Citation : 2017 Latest Caselaw 9392 Bom
Judgement Date : 7 December, 2017
1 Jud.FA 41.06.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR
First Appeal (L.A.) No. 41/2006
Appellant:- Shri Akbar Umar Teli,
aged about 66 yrs, Occ.
Cultivator, R/o. Digras,
Tah. Digras, Dist. Yavatmal.
VERSUS
Respondents:- 1. The State of Maharashtra,
through Collector, Yaotmal.
2. The Collector, Yaotmal.
3. The Sub Divisional Officer &
Land Acquisition Officer, Darwha
(Benefit Zone), Dist. Yaotmal.
4. Sub Divisional Engineer, Vidarbha
Irrigation Development
Corporation, Arunavati Project,
Diggras, Tah. Digras, Dist.
Yeotmal.(amended as per order
dated 07.12.2017)
Shri A. Z. Jibhkate, Advocate for appellant.
Shri M. A. Kadu, Assistant Government Pleader for respodent Nos. 1 to 3.
Shri V. G.Palshikar, Advocate for respondent No.4.
___________________________________________________________________________
WITH
Cross Objection No. 15/2006
Appellant:- Shri Akbar Umar Teli,
aged about 66 yrs, Occ.
Cultivator, R/o. Digras,
Tah. Digras, Dist. Yaotmal.
VERSUS
Respondents:- 1. The State of Maharashtra,
through Collector, Yaotmal.
2. The Collector, Yaotmal.
3. The Sub Divisional Officer &
::: Uploaded on - 14/12/2017 ::: Downloaded on - 15/12/2017 00:54:12 :::
2 Jud.FA 41.06.odt
Land Acquisition Officer, Darwha
(Benefit Zone), Dist. Yaotmal.
Cross-Objector 4. Sub Divisional Engineer, Vidarbha
Irrigation Development
Corporation, Arunavati Project,
Diggras, Tah. Digras, Dist.
Yeotmal.(amended as per order
dated 07.12.2017)
Shri A. Z. Jibhkate, Advocate for appellant.
Shri M. A. Kadu, Assistant Government Pleader respondent Nos.1 to 3.
Shri V. G. Palshikar, Advocate for respondent No.4 - Cross Objector.
___________________________________________________________________________
CORAM : S. B. SHUKRE, J.
DATE : 07.12.2017.
Leave to amend the cause title of the appeal and
the cross-objection by adding the words "Vidarbha Irrigation
Development Corporation between the "Sub-Divisional
Engineer" and "Arunawait Project, Digras" in respect of the
description of respondent No.4 in the First Appeal as well as
cross-objection is granted to Shri Palshikar, learned counsel for
the cross-objector. Amendment be carried out forthwith.
Oral Judgment :
1. Heard Shri Jibhkate, learned counsel for the
appellant/original claimant. Shri M.A. Kadu, Assistant
Government Pleader for respondent Nos. 1 to 3 and Shri
Palshikar, learned Advocate for newly added respondent No. 4
in the appeal and cross-objection.
3 Jud.FA 41.06.odt
2. Both the appeal and the cross-objection arise out of
judgment dated 3rd January, 2004 rendered in Land Acquisition
Case No. 66/1994 by the Civil Judge, Senior Division, Pusad.
The dispute involves an issue about grant of just and proper
compensation to the original claimant for the land which has
been acquired in the present case for the Arunavati Project,
Tah. Digras, Dist. Yaotmal. The reference application had been
filed in November 1988. At that time, the Vidarbha Irrigation
Development Corporation (for short VIDC) was not in
existence. It was constituted later on and it came into being
in March 1997. Even at the inception, Arunavati Project was
not handed over to the VIDC and therefore, an amendment
was carried out in Vidarbha Irrigation Development
Corporation Act, 1997 by Vidarbha Irrigation Development
Corporation Ordinance, 1998 (Mah. Ord. XV of 1998) whereby
the Act was extended even to Arunavati Project situated in
Yaotmal District. After this amendment , the VIDC should have
been impleaded as a party respondent. However, the VIDC
was not joined as a party respondent.
3. In a similar group of appeals starting with First
Appeal No. 791/2009 (State of Maharashtra & ors. Vs. Swapnil
S/o Girdhar Nagpure) decided on 14 th September, 2017, a
submission was made on behalf of VIDC that as the VIDC was
not made a party respondent in the reference application, the
4 Jud.FA 41.06.odt
dispute about enhancement of compensation was required to
be remitted back to the Reference Court for a decision afresh
by relying upon the cases of Abdul Rasak & ors. Vs. Kerala
Water Authority & ors reported in (2002) 3 SCC 228 and
Vidarbha Irrigation Development Corporation Vs.
Santosh Janba Warghane & anr. reported in (2017) 4
Mh. L. J.64. This Court held that those appeals were squarely
covered by the ratio of the said cases of Abdul Rasak and
Santosh (supra). Accordingly, this Court remitted back the
dispute involved in those matters for a decision afresh, to the
Reference Court.
4. In the present case, the facts are similar and
therefore, I do not see any reason for me to take a different
view of the matter. Of-course, Shri Jibhkate, learned counsel
for the appellant submits that according to his knowledge, the
VIDC was represented before the Reference Court. However,
on going through the original reference application filed under
Section 18 of the Land Acquisition Act, I find that the
contention is not consistent with the record. VIDC was never
joined as a party to the proceedings before the Reference
Court. The statement is, therefore, not accepted. Thus, I find
that this appeal and the cross-objection both being squarely
covered by the view taken by this Court in the aforesaid group
of appeals the dispute raised by the Reference Application
5 Jud.FA 41.06.odt
would have to be remitted back, just as it was done earlier.
5. At this stage, Shri Jibhkate, learned counsel for the
appellant submits that at least cost of this matter be saddled
on the VIDC for the reason that the appellant could not be said
to be at fault in not joining the VIDC as a party. He further
submits that it was the duty of the Sub-Divisional Engineer of
Arunavati Project to place on record the change of
circumstances after coming into force the Vidarbha Irrigation
Development Corporation Act, 1997, of which he was well
aware. He also submits that the Sub-Divisional Engineer, as a
matter of fact could not have allowed himself to continue as a
party respondent in his own right and therefore, he ought to
have placed on record the developments of law which
adversely affected his status in the matter, but, he did not.
Shri Palshikar, learned counsel for VIDC objects to this. He
submits that the VIDC could not have been said to be at fault
and in-fact, if the change in the status occurred because of
change of law, the party whose status is affected cannot be
made to pay the cost.
6. I find that there is only half truth in the submission
of learned counsel for the VIDC. The change of law may not
be in the hands of the authorities but is not and cannot be
behind the back of the authorities. It is always within the
6 Jud.FA 41.06.odt
knowledge at least post change of law, of authorities, either
directly or presumptively. If the authorities are directly or
presumptively possessed of knowledge about change of their
status by operation of law, would it not be their duty to bring
this fact on record of the case and if they fail in this duty,
which party is to be blamed? Obviously, the party failing in the
duty, which is the case here, would have to be answerable to
the claim made regarding imposition of cost made on it. In
this way, I find that VIDC would have to bear the cost of the
proceedings.
7. In the result, the appeal and the cross-objection
both are allowed and impugned judgment and order are
quashed and set aside.
8. The reference application, is remitted back to the
Reference Court for its decision afresh in accordance with law
from the stage of evidence. It is made clear that evidence
already tendered by the parties shall be valid and taken into
consideration by the Reference Court. The parties shall be at
liberty to adduce further evidence if they choose to do so.
9. The claimants having been permitted to withdraw
the decreetal amount on furnishing security/surety etc. shall
be bound by those conditions and shall also abide by the final
decree that will now be passed afresh by the Reference Court.
7 Jud.FA 41.06.odt
10. The Reference Court shall allow the VIDC to be
joined as a party-respondent. The amendment in this regard
be carried out within one week from the date of appearance of
the parties.
11. The parties to appear before the Reference Court on
18th December, 2017. The Reference Court shall dispose of
the reference application within six months from the date of
appearance of the parties before it.
12. The parties shall cooperate with the Reference
Court without seeking any adjournment except on the ground
of factors beyond their control.
13. The costs of appeal and the cross-objection shall be
borne by the VIDC.
14. The appeal and cross-objection stand disposed of
accordingly.
JUDGE Gohane
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!