom
Judgement Date : 11 January, 2018

Bombay High Court
Western Coalfields Ltd., Through ... vs P.G. Gupta, Prop. Machine India, ... on 11 January, 2018
Bench: Z.A. Haq
                                               1                   aa13.2013.odt

          IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                    NAGPUR BENCH, NAGPUR

                     ARBITRATION APPEAL NO. 13/2013

 1] Western Coalfields Ltd. 
    Through Chairman cum Managing
    Director, Coal Estate, Civil Lines, 
    Nagpur

 2] Chief Engineer (Civil)
    Western Coalfields Ltd.,
    Coal Estate, Civil Lines, 
    Nagpur

 3] Dy. Chief Engineer (Civil), 
    Western Coalfields Ltd., 
    Kanhan Area, Dongariya,
    Distt. Chhindwara (M.P.)                        ... APPELLANTS


                               ...V E R S U S...

 1] P.C. Gupta, 
    R/o. 3-A Onkar Apartment,
    Opp. Govind Gaurkhed Complex,
    Hajari Pahad, Seminary Hills,
    Nagpur- 440 006

       (Address of Respondent no. 1
       amended as per Courts
       order dated 08/05/2014)

 2] A.G. Watwe, Sole Arbitrator, 
    43-A, Shivaji Nagar, 
    Hill Road, Nagpur                               ... RESPONDENTS




::: Uploaded on - 16/01/2018                       ::: Downloaded on - 17/01/2018 01:22:14 :::
                                               2                     aa13.2013.odt


 ===================================
       Shri S.C. Mehadia, Advocate for the petitioners
       Shri R. Joshi, Advocate for the respondent no. 1
 ===================================

                                         CORAM:- Z.A. HAQ,J.

th DATED :- 11 JANUARY, 2018

ORAL JUDGMENT :-

As the appeal is pending since 2013, record and

proceedings are received and the learned advocates for the

respective parties have shown willingness to argue the matter, the

appeal is taken up for hearing.

Heard.

Admit.

2] The respondent no. 1 had approached this Court under

Section 11 of the Arbitration and Conciliation Act, 1996

(hereinafter referred as " the Act of 1996") contending that though

he had completed the work, the present appellants had not made

the payment and as there was a clause providing that the dispute

between the parties has to be resolved by an arbitrator, an

arbitrator be appointed in the matter. Then Hon'ble Chief Justice,

by order dated 14/08/1998 appointed an arbitrator to resolve the

3 aa13.2013.odt

dispute between the parties. At the time when arbitrator was to be

appointed, the present appellants had raised an objection that the

claim of the present respondent no. 1 is barred by limitation.

While appointing the arbitrator, the issue of limitation was kept

open to be considered by the learned Arbitrator.

The learned Arbitrator passed an award on 27/08/2007

accepting the objection raised by the present appellants that the

claim made by the present respondent no. 1 was barred by

limitation. The present respondent no. 1 had approached the

District Court under Section 34 of the Act of 1996 praying that the

award be set aside and the claim made by the present respondent

no. 1 be decreed. By the impugned order, the learned Principal

District Judge allowed the application filed by the present

respondent no. 1 under Section 34 of the Act of 1996, held that

the claim made by the present respondents was within limitation,

set aside the award dated 27/08/2007 and remanded the matter

to the arbitrator for considering the claim of the present

respondents afresh. Being aggrieved by this order, the appellants

have filed this appeal.

                                                  4                      aa13.2013.odt

 3]             The learned advocate for the appellants has submitted 

that the work was admittedly completed on 30/11/1991 and as

per the terms of agreement, the payment was to be made to the

respondent no. 1 within six months i.e. till 30/05/1992, and the

notice under Section 21 of the Act of 1996 was given by the

respondent no. 1 on 12/01/1996 i.e. beyond the period of three

years from 30/05/1995 and therefore the claim of the respondent

no. 1 is time barred. It is submitted that the learned Principal

District Judge has committed an error by holding that the claim of

the present respondent no. 1 is within limitation, being misled by

the fact that the letter dated 13/09/1995 was issued by the

Deputy Chief Engineer (Civil) which according to the learned

Principal District Judge amounts to acceptance that the claim of

the present respondent no. 1 was under consideration and was

alive on that date and it being so, the claim made by the present

respondent no. 1 by notice dated 12/01/1996 was within

limitation.

4] The learned advocate for the respondent no. 1 has

submitted that the appellants had not prepared the final bill within

six months and therefore the appellants cannot contend that the

5 aa13.2013.odt

limitation started to run from 01/06/1992. Supporting the

conclusions of the learned Principal District Judge, the advocate

for the respondent no. 1 has pointed out that by letter dated

19/08/1995, the Deputy Chief Engineer (Civil) informed the

respondent no. 1 that the approval to final extension of time to

complete the work upto 30/11/1991 was granted subject to token

penalty of Rs. 2,000/-, and this shows that till 19/08/1995, the

claim of the present respondent no. 1 was under consideration by

the appellants and was alive, and considering the facts of the case,

it has to be held that the notice issued by the respondent no. 1

under Section 21 of the Act of 1996 on 12/01/1996 was within

limitation. To support the submission, reliance is placed on the

following judgments:-

a) The judgment given by the Hon'ble Supreme Court in the case of Major (Retd.) Inder Singh Rekhi vs Delhi Development Authority reported in AIR 1988 S.C. at page 1007.

b) The judgment given by this Court in the case of R.P. Souza and Co., Goa and others vs Chief Engineer, P.W.D., Panaji, Goa and others reported in 2000 (1) Mh.L.J at page

558.

                                                  6                       aa13.2013.odt

            c)    The judgment given  by the Hon'ble Supreme Court in 

the case of National Aluminium Co. Ltd. & Anr. Vs G.C. Kanungo reported in AIR 2009 S.C. at page 2928.

In the case of R.P. Souza and Co., Goa and others

(supra), the claim raised by the claimant was held to be within

limitation as it was filed within three years of the preparation of

the final bill. In the present case, the final bill is not prepared. It

would have been a different thing if the final bill was prepared

after 01/06/1995 and the respondent no. 1 raised the dispute

within three years of preparation of the final bill.

In the case of Major (Retd.) Inder Singh Rekhi (supra),

the facts recorded in para 2 of the judgment show that the work

was completed on 02/04/1980, the claimant had sent a letter

dated 28/02/1983 to the Delhi Development Authority, requesting

to finalise the bills, and as this letter was sent within the period of

limitation, i.e. three years, treating that the cause of action had

arisen on 28/02/1983, the application filed under Section 20 of

the Arbitration Act, 1940 in January, 1986 i.e. within three years

from 28/02/1983 was considered to be within the prescribed

period. In the present case, the first communication by the

respondent no. 1 is on 10/12/1995 which was beyond the period

7 aa13.2013.odt

of limitation, calculating it from 01/06/1992 on which date the

cause of action had arisen as the claim of the respondent no. 1 is

not based on the final bill but is based on the fact that he had

completed the work on 30/11/1991 and according to the

agreement, the payment was required to be made within six

months.

In the judgment given in the case of National

Aluminium Co. Ltd. & Anr.(supra), the final bill was paid by the

company to the claimant in 1989, on 26/08/1992, the company

had sent a letter to the claimant which shows that the company

was considering the claim of the claimant regarding the difference

of amounts, and the request for appointment of an arbitrator was

made on 26/06/1995 i.e. within three years from 26/08/1992.

The claim of the claimant was found to be within limitation as the

company informed the claimant within three years from the

payment of the final bill that the request of the claimant for the

amount of difference was under consideration and then the

request for appointment of an arbitrator was made within three

years from 26/08/1992. In the present case, there is nothing on

record to show that from 01/06/1992 till 31/05/1995, there was

any communication by the appellants to the respondent no. 1

8 aa13.2013.odt

informing him that the claim of the respondent no. 1 was under

consideration. The respondent no. 1 issued first communication

on 10/12/1995 which is beyond three years. The communication

dated 19/08/1995 issued by the Deputy Chief Engineer (Civil) on

which the advocate for the respondent no. 1 relies to contend that

the claim of the respondent no. 1 was under consideration also

does not help the respondent no. 1 as this communication dated

19/08/1995 is issued after the prescribed period of limitation and

in view of Section 18 of the Limitation Act, 1963, the respondent

no. 1 cannot rely on it.

5] Considering the facts of the case, I hold that the

respondent no. 1 made the claim and sought appointment of an

arbitrator after the prescribed period of limitation. The learned

Arbitrator had rightly rejected the claim of the respondent no. 1 as

time barred. The order passed by the learned Principal District

Judge is unsustainable and has to be set aside.

Hence, the following order is passed:-

                                                 9                      aa13.2013.odt

                                           O R D E R

                   1]            The impugned order is set aside. 



                   2]            The   application   filed   by   the   respondent 

                   no.   1   under   Section   34   of   the   Act   of   1996   is 

                   dismissed. 



                   3]            The   award   passed   by   the   arbitrator   on 

                   27/08/2007 is restored. 



The appeal is allowed in the above terms. In the

circumstances, the parties to bear their own costs.

JUDGE

Ansari

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter