Citation : 2018 Latest Caselaw 1073 Bom
Judgement Date : 29 January, 2018
26-J-CRA-81,82-16 1/8
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL REVISION APPLICATION NO.81 OF 2016
Pravin s/o Madhukar Thakare
Aged about 35 years, Occ. Agriculturist,
R/o Belora, PO: Dhamak, Tq. Nandgaon (Kh),
Dist. Amravati ... Appellant
-vs-
1. The State of Maharashtra,
Represented by the Collector,
Amravati, Dist. Amravati.
2. Land Acquisition Officer,
Upper Wardha Project No.4,
Amravati, Dist. Amravati.
3. Executive Engineer,
Bemble Project Office, Yavatmal,
Dist. Yavatmal ... Respondents.
WITH
CIVIL REVISION APPLICATION NO.82 OF 2016
Madhukar s/o Tukaram Thakare
Aged about 65 years, Occ. Agriculturist,
R/o Belora, PO: Dhamak, Tq. Nandgaon (Kh),
Dist. Amravati ... Appellant
-vs-
1. The State of Maharashtra,
Represented by the Collector,
Amravati, Dist. Amravati.
2. Land Acquisition Officer,
Upper Wardha Project No.4,
::: Uploaded on - 14/02/2018 ::: Downloaded on - 21/05/2018 01:59:42 :::
26-J-CRA-81,82-16 2/8
Amravati, Dist. Amravati.
3. Executive Engineer,
Bemble Project Office, Yavatmal,
Dist. Yavatmal ... Respondents.
Shri Shrikant Saoji, Advocate for applicants.
Ms Geeta Tiwari, Assistant Government Pleader for non-applicant Nos.1 & 2.
Shri M. A. Kadu, Advocate for non-applicant No.3.
CORAM : A. S. CHANDURKAR, J.
DATE : January 29, 2018.
Common Judgment :
The land of the applicants came to be acquired pursuant to proceedings
initiated under Land Acquisition Act, 1894 (for short, the said Act). The
award came to be passed on 10/05/2004. The applicants not being satisfied
with the amount of compensation filed proceedings under Section 18 of the
said Act on 07/08/2004. The reference proceedings came to be dismissed on
the ground that the same were barred by limitation. This order is under
challenge in these civil revision applications.
2. Shri S. Saoji, learned counsel for the applicants submitted that an
identical challenge was raised in Civil Revision Application No.84/2016 and
this Court by judgment dated 17/07/2017 though held that the order
refusing to condone delay by the Reference Court was legally correct, the
proceedings are remanded to the reference Court for deciding the same
afresh with the condition that the claimant would not be entitled for interest
26-J-CRA-81,82-16 3/8
from the date of the award till the date of decision of civil revision
application. It is further submitted that notice calling upon the applicants to
collect the amount of compensation was received on 02/08/2004 and
therefore the reference proceedings were filed within limitation. It was
submitted that no written statement was filed by the non-applicants and
therefore the reference Court committed an error in treating the proceedings
to be barred by limitation.
3. Ms Geeta Tiwari, learned Assistant Government Pleader for non-
applicant Nos.1 and 2 and Shri M.A. Kadu, learned counsel for non-applicant
No.3 opposed the aforesaid submissions. According to them if the reference
proceedings are barred by limitation, there is no power with the reference
Court or this Court to condone the delay. It was further submitted that the
applicant in his deposition admitted that the notice was received on
21/06/2004 and therefore the reference proceedings were barred by
limitation. It was not the case of the applicants that the copy of the award
was not forwarded along with said notice. It is therefore submitted that the
revision applications deserve to be dismissed.
4. Heard the respective counsel. The reference Court has recorded a
finding that the applicant in his cross-examination admitted that notice
under Section 12(2) of the said Act was received on 21/06/2004. On that
26-J-CRA-81,82-16 4/8
premise it was held that proceedings filed under Section 18 of the said Act
were beyond time. In the application for reference it is not the case that a
copy of the award was not supplied to the applicant along with the notice
issued under Section 12(2) of the said Act. This fact has also been noted and
considered in Shankar s/o Govindrao Deulkar vs. The State of
Maharashtra and ors. 2018(1) Mh.L.J. 633. On that count I do not find
that the reference Court committed any error in dismissing the reference
proceedings.
5. It was then submitted by the learned counsel for the applicants
that the reference proceedings be directed to be decided on merits by
requiring the applicants to give up interest from the date of the award till
today. Such course was followed in Shankar s/o Govindrao Deulkar
(supra).
6. Perusal of paragraphs 17 and 18 of the judgment in Shankar
Govindrao Deulkar (supra) indicates that the order of the Reference Court
dismissing the reference as being barred by limitation has been upheld.
Thereafter, in view of the judgment in Imratlal and ors. vs. Land
Acquisition Officer (2014) 14 SCC 133 a direction has been issued to decide
the reference proceedings on merits subject to the claimant not being entitled
for interest on the amount of compensation enhanced by the Reference
26-J-CRA-81,82-16 5/8
Court. The question therefore is after finding the reference proceedings to be
barred by limitation whether the reference Court can be directed to decide
the same under Section 18 of the said Act.
7. The issue as to whether the Collector acts as a statutory authority
or as a "Court" while making a reference under Section 18(1) of the said Act
was considered by the Honourable Supreme Court in Officer on Special
Duty (Land Acquisition) and anr. vs. Shah Manilal Chandulal Etc.
1996(1) Mh.L.J. 609. Holding that the Collector does not act as a "Court"
while making a reference under Section 18(1) of the said Act it observed in
paragraphs 9 and 18 as under :
" 9. It would thus be clear that one of the conditions precedent to make a valid reference to the court is that the application under Section 18(1) shall be in writing and made within six weeks from the date of the award when the applicant was present either in person or through counsel, at the time of making of the award by the Collector under clause (a) of proviso to sub-section (2).
18. Though hard it may be, in view of the specific limitation provided under proviso to Section 18(2) of the Act, we are of the considered view that sub-section (2) of Section 29 cannot be applied to the proviso to sub- section (2) of Section 18. The Collector/LAO, therefore, is not a court when he acts as a statutory authority under Section 18(1). Therefore, Section 5 of the Limitation Act cannot be applied for extension of the period of limitation prescribed under proviso to sub-section (2) of Section
18....."
26-J-CRA-81,82-16 6/8
Thus from the aforesaid decision it is clear that for the purposes of
making a valid reference the application under Section 18(1) of the said Act
should be made within the time prescribed. The provisions of Section 5 of
the Limitation Act, 1963 cannot be applied for extending the period of
limitation prescribed under proviso to Section 18(2) of the said Act. When
the period for making a reference cannot be extended by the Collector and
the provisions of Section 5 of the Limitation Act, 1963 cannot be resorted to,
it is obvious that even the Court cannot extend that period. In other words
the delay in filing the reference proceedings cannot be condoned. If the
delay in filing reference proceedings cannot be condoned, it is obvious that
the Reference Court would not have any jurisdiction to consider any
reference that is time barred. In Damodaran Pillai and ors. vs. South
Indian Bank Ltd. (2005) 7 SCC 300, it has been held that in the absence of
applicability of the provisions of Section 5 of the Limitation Act, 1963 the
Court cannot invoke any inherent power. In such situation, hardship or
injustice cannot be a ground for extending the period of limitation.
8. The directions issued in Shankar Govindrao Deulkar (supra) by
which the Reference Court has been called upon to decide the reference
proceedings despite the same being barred by limitation amounts to
conferring jurisdiction on the Reference Court which it does not possess. It
would amount to doing something indirectly that which cannot be done
26-J-CRA-81,82-16 7/8
directly. Hence the direction to the Reference Court to entertain the time
barred reference proceedings as issued in the aforesaid decision cannot be
followed being contrary to the law referred to above.
9. In Imratlal and ors. (supra) the question was with regard to
condonation of delay in filing the appeal under Section 54 of the said Act. It
cannot be disputed that for the purposes of condoning delay for filing appeal
under Section 54 of the said Act the provisions of Section 5 of the Limitation
Act, 1963 are applicable. However, when the delay in filing the reference
proceedings cannot be condoned, there would be no question of directing the
Reference Court to decide a belated reference by requiring the applicant to
forgo the amount of statutory interest.
The Honourable Supreme Court in Government of W.B. vs.
Tarun K. Roy and ors. (2004) 1 SCC 347 has observed that an order passed
in ignorance of an earlier binding precedent by itself would not constitute a
binding precedent and can be held to have been rendered per incuriam. With
respect, the directions issued in Shankar Govindrao Deulkar to the
Reference Court to entertain the reference proceedings despite the same
being barred by limitation are against the ratio of the decision in Officer on
Special Duty (Land Acquisition) and anr. (supra). For said reason the
directions to that effect in Shankar Govindrao Deulkar (supra) cannot be
followed.
26-J-CRA-81,82-16 8/8
10. As the reference proceedings have been found to be barred by
limitation there is no reason to interfere with the order of the Reference
Court. Civil Revision Applications are therefore dismissed with no order as
to costs.
JUDGE
Asmita
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!