Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sachin Ananda Patil And Others vs The State Of Maharashtra And ...
2017 Latest Caselaw 170 Bom

Citation : 2017 Latest Caselaw 170 Bom
Judgement Date : 1 March, 2017

Bombay High Court
Sachin Ananda Patil And Others vs The State Of Maharashtra And ... on 1 March, 2017
Bench: T.V. Nalawade
             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                        BENCH AT AURANGABAD

                        WRIT PETITION NO. 9941 OF 2016

1.     Sachin s/o Ananda Patil,
       Age : 30 years, Occu.: Agri.,

2.     Bhagwan s/o Sahebrao Badgujar,
       Age : 50 years, Occu.: Agri.,

3.     Atmaram s/o Kukudu Patil,
       Age : 55 years, Occu.: Agri.,

4.     Bhagwan s/o Jagannath Patil,
       Age : 58 years, Occu.: Agri.,

5.     Rajdhar s/o Ramdas Badgujar,
       Age : 70 years, Occu.: Agri,

6.     Sambhaji s/o Devidas Patil,
       Age : 29 years, Occu.: Agri.,

7.     Bhagwat s/o Tulshiram Patil,
       Age : 40 years, Occu.: Agri.,

8.     Ramdas s/o Sambhu Patil,
       Age : 72 years, Occu.: Agri.,

9.     Maharu s/o Chaitraram Patil,
       Age : 50 years, Occu.: Agri.,

10. Fulchand s/o Mahadu Patil,
    Age : 52 years, Occu.: Agri.,

       All r/o. Samaner, Tq. Pachora,
       District Jalgaon                                  ..PETITIONERS

       VERSUS

1.     The State of Maharashtra,
       Through District Collector,
       Jalgaon, District Jalgaon

2.     The Special Land Acquisition Officer,
       Jalgaon (3) Upper Tapi Project,
       Hatnoor, District Jalgaon




     ::: Uploaded on - 01/03/2017            ::: Downloaded on - 02/03/2017 01:07:57 :::
                                          2                            wp9941-2016




3.     The Executive Engineer,
       Building and Construction
       (P.W.D.) Department, Jalgaon
       District Jalgaon

4.     The Desk Officer (Road-3),
       Building and Construction 
       Department, Mantralaya,
       Mumbai - 32                                         ..RESPONDENTS
        

                          ----
Mr. P.B. Rakhunde, Advocate for the Petitioners
Smt.A.V.Gondhalekar, A.G.P. for the respondents/State 
                          ----

                                    CORAM  :  T.V. NALAWADE AND
                                              SANGITRAO S. PATIL, JJ.

                       Reserved On  :  27th FEBRUARY, 2017
                       Pronounced On:  1st  MARCH, 2017


JUDGMENT (PER : SANGITRAO S. PATIL, J.) :

Rule, returnable forthwith. With the consent of

the learned counsel for the petitioners and the learned

A.G.P. representing the respondents, heard finally.

2. The admitted facts, in brief, are that the

lands of the petitioners came to be acquired by

respondent no.3 - Executive Engineer, Building and

Construction (P.W.) Department, Jalgaon, for

construction of a bridge at village Samner, Taluka

3 wp9941-2016

Pachora, District Jalgaon, on Jalgaon to Pachora Road.

Possession of the lands of the petitioners was taken by

private negotiations on 12.06.1997. However, the notice

under Section 4 (1) of the Land Acquisition Act, 1894

("the Act of 1894", for short) was issued on 11.01.2013.

The declaration under Section 6 of the Act of 1894 was

made on 26.02.2013. The public notice under Section 9(1)

and (2) was given on 24.05.2013. The Award under Section

11 of the Act of 1894 came to be passed on 05.12.2013,

however, the amount of compensation was not paid to the

petitioners. Therefore, the petitioners filed Writ

Petition No.8495 of 2015, seeking directions against

respondent nos.2 and 3 to pay compensation to them. This

Court passed an order on 16.12.2015 and directed the

said respondents to deposit the amount payable to the

petitioners under the Award dated 05.12.2013, together

with interest and other benefits in this Court, within a

period of eight weeks from the date of the said Award.

Accordingly, the said respondents deposited amount of

compensation payable to the petitioners in this Court,

which was ultimately received by them on 04.03.2016.

3. According to the learned Counsel for the

4 wp9941-2016

petitioners, since the amount of compensation was not

paid to the petitioners on or before the date of

commencement (i.e. 01.01.2014) of the Right to Fair

Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013 ("the Act of

2013", for short), in view of the proviso given under

sub-section (2) of Section 24 of the Act of 2013, the

petitioners are entitled to get compensation as per the

provisions of the Act of 2013. In support of this

contention, he placed reliance on the decision in the

case of Pune Municipal Corporation and Another vs.

Harakchand Misrimal Solanki and others, 2014 (4) Mh.L.J,

(S.C.) 566 = (2014) 3 SCC 183.

4. On the other hand, the learned A.G.P., relying

on the contentions raised in the reply filed on behalf

of respondent no.2- Special Land Acquisition Officer,

submits that since the Award in respect of lands of the

petitioners has not been passed under Section 11 of the

Act of 1894, five years or more prior to the

commencement of the Act of 2013 and since possession of

the lands of the petitioners has been taken in the year

1997 and the amount of compensation also has been paid

5 wp9941-2016

to them, the proviso under sub-section (2) of Section 24

of the Act of 2013 would not apply to the facts of the

present petition and petitioners would not be entitled

to get compensation in accordance with the provisions of

the Act of 2013. The learned A.G.P. relying on the

judgment in the case of Babasaheb Eknath Wakchaure and

others vs. The State of Maharashtra and others, 2017(1)

Mh.L.J. 925, prays that the Writ Petition may be

dismissed.

5. We have considered the rival contentions of the

parties with reference to the documents produced on

record. In our opinion, the issue involved in this

petition is no more res integra, in view of the Full

Bench judgment of the Nagpur Bench of this Court in

Dayaram Bhondu Koche and others vs. The State of

Maharashtra and others, 2017(1) Mh.L.J. 487, wherein the

following question was framed for consideration;

"Whether proviso to Section 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 is also applicable to the Awards which are covered under Clause (b) of sub- section (1) of Section 24 of the 2013?".

6 wp9941-2016

After considering the rival contentions of the parties,

this Court answered the above referred question in the

following words:-

"For the reasons to follow, we answer the question by holding that the proviso to section 24 of the 2013 Act is also applicable to the awards which are covered under clause (b) of sub-section (1) of section 24 of the 2013 Act. Resultantly, we hold that all such beneficiaries, whose names are specified in notification under section 4 of the Land Acquisition Act, 1894 and in case of which the awards have been passed within a period of five years prior to the date of commencement of the 2013 Act and wherein the compensation as construed by the Hon'ble Supreme Court in the case of Pune Municipal Corporation and Another vs. Harakchand Misrimal Solanki and others, 2014(4) Mh.L.J. (S.C.) 566 = (2014) 3 SCC 183, is not paid to the majority of the beneficiaries would also be entitled to the compensation as per the 2013 Act."

6. Here, reference may conveniently be made to the

judgment in the case of Dilip Narayan Chaudhari & Ors.

Vs. State of Maharashtra, Water Resources Department &

Ors., 2016 (1) LJSOFT 71 = 2016 (3) ALL MR 890, wherein

the facts were that the Award under Section 11 of the

7 wp9941-2016

Act of 1894 was passed on 17.07.2013, the possession of

the lands subject matter of the Award was not taken over

by the acquiring body. The majority of the petitioners

therein had not been paid the amount of compensation.

Therefore, the petitioners therein had claimed that in

view of the provisions of Section 24 (2) of the Act of

2013, the acquisition proceedings should be deemed to

have lapsed. This Court considered the rival contentions

in detail with reference to the provisions of Section 24

of the Act of 2013 and held that the acquisition

proceedings would not be deemed to have lapsed and the

petitioners would be entitled to get compensation in

accordance with the provisions of the Act of 2013. This

Court observed in para 31 as under:

"31. .... ........

In view of the recent pronouncement of the Hon'ble Supreme Court, as quoted above, the argument advanced by learned Assistant Government Pleader that the scope of proviso shall have to be read in the context of sub- section (2) of Section 24; and that it applies only in a case where award has been declared five years or more prior to the enforcement of Act of 2013, is not a sound proposition. As has been held by the Hon'ble

8 wp9941-2016

the Supreme Court, the proviso has no effect so as to exclude from main enactment by implication, which clearly falls within its express terms and as such, contention of the State that the proviso shall have to be read as excepting something out of the provisions of sub-section (2) of Section 24, does not deserve acceptance. Considering the language of the proviso, it has to be construed as a stand alone proviso independent of sub- section (2) of Section 24 of the Act of 2013."

7. In the present case, though possession of the

lands of the petitioners was taken in the year 1997, the

amount of compensation was not paid to them as

contemplated by the Hon'ble Apex Court in the case of

Pune Municipal Corporation and Another (supra), on or

prior to commencement of the Act of 2013, the subsequent

payment to the petitioners on 04.03.2016, would have no

adverse affect on the right of the petitioners to claim

compensation in accordance with the provisions of the

Act of 2013.

8. The judgment in the case of Babasaheb Eknath

Wakchaure and others (supra), cited by the learned

9 wp9941-2016

A.G.P. has no bearing at all on the facts of the present

case. Since the Award in that case was passed on

10.03.1997, in that case ultimately this Court held and

declared that the land acquisition proceedings in

respect of the lands of the petitioners therein stood

lapsed. This judgment is of no help to the respondents

to deny the claim of the petitioners.

9. In the result, we pass the following order.

O R D E R

(i) The respondents are directed to determine and

pay the amount of compensation with interest, as

admissible under the law, to the petitioners in

accordance with the provisions of the Right to Fair

Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013, within a

period of six months from today.

(ii) The amount of compensation that has already

been paid to the petitioners shall be adjusted towards

the amount payable to them in accordance with the

provisions of the Act of 2013.

                                       10                              wp9941-2016




(iii)          Rule   is   made   absolute   in   the   above   terms   and

the Writ Petition is disposed of accordingly.

              Sd/-                                      Sd/-
      [SANGITRAO S. PATIL]                       [T.V. NALAWADE]
             JUDGE                                     JUDGE



mandawgad_sa/wp9941-2016





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter