Citation : 2017 Latest Caselaw 4243 Bom
Judgement Date : 10 July, 2017
1.arbp.46.17.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO. 46 OF 2017
M/s Surya Construction
(through its POA Shri Akhilesh J. Singh) ..Petitioner
Vs.
Steel Authority of India Ltd
(through its Asst.General Manager) ..Respondent
Mr. Abhijeet Desai i/b Mr. A. M. Savgave, for the Petitioners
Mr.Hiren Kamod a/w Mr. Abhishek Adke, Mr. Siddharth Mathur
i/b Zunzarrao and Co, for the Respondent.
CORAM :- B. P. COLABAWALLA , J.
DATE :- JULY 10, 2017.
ORAL JUDGMENT(PER B. P. COLABAWALLA,J.)
Admit. By consent of parties, taken up for hearing
and final disposal.
2 By this Arbitration Petition filed under Section 34 of
the Arbitration and Conciliation Act, 1996 (for short "the Act")
the Petitioner challenges the impugned Award dated 19th June,
2016 passed by the Arbitral Tribunal to the extent that the
Aswale 1/17
1.arbp.46.17.doc
Arbitral Tribunal rejected the claim of the Petitioner as more
particularly set out in Exhibit A-1 to the Petition. The claims that
were rejected by the Arbitral Tribunal were under two heads. The
first head was for claim of less supply (calculated at 80% of
Estimated Quantity in 33 months) for an amount of Rs.
80,88,015/-. In the alternative, a claim was made for
reimbursement / recovery of unrecovered expenses / costs in the
amount of Rs.99,04,779/-. It is these two claims that were
rejected by the Arbitral Tribunal and hence the present Petition.
3 The brief facts are as under:-
The Petitioner is a Proprietary concern of one Shri
Akhilesh J. Singh. The Respondent is the Steel Authority of India
Limited and which according to the Petitioner is a Government of
India undertaking engaged in the production, distribution and
marketing of steel throughout the country. It manufactures
variety of Iron and Steel products.
4 In/about November, 2007, the Respondent floated a
tender dated 12th November, 2007 inviting offers from the public
for operating a Consignment Agency Yard at Silvassa, Dadra and
Nagar Haveli. According to the Petitioner, it was the sole Bidder
Aswale 2/17
1.arbp.46.17.doc
and quoted a rate of Rs.1,000 per metric tons for its services
under the contract.
5 It is the case of the Petitioner that thereafter the
Respondent called the Petitioner for negotiations wherein the
Respondent informed the Petitioner that the estimated quantity of
supply of Steel was mentioned in the tender document. It is the
case of the Petitioner that the Respondent assured him that the
Respondent was expecting good business and will make all efforts
to ensure that the estimated quantity of Steel as mentioned in the
tender documents would be adhered to. After these negotiations,
the parties agreed that the rate at which the Petitioner would be
paid was Rs. 550 per metric ton inter alia for the purposes of
storage of the Steel that was to be supplied by the Respondent.
6 Accordingly, the Respondent issued a Letter of Intent
on 30th January, 2008 wherein, according to the Petitioner it was
mentioned that the estimated quantity of Steel to be supplied was
10,800 metric tons per year. Thereafter, the Respondent issued a
work order on 3rd November, 2008 and parties signed the
agreement on the same day. Pursuant to this agreement, the
Petitioner was appointed as a Consignment Agent for the period of
Aswale 3/17
1.arbp.46.17.doc
2 ½ years i.e. up to 2nd May, 2011. It is the case of the Petitioner
that to honour its commitments under the contract, it made huge
investments of approximately Rs. 30,00,000/- up to 3rd
November, 2008 and also availed of a cash credit facility from
State Bank of Indore. Over and above this, the Petitioner also
incurred monthly expenses of Rs. 3,00,000/- to employ different
persons.
7 It is thereafter averred in the Petition that due to
supply of stock (of Steel) being much below the quantity that had
been estimated during the negotiations (10,800 metric tons per
year), the Petitioner repeatedly approached officers of the
Respondent regarding the same but got no response. Thereafter,
in the year 2010, the Petitioner submitted a comparative
statement to the Director (Commercial) of the Respondent
bringing these facts to his notice. Despite this, there was no
response, and therefore, the Petitioner vide its notice dated 19th
July, 2012 invoked Rules of Conciliation as per the contract. The
Petitioner forwarded a claim of Rs. 1,33,95,686/- before the
Conciliator. This conciliation failed and thereafter vide its letter
dated 2nd June, 2014, the Petitioner made a reference for
Aswale 4/17
1.arbp.46.17.doc
resolution of the disputes by arbitration under SCOPE Rules.
8 In the arbitration, on 15th August, 2014, the
Petitioner filed his Statement of Claim seeking an amount of
Rs.2,68,57,051/- from the Respondent. To this Statement of
Claim, the Respondent filed its Written Statement. On the basis of
these pleading, the Petitioner led his evidence before the Arbitral
Tribunal. The Respondent chose not to lead any evidence. On the
basis of the pleadings before the Arbitral Tribunal, and the
evidence led, the Arbitral Tribunal after hearing the respective
parties, passed the impugned award dated 19th September, 2016.
The Arbitral Tribunal ruled that the Petitioner was entitled to Rs.
4,99,385/- and interest thereon at the rate of 8% per annum with
effect from 1st September, 2011 till the date of Award. This
amount was in relation to certain amount that the Respondent
had deducted on account of excess and shortage. The Arbitral
Tribunal also ruled that the Petitioner is entitled to interest at the
rate of 8% per annum on Rs. 56,079/- (balance amount under 1st
escalation not paid in time) with effect from 2nd November, 2010
and on Rs. 73,587/- (balance amount under 2nd escalation not
paid in time) with effect from 1st August, 2011 till the date of
Aswale 5/17
1.arbp.46.17.doc
Award. Over and above this, the Arbitral Tribunal also awarded
costs of Rs.1,00,000/- in favour of the Petitioner. As far as the
claims for less supply is concerned, as well as for reimbursement /
recovery of unrecovered expenses, the Arbitral Tribunal did not
grant these claims inter alia on the basis of certain clauses in
tender document. The reasoning of the Arbitral Tribunal for
denying these aforesaid two claims can be found from paragraphs
62 to 69 of the impugned Award.
9 Being aggrieved by this part of the Award which
negates the claim of the Petitioner with reference to these two
claims, it is before me under Section 34 of the Act.
10 In this factual backdrop, Mr. Desai, the learned
counsel appearing on behalf of the Petitioner submitted that the
Award suffers from a patent illegality and is contrary to the public
policy of India. He submitted that the learned Arbitral Tribunal
has refused these two claims of the Petitioner solely on the basis of
Clauses 3.5 and 5.12 of the tender document. Mr.Desai submitted
that the Arbitral Tribunal has put a very narrow construction on
the interpretation of these clauses and has not taken into
Aswale 6/17
1.arbp.46.17.doc
consideration the other terms of the contract, namely, Clauses 2.1,
2.2 (D) and 3 which deal with Schedule of Operations as well as
Clause 8 which deal with Declarations. He submitted that on
reading the contract as a whole, it was clear that it was a binding
obligation on the part of the Respondent to supply 10,800 metric
tons per year as agreed between the parties. This evidence has
not even been considered by the Arbitral Tribunal, was the
submission of Mr. Desai.
11 In addition to the aforesaid argument, Mr. Desai
submitted that Clauses 3.5 and 5.12 are in the nature of a negative
covenant. He submitted that the Respondent being a Government
of India undertaking was in dominant position as far as the
Petitioner was concerned. These clauses in the contract were
totally one sided and were forced upon the Petitioner, and
therefore, cannot be binding on the parties, especially to entitle
the Respondent to wriggle out of its obligation to supply at least
10,800 metric tons per year as mentioned in the tender document.
In support of these propositions, Mr. Desai relied upon a decision
of the Supreme Court in the case of Central Inland Water
Transport Corporation Limited and Another v/s Brojo
Aswale 7/17
1.arbp.46.17.doc
Supreme Court Cases 156 and more particularly paragraphs
90 to 94 thereof. Placing reliance on this decision Mr Desai
submitted that the word "public policy" or "opposed to public
policy" though not defined in the Indian Contract Act, connote
some matter which concerns public good and public interest. It is
a concept which keeps changing, with the changing times. As new
concepts replace the old, transactions which were once considered
against public policy are now being upheld by the Courts and
similarly where there has been a well recognized head of public
policy, the Courts have not shirked from extending it to new
transactions in changed circumstances. He submitted that in the
facts of the present case the contract was in the prescribed and
standard form which embodied a set of rules as part of the
contract entered into with the Respondent who had a superior
bargaining power. Such a contract was unconscionable, unfair
and unreasonable and also injurious to the public interest, was
the submission of Mr. Desai. He submitted that such a contract
was not only voidable but in fact void. He submitted that looking
at Clauses 3.5. and 5.12, it was clear that the Respondent was in a
superior bargaining power qua the Petitioner, and therefore these
Aswale 8/17
1.arbp.46.17.doc
clauses be termed as void and not binding on the Petitioner.
12 On the other hand, Mr. Hiren Kamod, the learned
counsel appearing on behalf of the Respondent submitted that the
impugned award suffers from no infirmity requiring interference
in my limited jurisdiction under Section 34 of the Act. He
submitted that the Award is a detailed and well reasoned award
which runs from pages 63 to 82 of the paper book. The Arbitral
Tribunal has given proper and cogent reasons for coming to the
conclusion that it has. He submitted that from paragraphs 62 to
69 are the findings of the Arbitral Tribunal in relation to two
claims that were rejected by the Arbitral Tribunal. He submitted
that the reasoning given by the Arbitrator is not only fully
justified but the view taken is certainly a possible and a plausible
view that does not require any interference. As far as the
argument regarding clauses being void is concerned, Mr. Kamod
submitted that this argument has been raised first time across the
bar and this is not even a ground taken in the Arbitration Petition.
In fact, from reading the Award, it appears that this argument was
never even made before the Arbitral Tribunal. In these
circumstances, Mr. Kamod submitted that I ought not to take any
cognizance of this argument.
Aswale 9/17
1.arbp.46.17.doc
13 In the alternative, Mr. Kamod submitted that in any
event this argument has no substance. The Respondent had
floated the tender inviting offers from the public at large. The
tender document clearly mention these clauses. If the Petitioner
found these clauses unfavourable to his business interests, he
ought not have made any bid. Once having made a bid and being
accepted as a successful tenderer, he now cannot question the
clauses in the tender document, on the basis of which it had made
the offer in the first place. He submitted that the concept of
superior bargaining power can never be applied to the contract of
the present nature because nobody held gun to the head of the
Petitioner to make his offer to the Respondent pursuant to the
tender document floated by it. For all these reasons, Mr Kamod
submitted that there was no merit in this Arbitration Petition and
same ought to be dismissed with costs.
14 I have heard the learned counsel for the parties at
length and have perused the papers and proceedings in the
Arbitration Petition. I have also carefully gone through the
impugned Award passed by the Arbitral Tribunal. It is the case of
Mr. Desai that it was a binding obligation on the Respondent to
Aswale 10/17
1.arbp.46.17.doc
supply at least 10,800 metric tons per year to the Petitioner for
which the Petitioner was to be paid Rs. 550/- per metric ton. It
was the case of the Petitioner that admittedly this binding
obligation was not adhered to which has given rise to the claims as
more particularly set out in Exhibit A-1 to the Petition.
15 To understand this argument, one has to first examine
as to whether there was any binding obligation on the Respondent
to supply 10,800 metric tons per year as contended by the
Petitioner. If the answer to this issue is in the negative, then,
there is no question of saddling the Respondent with any loss
allegedly suffered by the Petitioner. The question of the Petitioner
being reimbursed for the alleged loss suffered by it would arise
only if there was a binding obligation on the Respondent to supply
at least 10,800 metric tons per year.
16 In this respect, it would be important to reproduce
clauses 3.5. and 5.12 of the tender document which read as
under:-
"3.5:- To enable the tenderer to assess the quantum of work, the estimated quantities expected to be delivered during the first year of operation is indicated below:
Aswale 11/17
1.arbp.46.17.doc
Steel: 10,800 MT
Pig Iron:NIL
Note: The above quantities are only indicative for enabling the tenderer to asses the probable/expected quantum to be handled. The company doesn't guarantee any minimum quantity of handling during the entire period of contract.
5.12:No guarantee whatsoever is given as to any definite tonnage, which would be entrusted the Consignment Agent for transportation, handling and storage at any given period of time during the entire tenure of contract."
17 As can be seen from the aforesaid clauses, what is
clear is that to enable the tenderer to assess the quantum of work,
the estimated quantities expected to be delivered during the first
year of operation was 10,800 metric tons of Steel. It was made
amply clear that the above quantity was only indicative for
enabling the tenderer to asses the probable / expected quantum to
be handled. The Respondent did not guarantee any minimum
quantity of handling during the entire period of contract. This is
made further expressly clear in clause 5.12 which clearly states
that no guarantee whatsoever is given as to any definite tonnage,
which would be entrusted to the Consignment Agent (Petitioner)
for transportation, handling and storage at any given period of
time during the entire tenure of the contract. To my mind, these
Aswale 12/17
1.arbp.46.17.doc
clauses are as clear as day light. They make it amply clear that
there was no obligation on the Respondent to supply a minimum
quantity of 10,800 metric tons per year, as contended by the
Petitioner. I find further support in this interpretation from
clause 5.2 of the tender documents (page 30 of the additional
compilation of documents tendered by the Petitioner) which
clearly stipulates that the Consignment Agent (Petitioner) may at
his discretion utilize the establishment for the purpose of dealing
with the materials of some other persons. In such a situation, the
Consignment Agent shall earmark the places for storage of the
materials of the Respondent, and shall take every step to avoid a
mix-up of the materials of the Respondent with those of others.
This clause also clearly shows that the Petitioner, as the
Consignment Agent of the Respondent, could utilize its premises
for storage of materials or third parties, in addition to that of the
Respondent. Mr. Kamod, and in my opinion correctly, placed
reliance on these clauses to show that the entire argument of the
Petitioner that he was in a weaker position or had a lesser
bargaining power with the Respondent is completely misplaced. It
is not as if the Petitioner was bound to the Respondent and had to
store only the material supplied by the Respondent. He was free
Aswale 13/17
1.arbp.46.17.doc
to store material of other persons over and above what was going
to be supplied by the Respondent. He was also free to negotiate a
rate with those other persons, if the Petitioner so chose. This
being position, I find considerable force in the argument of Mr.
Kamod that not only there was no binding obligation on the
Respondent to supply 10,800 metric tons of Steel per year but the
contract itself indicates that there was no unequal bargaining
power between the Petitioner and the Respondent. Having come
to this conclusion by looking at the contract as a whole, I find that
this issue has been correctly and adequately dealt with by the
Arbitrator from paragraphs 62 to 69 of the impugned Award. Not
only do I find that the reasoning and findings are fully justified,
but the view taken by the Arbitral Tribunal is certainly a plausible
and a possible view which does not require any interference in my
limited jurisdiction under Section 34 of the Act. I find that even
the Clauses relied upon by Mr. Desai, namely Clauses 2.1, 2.2(D)
and 3 do not in any way indicate that there was any binding
obligation on the Respondent to supply a quantity of 10,800
metric tons per year. Clause 2.1 talks about the infrastructural
requirements that the tenderer has to offer in order to participate
in the said tender. Clause 2.2 (D) also talks about other
Aswale 14/17
1.arbp.46.17.doc
infrastructure facilities that the tenderer has to provide such as
UPS of sufficient capacity, dust free A.C. environment and
dedicated Copper earth along with required cabling inside the
computer room. Clause 3 also deals with Schedule of Operations.
Nothing in these Clauses even remotely indicates that there was
any binding obligation on the Respondent to supply a minimum
quantity of 10,800 metric tons per year, as sought to be contended
on behalf of the Petitioner.
18 Having said this, it now leaves me only to deal with the
decision of the Supreme Court in the case of Central Inland Water
Transport Corporation Limited(supra) that was cited by Mr.
Desai. On carefully going through this judgment, I find that this
decision is wholly inapplicable to the facts of the present case. In
the facts before the Supreme Court, originally the Writ Petitions
were filed in the Calcutta High Court under Article 226 of the
Constitution of India challenging the termination of the services of
certain employees as also the validity of Rule 9(i) of the Central
Inland Water Transport Corporation Limited(Service, Discipline
and Appeal) Rules of 1979. In both these Writ Petitions, Rule NISI
was issued and an exparte ad-interim order staying the operation
of the notice of termination was passed by the learned Single
Aswale 15/17
1.arbp.46.17.doc
Judge of the Calcutta High Court. In the Letters Patent Appeal,
the Division Bench ordered in both the Appeals that the said Writ
Petitions be transferred to it and heard by it along with the said
Appeals. The said Appeals and Writ Petitions were thereafter
heard together and by a common judgment delivered on 9 th
August, 1985, the Division Bench held that the Corporation was a
State within the meaning of Article 12 of the Constitution and that
the said Rule 9(i) was ultra vires Article 14 of the Constitution.
Consequently the Division Bench struck down the said Rule 9(i) as
being void and also quashed the impugned order of termination. It
is against the said judgment and order of the Calcutta High Court
that the Appeals were filed before the Supreme Court. It is in this
context that one has to read paragraphs 90 to 94 on which
reliance was placed by Mr. Desai. There is no dispute with the
propositions laid down in the aforesaid decision of the Supreme
Court. However, I find that the same are wholly inapplicable to
the facts of the present case. In the facts of the present case, as
indicated above, no one held a gun to the head of the Petitioner for
participating in the tender floated by the Respondent. On reading
the clauses of the tender document, if the Petitioner was of the
view that it was not a worth while business risk, he ought not to
Aswale 16/17
1.arbp.46.17.doc
have participated in the tender at all. Having done so, he cannot
now today be heard to complain that certain clauses of the
contract, being unfavourable to him, ought to be struck down on
the ground that he did not have equal bargaining power with the
Respondent. He entered into the contract with the Respondent
with his eyes open, and therefore, is bound by the terms in the
tender document. This was not the case before the Supreme Court
at all. The case before the Supreme Court was with reference to
certain employees and was with reference to the Central Inland
Water Transport Corporation Limited (Service, Discipline and
Appeal) Rules of 1979.
19 For all the aforesaid reasons, I find no merit in this
Arbitration Petition. It is accordingly dismissed. However, in the
facts and circumstances of the case, there shall be no order as to
costs.
( B. P. COLABAWALLA, J.)
Aswale 17/17
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!