Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Prajita Developers Pvt.Ltd vs Yusuf Khan @ Dilip Kumar And Anr
2016 Latest Caselaw 328 Bom

Citation : 2016 Latest Caselaw 328 Bom
Judgement Date : 4 March, 2016

Bombay High Court
Prajita Developers Pvt.Ltd vs Yusuf Khan @ Dilip Kumar And Anr on 4 March, 2016
Bench: Anoop V. Mohta
    dgm                           1                                        appl-74-16.sxw


                 IN THE  HIGH COURT OF JUDICATURE AT BOMBAY
                     ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                 
                      ARBITRATION APPEAL (L) No. 74  OF 2016




                                                         
                                       IN
                      ARBITRATION PETITION NO. 829 OF  2015

                                    WITH 




                                                        
                      NOTICE OF MOTION (L) NO. 583 OF 2016 


    Prajita Developers Pvt.Ltd.                           ..      Appellants




                                               
                                                          (Orig.Petitioners)
           Vs.
    1  Yusuf Khan alias Dilip Kumar 
                                   
                                  
    2  M/s. Gold Beam Construction Pvt. Limited ..                Respondents 
                                                          (Orig. Respondents)
    Mr.   Janak   Dwarkadas,   Senior   Advocate   with   Mr.   Zal   Andhyarujina 
        


    with Arup Dasgupta, Ms. Shruti Sardesai Mr. Nirav Merchant and Ms. 
    Deepika Sekar i/b. Jhangiani Narula & Associates for the appellants.
     



    Mr.   Milind   Sathe,   Senior   Advocate   with   Mr.Chirag   Shah   and   Parag 
    Shah i/b. M/s. Mahesh Shah & Co. for respondent No.1





    Mr.N.H.Seervai, Senior Advocate with Mr. Rahul Chitnis i/b. Akshay 
    Shah for respondent No.2

                                      CORAM:    ANOOP V. MOHTA AND 





                                                G. S. KULKARNI,  JJ. 

    CLOSED FOR JUDGMENT ON:                    February 26,  2016 
    PRONOUNCED ON                 :            March  04,  2016

    JUDGMENT (Per Anoop V. Mohta, J.)

The Appellants (original Petitioners) have challenged

dgm 2 appl-74-16.sxw

impugned order dated 14.01.2016 passed by the learned Single

Judge, thereby the Petition under Section 9 of the Arbitration and

Conciliation Act, 1996 (for short, "Act of 1996") is dismissed.

2 The Appellants, through Section 9 Petition, sought

injunction against Respondent No.1, his servants and agents from

dispossessing from the property bearing land admeasuring 2,056

sq.mtrs. plot no.16 of Pali Hill Estate in the Village of Danda (Bandra),

Taluka-Andheri, Bandra (East), Mumbai 400 051, forming part of

Survey No.236, No.3, N.A. No.329 corresponding CTS. No. C/1395,

C/1396 and C/1397 (hereinafter referred to as the said Property).

3 Respondent No.1 is 92 years old, a senior citizen, had

entered into Development Agreement dated 23.06.2006. The learned

Judge referred those facts in paragraphs 4, 5 and 6 in the impugned

order, which read thus:

"4 The development agreement dated 23.6.2006 was

executed between Yusuf Khan alias Dilip Kumar

Respondent no.1, M/s.Sharyans Resources Limited

dgm 3 appl-74-16.sxw

(hereinafter referred to as M/s.Sharyans) and respondent

no.2 M/s.Gold Beam Construction Pvt.Ltd. whereby

respondent no.1 granted development rights to the said

M/s.Sharyans and to the respondent no.2 as stated therein

in respect of the said property upon terms and conditions

and for consideration of Rs.10 crores. The development

agreement was duly registered with the Sub-Registrar of

Assurance. Power of Attorney executed by respondent no.1

in favour of respondent no.2 and its director to enable the

developer to commence the development work. As per the

said Development Agreement developers paid sum of Rs.1

crores to the respondent no.1 on execution of development

agreement and thereafter paid sum of Rs.3 crores. In all

they paid Rs.4 crores to the respondent no.1. Some of the

relevant clauses of the said development agreement dated

23.6.2006 are as under:

"1. (A) For monetary consideration as hereinafter provided to be paid by the Developers to the Owner and

other than the consideration of providing to the Owner free of costs the built-up premises desired to be retained by the Owner, in the buildings to be constructed on the said property the Owner hereby grants to the Developers and the Developers hereby acquired from the Owner the development rights to the extent and in the manner hereinafter provided in respect of the said property more particularly described in the Schedule hereunder written

dgm 4 appl-74-16.sxw

(hereinafter as aforesaid referred to as "the said Property") by consuming and utilizing the entire permissible F.S.I. in

respect of the said Property (including F.S.I. of staircase, lifts, passage, balcony etc.) as well as by consuming and utilizing entire permissible T.D.R. In accordance with the

Development Control Regulations of MCGM.

(B) It is estimated that for development of the said Property the total permissible FSI available is about 2056

sq.mtrs. Equivalent to 22130 sq.ft. and further FSI by way of TDR as permissible under D.C.Regulations of MCGM.

(i) The entitlement of the parties in the development

potential shall be as under:

             Party 
                                   
                           Residential User
             (1)                   (2) 
                                                                            CPS

             Owner                50%                                       50%
                                  
             Developers       50%                                           50%

(ii) The Owner has retained and/or will be deemed to have retained for his own use and benefit above stipulated entitlement of the Owner out of the total FSI and TDR

available for the development of the said property including proportionate entitlement of the total number of

car parking slots (CPS) (both stilted and/or open) that may be provided in the complex and the said portion of the FSI (hereinafter collectively referred to as "the Owner's Lot), shall be developed by the Developers at the cost of the

Developers in the manner and in accordance with the plans prepared as per the requirement of the Owner and under the supervision of the Architect of the project and in the time frame and in the manner as provided herein.

(iii) The benefit of the above stipulated entitlement of the Developers out of the total FSI and TDR available for development of the said property as also of the total CPS (both stilted and open) that may be provided in the complex (such Developer's entitlement available for development on the said Property and the CPS-both stilted and open) that may be provided in the complex (hereinafter referred to as "the Developer's lot) shall be

dgm 5 appl-74-16.sxw

developed by the Developers at its own costs and shall belong to the Developers and shall be at the disposal of the

Developers.

(iv) In case any additional area or potential over and

above the present development potential is allowed in future to be constructed on payment of premium, the same shall be divided between the Owner and Developers in the proportion as provided in Clause 1(B) (I) above and then

ali pro-rata costs of such premium and the costs of construction of such additional area coming to the share of the Owner shall be borne and paid by the Owner and the remaining pro-rate costs of such premium and the costs of

construction coming to the share of the Developers shall be borne and paid by the Developers. Above stipulated

entitlement of the Owner of such additional built-up area shall form part of the Owner's lot and above stipulated entitlement of the Developer's lot. It is certified that the

purpose aforesaid the term "present development potential" shall means F.S.I. available on the said property for redevelopment and additional 50% thereof by way of T.D.R.

3. The Developer's shall pay to the Owner the sum of Rupees Ten Crore as and by way of lump sum monetary

consideration in the manner as provided herein:

(a) a sum ali of Rs.1,00,00,000/- (Rupees One Crore Only) on execution of these presents.

(b) a sum of Rs.4,00,00,000/- (Rupees four crore Only) before handing over vacant possession of the said property including the Bungalow standing on the said property to enable the Developers to enter upon the said property and

commence development.

(c) the balance sum of Rs.5,00,00,000/- (Rupees five crores Only) within six months from the date of this Agreement provided the Developers are not restrained and/or not prevented from carrying on the development of the property as provided thereunder.

dgm 6 appl-74-16.sxw

17. Upon payment of the balance monetary consideration by the Developers to the Owner as provided

in Clause 3(b) the Owner shall permit and the Developers shall have the license to enter upon the said Property to develop the said Property,to carry on construction on the

said Property and for that purpose to do all acts, deeds, matters and things as may be necessary exercising the following rights and authorities:

(a) To put and/erect sign boards upon the said Property as also to issue advertisement in the newspapers and other medias as may be deemed fit by the Developers announcing the construction of the buildings on the said Property and

the sale of the flats, shops, offices, garages, parking spaces, tenements, etc. (coming to the share of Developers on ownership basis.

(b) After revalidation of the building plans to commence,

carry on and complete construction of the buildings on the said Property by the Developers or through its contractors, sub-contractors or any other agent at its costs.

(c) To dispose of in its own name on ownership basis of

the flats, shops, offices, garages, parking spaces, tenements, stilts or any other rights in the buildings to be constructed

on the said Property which comes to the share of the Developers to the person or parties of its choice at the price and upon the terms and conditions as the Developers may deem proper.

(d) To receive the consideration from the purchasers of the flats, shops, offices, garages, parking spaces, tenements, stilts or any other rights in the buildings to be constructed on the said Property which comes to the share of the

Developers and the Developers shall be entitled to appropriate the same as it may deem fit and proper.

(e) To enter into agreements for sale of the premises which comes to the share of the Developers comprising of the flats, garages, parking spaces, tenements, stilts or any other rights in the buildings to be constructed on the said Property."

     dgm                           7                                              appl-74-16.sxw



             5       Initially, the said M/s.Sharyans applied to the various 




                                                                                       

authorities for permission to develop the suit property. M/s.Sharyans paid an amount of Rs.2,89,900/- on

28.4.2008 to the National Institute of Oceanography to obtain requisite CRZ clearance to load TDR upon the said

property. In May 2008, the said M/s.Sharyans applied for height clearance for the building to be constructed to the Airport Authority. The Airport Authority of India granted

NOC for height clearance for the building to be constructed on the said property on 22.8.2008. Thereafter the said

M/s.Sharyans appointed a Contractor to execute the Development work under the Development Agreement and

the said contractor has done demolition of the old bungalow, excavation work necessary to lay foundation of the new building, pilling work, foundation work etc. On

22.9.2008 Municipal Corporation for Greater Mumbai

granted commencement certificate for development of the said property.

6 On 20.4.2010, the deed of assignment came to be executed between M/s.Sharyans and the petitioners by which M/s.Sharyans have assigned their right, title and

interest of the development agreement dated 23.6.2006 to the petitioners. As per the said deed of assignment dated 20.4.2010 the petitioners acquired M/s.Sharyans right in development agreement dated 23.6.2006. Pursuant to the said deed of assignment, partnership deed between respondent nos.1 and 2 modified and the petitioners

dgm 8 appl-74-16.sxw

became a partner of the said partnership firm whose aim was to develop the said property as per the development

agreement. Because of the dispute between the parties,

the petitioners invoked Arbitration Clause of development agreement dated 23.6.2006 calling upon the respondents to appoint the Arbitrator to dissolve their disputes. The

Arbitration Clause of the development agreement dated 23.6.2006 reads thus:

"40 All disputes differences and questions whatsoever arising between the parties hereto and/or the persons

claiming by under or through them at any time touching these presents or any matter arising out of this transaction if not resolved mutually between the parties, the same shall

be resolved by arbitration of a single arbitrator if both parties agree upon one such, or by two arbitrators one each appointed by each party and third Arbitrator appointed by them, and the decision of the Arbitrator/s shall be final and

binding upon the parties. The Venue of such Arbitration shall be Mumbai and subject as above, the same shall be in

accordance with the Arbitration and Conciliation Act, 1996."

4 The learned Judge referring to the affidavit so filed on

record, including the documents read with judgments so cited, noted

even the rival submissions in paragraphs 13 to 17 of the Order.

5 The learned Judge ultimately concluded in paragraphs 21

to 23 and dismissed the Petition.

     dgm                           9                                         appl-74-16.sxw




                                                                                  
    6               The   Appellants/Petitioners/Prajita   have   obtained   the 




                                                          

leasehold rights in the property together with the bungalow standing

thereon by virtue of Lease dated 25 September 1953. Since they

wanted to develop the said property, applied to the Corporation of

Greater Mumbai (MCGM) and obtained IOD dated 6 October 2000.

Therefore, for the same, a Memorandum of Understanding of 1 July

2004 was executed with M/s. Sharyans Resources Limited

(Sharyans), who was appointed as the Project Manager for the

development of the property. Sharyans and M/s. Gold Beam

Construction Pvt Ltd (Gold Beam) entered into a Partnership on 16

June 2006 for development of the property. A fresh Partnership Deed

was executed on 10 December 2008 (the Partnership Deed) with

Respondent No.2/Gold Beam. Based upon the Partnership, the

monetary burden was upon them to develop the property. Gold Beam

was required to bring its contribution of 50% of the cost and 50% of

monetary consideration through Respondent No.1 (owner). The

profit of the firm was to be shared equally between the Sharyans and

Gold Beam. A development agreement was entered into with

Sharyans on 23 June 2006 and Gold Beam. The same was further

dgm 10 appl-74-16.sxw

rectified by the Deed of Rectification on 11 September 2006 (the

Development Agreement). The owner executed a Power of Attorney

(POA) in favour of Gold Beam to authorise various agreements.

Sharyans and Gold Beam were supposed to develop the said property

as per the said agreement (the Developer). A monetary consideration

of Rs. 10 crores as per clause 3 was required to be paid to the owner.

The said instalments are mentioned in the above paras as noted by the

learned Judge. Based upon the Development Agreement, the

Sharyans and the Gold Beam were permitted to enter upon the

property as developers. The remaining amount was required to be

paid from the date of Development Agreement (23 December 2006).

The remaining said amount was not paid to the owner in full. The

amount paid was approximately, 7,14,00,000/-. The part payment

apart, no progress of construction and development as agreed was

made.

7 As per the agreements, Sharyans and Gold Beam were to

get 50% of the development potential area to be constructed which

was subject to further division equally between the Sharyans and the

Gold Beam. There is no dispute that as per clause 19 (d) of the

dgm 11 appl-74-16.sxw

Development Agreement, the entire development work was to be

carried out by the developer/Appellant/Petitioner at their own costs,

including to procure the permissible TDR as per clause 2 of the

agreement. There is nothing to show that the developers have

procured any part of TDR in view clause 11-A(a). Admittedly, as per

the agreement, the development was supposed to commence within

30 days and should be completed within a time period of 12 months

from the date of IOD/Commencement Certificate. The plans were

approved on 2 January 2008 and CC was obtained on 22 September

2008. No steps to initiate even construction were taken. Admittedly

the development of the remaining was not completed before

September 2011 - even the foundation was not laid, except some

piling work with two coloums. The position remained same till the

year 2013-2014. The said position of 2013 and 2014 still remained

same till this date. In the background, such

construction/development contract so entered into by Respondent

No.1/owner to develop his property as a owner within his lifetime

considering his age. The agreement clause itself shows that time was

an essence of the contract to complete the development so that all the

parties including the Appellants/Petitioners would get his 25% share

dgm 12 appl-74-16.sxw

after completion of the construction at this costs. The

Appellants/Petitioners entitlement was only after completion of the

development. The remaining 25% was admittedly of Gold Beam. In

the remaining 50% area, the Appellants and/or Gold Beam and/or

Sharyans had no right whatsoever. Their rights/interest/entitlement

was also subject to to the development and construction for the

development potential area. The Developers could not even obtain

permission, NOC, though obtain re-validation of CC till the year 2013.

The Sharyans and his assignee/Petitioner/Prajita, therefore, failed to

develop the property further as per the agreement.

8 Sharyans executed a Deed of Assignment (the Deed of

Assignment) on 20 April 2010 and assigned its rights and liabilities

arising out of the Development Agreement in favour of the

Appellants/Petitioner/Prajita, by which the Appellants were entitled to

25% share in the development rights, but it was subject to all

liabilities and obligations of the Sharayans under the agreement. The

Deed of Assignment was confirmed by the Respondents also. On the

same day, a Deed of Admission-cum-Retirement was executed by and

between the Sharyans and the Appellants/Petitioners/Prajita and Gold

dgm 13 appl-74-16.sxw

Beam, whereby the Sharyans retired from the said firm and

Prajita/Appellants was treated as new partner on the same terms and

conditions in place of Sharyans under the Partnership Deed.

Admittedly, the Appellants, therefore, stepped into the shoes of

Sharyans with all rights and liabilities mentioned in the said

development agreement. The Appellants, therefore, knowing the

background and the obligation, including the time being the essence

of the contract in view of the nature of construction and the reason for

development of the property by the owner, the Appellants as well as

the Gold Beam/Respondent No.2, failed to comply with the essential

terms and conditions of the Development Agreement in time. They

have not complied with the various conditions mentioned in the IOD

and the NOC till this date. There was no dispute with regard to the

title/ownership of Respondent No.1. There was no restraintment

order of any kind passed against Prajita/the Sharyans and/or the

property in question. There was nothing to prevent the developer to

carry out the construction activities in time. The suit by Sameer

Bhojwani, even if any, about rent, pending in Small Causes Court,

Bandra, ad-interim injunction was only between 25 September 2013

which was vacated on 31 October 2013 i.e. only for 37 days.

dgm 14 appl-74-16.sxw

Therefore, there was no constraint of any kind for the development of

the property in question. There was no any such communication

and/or agreement to stop the construction work. The Developers

including the Appellants, therefore, failed to stick to the time so

agreed. The submission that for some time, Respondent No.1 asked to

stop the construction on account of third party claim against his title

in the Suit which was for short time is of no assistance to claim the

defence of stopping of work by Respondent No.1. The Appellants,

therefore, as noted, has not shown any progress of construction. This

shows that the developers were unwilling to develop the said

property for various reasons including the requisite funds to carry out

the development work. Admittedly, they did not commence and

complete the development of the property. In the meantime, there

was no question of touching the portion of the bungalow as it was

subject to other clause of the agreement and basically when developer

for eight years except two coloums and carry out piling work, made

no construction as per the agreements, as they agreed to complete the

building and made ready for occupation within 25 months from the

date of obtaining CC. The Appellants, as recorded, have not done any

activity of construction except by Sharyans so made before the

dgm 15 appl-74-16.sxw

assignment. This itself, as rightly expressed by the learned Judge and

we have also noted the inability and unwillingness to pursue the

development as per the agreement.

9 The nature of agreement itself shows that the

Appellants/Petitioners and the Sharyans and/or Developers were

permitted to enter into the property as developer only after part

payment of consideration. The said licence was for limited purpose

and for ancillary activities. The intention was made known to all.

This licence, in our view, also cannot be read to mean and as sought to

be contended by the counsel appearing for the Appellants, that the

interest was created in the property in perpetuity.

10 The reliance was placed on a judgement of a Division

Bench in Chheda Housing Development Corporation v. Bibijan Shaikh

Farid and ors1., in support of their contention. In that case, the

agreement was totally different. There was no such development

agreement whereby share of the Petitioner, at the most is 25% i.e.

after completion of the construction and developing the further

1 2007 (3) Mh. L. J. 402

dgm 16 appl-74-16.sxw

property. In the facts and peculiar circumstances and basically the

clauses so read and referred and the agreement so entered into and as

admittedly, the Petitioner was not in picture at the time of basic

development agreement and admittedly came into picture in the year

2010 and as no property was developed at any point of time, though

permitted to enter into the premises, the said judgment is of no

assistance to claim the interest in the property based upon the

agreement itself.

11 The submission that time was not the essence of the

contract based upon the decision in M/s.Hindu Construction

Contractors v. State of Maharashtra,2 is also unacceptable. The

findings given by the learned Judge, based upon the clauses so read

and referred and as we have also considered those rival contentions

and submissions and as there was no progress whatsoever shown and

it is a case where the Petitioners who subsequently entered into the

suit property based upon the agreement so referred and unable to

show willingness and desire to complete the construction as agreed on

the basis of 2006 Development Agreement and as we have also come

2 (1979) 2 SCC 70

dgm 17 appl-74-16.sxw

to a conclusion, looking to the facts and circumstances, the time was

the essence of the contract,, the Appellants therefore failed to perform

their obligations. The invocation of arbitration clause and the

termination of the contract by the Appellants/Petitioners in no way

can be stated to be wrong and/or impermissible. The breach

committed by the Appellants and Respondent No.2, therefore, goes to

the root of the agreement of such contract and as there is no case of

any waiver and/or extension of agreed time for further development,

in view of express provisions, the contention that the time was not the

essence of the contract, is unacceptable.

12 The submission is raised for the first time in Appeal that

the Appellants are entitled to claim specific performance and/or

related reliefs from Respondent No.2 being part of the Development

Agreement as well as Assignment Deed in question. Admittedly,

Respondent No.2 has not raised any such issue and/or not claimed

any specific performance and/or not made any demand from

Respondent No.1. Therefore, having accepted the position including

the termination by one of the partner/party to the Development

Agreement/Deeds, the intended claim of specific performance, even if

dgm 18 appl-74-16.sxw

any, in the present facts and circumstances, in our view, is an

additional ground and reason, to hold that the Appellants/Petitioners

are not entitled for interim protection and/or relief so sought by

restoring the terminated contract. Out of two partners, one partner

has already accepted the termination, the interest even, if any, as

noted, of 25% share, which was also subject to completion of

construction, the Appellants/Petitioners are at the most entitled for

the damages and/or similar compensation. However, after

considering the totality of the matter and as admittedly, the

Appellants/Petitioners have no right or interest till other remaining

75% of the property in question, no case for interim relief/or

protection and/or restoration of possession so stated, is made out.

13 The judgment referred to Order 1, Rule 1 of Code of Civil

Procedure (CPC) to join parties for specific performance and for

related claims, based upon Jahar Roy (Dead), through L.Rs v. Premji

Bhimji Mansata,3 Poonuswami Gounder v. Rama Boyan and ors.,4 are

of no assistance to interfere with the impugned order so also the

judgment revolving around Section 45 and Section 23 of Specific 3 (1977) 4 SCC 562 4 AIR 1979 Madras 130

dgm 19 appl-74-16.sxw

Relief Act in Kandaswami and ors v. Venkatachala Kandar and ors. 5,

specifically when it is settled that the remedy of specific performance

is an equitable one and is in the discretion of the Court. As noted, the

facts and circumstances, though we are not expressing final opinion,

as it will be subject to Suit and/or Arbitration, if initiated, but we are

inclined to observe that the Appellants and the Plaintiffs claim, even if

any, in no way, can be more than damages and/or compensation.

These observations are for deciding this Appeal against judgement on

Section 9 Application. The main relief of specific performance, in

view of above admitted position, as not possible and would not be

executable, the interim protection and/or relief in aid to the same, as

prayed in Section 9 Application, therefore, as not granted by the

learned Judge and we see no case is made out to interfere with the

same, considering the scope and power of Appellate Court under

Section 37 of the Act of 1996. The Apex Court in Wander Ltd and anr

v. Antox India P Ltd6., has dealt with the power of Appellate Court to

interfere with the reasoned order passed by the learned Judge in

exercising and taking note of basic principle of law of injunction.

Even otherwise, as noted, no case is made out to substitute the order 5 1972 The Madras Law Journal Reports 401 6 1990 (Supp) SCC 727

dgm 20 appl-74-16.sxw

so passed as the same is not illegal, contrary and/or perverse. The

order so passed is well within the frame work of law and the record.

14 The judgment so cited by the learned senior counsel

appearing for the Appellants in ICICI Bank Limited v. United Breweries

(Holdings) Limited and ors., in Appeal (L) No.409 of 2015 in Notice of

Motion (L) No. 905 of 2015 in Suit (L) No. 290 of 2015 with Notice of

Motion (L) No. 1285 of 2015 dated 3 December 2015 ( V. M. Kanade,

Acting Chief Justice & Dr. Shalini Phansalkar-Joshi, J.), in support of

his submission that if case is made out, the Appellate Court is required

to interfere even with the reasoned order so passed by the learned

Judge. In the facts and circumstances, the Division Bench of this

Court interfered with the reasoned order, apart from the reasons

which we have noted above, as it would be difficult for the Court,

even the Arbitrator to pass order of specific performance except,

subject to material and evidence, compensation/damages, if any. This

is subject to counter claim/damages by Respondent No.1 also.

15 In the result, the Appeal is dismissed. There shall be no

order as to costs.

     dgm                           21                                            appl-74-16.sxw




                                                                                      
    16              In view of dismissal of Appeal, Notice of Motion (L) No. 




                                                              

583 of 2016 does not survive and stands disposed of accordingly.

17 At this stage, learned senior counsel appearing for the

Appellants submits that the statement of Respondent No. 1 to

continue for a period of two weeks. Considering the issue so involved

and the reasons so recorded and in the interest of justice, we are

inclined to continue the statement of Respondent No.1 for two weeks.

Order accordingly.

    (G. S. KULKARNI, J.)                               (ANOOP V. MOHTA, J.)
     











 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter