Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Shirdi Country Inns Pvt. Ltd vs M/S. Suvidha Engineers India Pvt. ...
2016 Latest Caselaw 2785 Bom

Citation : 2016 Latest Caselaw 2785 Bom
Judgement Date : 13 June, 2016

Bombay High Court
M/S. Shirdi Country Inns Pvt. Ltd vs M/S. Suvidha Engineers India Pvt. ... on 13 June, 2016
Bench: Anoop V. Mohta
     PVR                                 1/6                                        4app246-15.odt

                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                         ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                            
                                 APPEAL NO. 246 OF 2015




                                                                    
                                          IN
                          ARBITRATION PETITION NO. 782 OF 2014

    M/s. Shirdi Country Inns Pvt. Ltd.,                        )
    having their address at 5th Avenue,                        )




                                                                   
    A-1, 5th floor, Dhole Patil Road,                          )
    Pune 411 001                                               )                ...Appellant

              Versus




                                                    
    M/s.Suvidha Engineers India Pvt. Ltd.
                                    ig                         )
    having their address at 409-412,                           )
    Siddharth Towers, 4th floor, S.No.12/38,                   )
    Sangram Press Road, Kothrud,                               )
                                  
    Pune-411029.                                               )                ...Respondent
      

    Mr.Rajiv Singh with Mr.Sayeed Mulani and Mr.Dileep Sutale i/b. MULANI  
    AND CO., for the Appellant.
   



    Mr.L.G.Rai, for the Respondent.

                                               -------





                                CORAM                    :     ANOOP V. MOHTA &
                                                               G.S.KULKARNI, JJ.
                                DATE                     :     13th JUNE,2016





                               ---
    ORAL JUDGMENT: (PER ANOOP V. MOHTA, J.)
     

1. This Appeal is filed under Section 37 of the Arbitration and

Conciliation Act,1996 (for short 'the Act') against judgment and order

dated 13th January,2015 passed by the learned Single Judge under

Section 34 of the Arbitration Act whereby the Appellant's petition was

PVR 2/6 4app246-15.odt

dismissed and the Award passed in favour of the Respondent (original

claimant) and against the Appellant has been maintained. Hence, this

appeal.

2. The Appellant invited a tender for certain work through its

consultant. The Respondent had submitted its tender. A work order was

issued and the tender work was completed. The amount so due was

paid accordingly. It is averred that the Respondent carried out extra

work and raised various invoices for the same. Thus, disputes arose

between the parties on the issue of this extra work. By a consent order

dated 18th February,2011 in an application under Section 11 of the Act,

the Chief Justice appointed a sole arbitrator. The learned Arbitrator

made an award which came to challenged by the Appellant by filing

earlier arbitration petition. By consent of both the parties the Award was

set aside by order dated 29th October,2012. The Court appointed

another Arbitrator to adjudicate the disputes. The learned Arbitrator

made a fresh Award on 18th January,2014 which was challenged in the

Arbitration Petition No.782 of 2014. The petition was dismissed by order

dated 13th January,2015. Hence, the appeal.

3. There is no dispute that the Respondent's claim was arising

out of extra work which was outside the purview of the basic work

order. There is no issue on the fact that the work was actually carried

PVR 3/6 4app246-15.odt

out. The obligation of the Appellant to make payment was, therefore,

considered on the basis of the claim so raised by the Respondent by

leading evidence in support of the same with supporting documents.

The learned Arbitrator has appreciated the same. This is also in the

background that the Appellant did not lead any counter-evidence except

making denials and/or opposing the claim, also on the ground of no

jurisdiction to entertain the claim so raised.

4.

Admittedly, there was no specific arbitration clause for the

extra work as carried out, but the claim was raised by the Respondent

covering the amount due and payable for extra work. The same was

denied and has not been paid fully. It was recorded that a part payment

was made in the year 2007 and what remained was a payment of

Rs.10,72,899/-. This was the foundation based upon which the learned

Arbitrator and the learned Judge has accepted the case of the

Respondent and rejected the submissions of the Appellant that the claim

is beyond limitation. A finding is given by the learned Arbitrator and the

learned Judge that the claim is within limitation. We have also gone

through these findings, including the letter dated 29 th March,2008 to

justify that there was no denial to the part payment made, for this extra

work and the claim was for the balance amount.

5. The issue of claim being outside the purview of the work

PVR 4/6 4app246-15.odt

order, in the present facts, is also unacceptable, as apart from the earlier

appointment of Arbitrator, as there arose disputes, after hearing both

the parties in view of no objection so raised about the claim of the

amount of extra work, which are stated to be outside the purview of the

work, by consent for the second time an Arbitrator was appointed. The

learned Arbitrator, in view of the above consent order proceeded with

the arbitration. The issues were raised but no evidence led by the

Appellant though participated in the proceedings. We see that there is

no illegality in deciding the claim so referred and as decided. The above

order passed by the learned Judge is well within the purview of record

and law.

6. The issue of jurisdiction even if raised, that itself is not

sufficient to interfere with the Award passed by the learned Arbitrator.

Even otherwise, there is no substance in the objection so raised with

regard to the jurisdiction. This is specifically in the background of the

order passed by the Chief Justice while appointing the Arbitrator on 18 th

February,2011. The issue of arbitrability and the jurisdiction, in our

view, is also concluded by the consent order. The Appellant cannot be

permitted to go behind the consent order. Even otherwise in the present

case there is no reason to permit the Appellant to re-agitate the issue in

appeal, merely because while appointing the Arbitrator all contentions

were kept open. We have to see the background of the disputes between

PVR 5/6 4app246-15.odt

the parties and so also the conduct. The work done if not in dispute and

not seriously contested by not leading evidence in defence, on the

contrary the Respondent based upon the material by leading evidence

justified its claim and the learned Arbitrator has accepted it. We thus

see no case is made out of any illegality and/or perversity.

7. The learned Judge after considering the reasoned award

passed by the learned Arbitrator, has considered the submissions of the

Appellant and the Respondent and rejected the petition. We have also

gone through the reasons given by the learned Arbitrator and by the

learned Single Judge. We also see no reason to interfere as there is no

perversity and/or there is no illegality to the extent that the Appeal

Court should interfere with the reasoned order passed by the learned

Single Judge.

8. The judgment cited by the learned Counsel appearing for

the Appellant in the case "VISA International Ltd. Vs. Continental

Resources (USA) Ltd., (2009(2) SCC 55)" is of no assistance in view of

the reasons so recorded above as the Appellant itself made a part

payment and the claim was for the balance amount for the extra work

done. Therefore, the submission that there was no "issue" between the

parties in the present case, is unacceptable. The judgment relied on is

distinct and distinguishable on facts and on law also.

PVR 6/6 4app246-15.odt

9. The Apex Court has reiterated and maintained the payment

for the extra work done beyond the basic contract, in "Venkatesh

Construction Company Vs. Karnataka Vidyuth Karkhane Limited

(Kavika), (2016(2) All MR 953 (S.C.)."

10. Therefore, taking overall view of the matter and in view of

the Judgment also in the case of "M/s.Chebrolu Enterprises Vs. Andhra

Pradesh Backward Class Co-operative Finance Corporation Ltd., reported

in '2015(12) SCALE 207', wherein it is observed that:-

"20. ... ... ... .... This Court or even the Appellate Court would not look into the finding of facts unless they are

perverse."

The appeal is liable to be dismissed. Hence, the following order:-

ORDER

The Appeal is dismissed.

No costs.

             (G.S.KULKARNI, J.)                              (ANOOP V. MOHTA, J.)





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter