Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Sarathi Enterprises vs Union Of India Through Executive ...
2016 Latest Caselaw 2528 Bom

Citation : 2016 Latest Caselaw 2528 Bom
Judgement Date : 6 June, 2016

Bombay High Court
M/S Sarathi Enterprises vs Union Of India Through Executive ... on 6 June, 2016
Bench: Anoop V. Mohta
        ssm                                                     1                                              9-app123.16.sxw

                  IN THE  HIGH COURT OF JUDICATURE AT BOMBAY

                          ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                                                  
                                  APPEAL NO. 123 OF 2016




                                                                                     
                                            IN
                           ARBITRATION PETITION NO. 950 OF 2013

    M/s. Sarathi Enterprises




                                                                                    
    1101, Udhyan II, Off Marol Military Road,
    Saki Naka, Andheri (East),
    Mumbai-400 072                                                                              ....Appellant.




                                                                  
                         Vs.

    Union of India,
    Through Executive Engineer,
                                          
    Mumbai Central Division No. I,
                                         
    CPWD, M.K. Road, Churchgate,
    Mumbai-400 020.                                                                             ....Respondent. 

    Ms. Shilpa Kapil for the Appellant.
          


    Dr. G.R. Sharma a/w Mr. D.P. Singh for the Respondent.
       



                                   CORAM  :  ANOOP V. MOHTA AND
                                                A.S. GADKARI, JJ.

DATE : 6 JUNE 2016.

ORAL JUDGMENT (PER- ANOOP V. MOHTA, J.):-

Heard the learned counsel appearing for the Appellant

finally, as the matter is fixed for the final hearing.



    2                    In nutshell, the case of the Appellant-Original Respondent, 







         ssm                                                     2                                              9-app123.16.sxw

    is that-

On 22 July 2010, a tender was invited for "providing and fixing

vitrified tiles flooring over existing flooring from Ground to sixth Floor at

Aayakar Bhawan, Mumbai". The work was awarded to the Appellant

by letter dated 22 July 2010. The Appellant by letter dated 5 August

2010, recorded the verbal discussion with the Executive Engineer

whereby, the Executive Engineer has directed to use only Johnson

vitrified tiles and no other equivalent brand. The Appellant has

further informed the Respondent that the Appellant intends to use

some other equivalent brand as per condition of contract. By letter

dated 16 August 2010, the Respondent again reiterated that only

Johnson vitrified tiles and no other equivalent brand be used as the

client has approved Johnson vitrified tiles only.

3 The Appellant was directed to execute the work with

Johnson vitrified tiles only and no other equivalent brand. The

Appellant by letter dated 28 September 2010, informed the

Respondent that they have already shown their inability to execute the

work with Johnson Vitrified tiles as M/s. H.R. Johnson (India) Limited

is quoting exorbitant price for the product specified in the tender in

ssm 3 9-app123.16.sxw

comparison to other equivalent brand by taking advantage of the fact

that he is the only preferred manufacture by the Respondent. By

letter dated 9 October 2010, the Appellant informed the Respondent

that they have lodged a complaint with Chief Engineer (Vigilance)

CPWD.

4 The Appellant, time and again, had stated that they are

always ready and willing to execute the work subject to approval of

"equivalent brand". The Respondent never agreed to it. On the aspect

of violation of Sections 3 and 4 of the Competition Act, 2002 (for

short, "the Competition Act"), the Executive Engineer by letter dated 7

December 2010, had stated that the agreement is entered into

between the parties and the breach is on the part of the Appellant.

5 On 22 January 2011, the advertisement appeared in the

newspaper for the work of "Providing and Fixing vitrified tiles flooring

over existing flooring from Ground to Sixth floor at Aayakar Bhavan,

Mumbai" which is the same work, which was awarded to Appellant.

Interestingly, except issuance of "final notice", the work awarded to

the Appellant is neither terminated nor foreclosed. The fresh tender

ssm 4 9-app123.16.sxw

invited, was also not the risk and cost tender. The Appellant, by letter

dated 29 January 2011, requested the Executive Engineer to foreclose

the contract without liability upon the Appellant and refund the EMD

and performance guarantee. On 8 February 2011, the Executive

Engineer by its letter stated that contract has already been determined

with forfeiture of EMD and Security Deposit by their letter dated 16

November 2010.

In view of an Arbitration under Clause 25, the Appellant

by letter dated 9 March 2011, requested the Chief Engineer to appoint

the Arbitrator. The Chief Engineer by letter dated 27 July 2011,

appointed Shri Rajiv Kumar as the sole Arbitrator in respect of the

claims of the Appellant and counter claim of the Respondent. On 6

March 2013, the Appellant and the Respondent filed their respective

pleadings before the Arbitrator. The Respondent also raised the

counter claim before the Arbitrator. The Arbitrator after hearing both

the parties passed Award dated 6 March 2013.

7 Being aggrieved, the Respondent filed an Arbitration

Petition under Section 34 of the Arbitration and Conciliation Act, 1996

ssm 5 9-app123.16.sxw

(for short, "the Arbitration Act") for setting aside the Award.

8 On 20 April 2015, the Arbitration Petition was allowed by

the learned Single Judge and impugned Award dated 6 March 2013 in

respect of claim No.1 and 2, was set aside. Hence the present Appeal.

9 The Appellant has challenged impugned Judgment and

order dated 20 April 2015, passed by the learned Single Judge under

Section 34 of the Arbitration Act, thereby prayer clause (a) of the

Petition to the extent of claim Nos. 1 and 2 of the Respondent has

been allowed and thereby, the award of the learned Arbitrator in

respect of claim Nos. 1 and 2 are set aside. The rest of the award has

been upheld.

10 The learned counsel appearing for the Appellant has

strongly relied upon the following contract clause (8) of Special

Condition and thereby, submitted that the Respondent ought to have

permitted the Appellant to provide equivalent brand as an alternative.

"8. Unless otherwise specified, the brand/make of the material as specified in the item nomenclature shall be used in the work. In case of non availability of the brand specified in the contract the Contractor shall be

ssm 6 9-app123.16.sxw

allowed to use alternate equivalent brand of the material subject to submission of documentary evidence of non-availability of the specified brand.

The necessary cost adjustments on account of above change shall be made for the material with wastage

and contractor's profit."

11 After hearing the learned counsel appearing for the

Appellant, we have noted that there is no material and/or documents

placed on record to show that the tiles of M/s. H.R. Johnson (India)

Limited was not available at the relevant time, though it was

specifically agreed by and between the parties to use the same for the

concerned purposes. The Appellant was fully aware of the terms and

conditions of the agreement, by which it was specifically insisted and

also agreed by the Appellant to supply and use the agreed branded

tiles. The reasons behind the selection of those brands, at this stage,

cannot be gone into so also the Respondent's decision to use the said

tiles.

12 The Appellate Court, at this stage, would not like to even

test/accept the submission that the insistence of particular branded

product by the Respondent-Union of India, in view of Section 3 of the

Competition Act, read with Section 23 of the Indian Contract Act,

ssm 7 9-app123.16.sxw

1872, inspite of Clause 8 of Special condition, was impermissible and

contrary to contract conditions. The Appellant was fully aware of the

Competition laws and the related circulars, still instead of raising the

objections at initial stage, submitted the offer for the supply of

branded tiles. The Appellant therefore, was under contractual

obligation to provide/supply the said branded tiles. There was no

case of non-availability of the said tiles. The Respondent's insistence

for the branded tiles, which the Appellant was not ready to supply,

therefore, was within the frame of the contract. The defence of law of

Competition Act, therefore, is unsustainable in the present case.

13 This is also for the reason that the Appellant, in the

commercial contract like this, knowing fully the effect of selection of

the branded tiles by the Respondent, as the insistence of use of

particular brand at the relevant time, in no way can be stated to be

with ulterior motive to favour the brand. The Appellant having

agreed upon therefore, bound by it. There was no choice, unless

specific case made out of non-availability of those branded tiles. The

insistence upon only for equivalent product, as sought to be done by

the Appellant, was contrary to the contract condition.

         ssm                                                     8                                              9-app123.16.sxw




    14                   The Departmental internal quality test and the reasons for 




                                                                                                                  

selecting the brand, therefore, cannot be gone into at the instance of

the Appellant, at this stage. The acceptance of other equivalent quality

tiles after awarding the contract, in the present case, would have

affected the basic terms and conditions of the contract. This would

definitely give leverage to the contractor to use and utilize the other

sub-standard products/tiles.

15 This Court (Coram:- Anoop V. Mohta and S.C. Gupte, JJ.)

1 has already in Indian Oil Corporation Ltd. Vs. Artson Engineering Ltd.

recorded the power and scope of Appellate Bench while deciding the

Appeal. In paragraph No.17 it is observed that:-

"17. The Apex Court in the case of M/s. Chebrolu

Enterprises Vs. Andhra Pradesh Backward Class Cooperative Finance Corporation Ltd. reported in 2015(12) Scale 207, recently reiterated and reinforced the the principle that unless case of perversity and/or error on the face of the record and/or any issue of

jurisdiction is raised which goes to the root of the matter and/or any Award and/or order is contrary to the agreed terms and conditions, no interference is called for by the learned Judge as well as the Appellate Court in the finding of facts. In para 20 of the Judgment, the Apex Court has observed thus:

ssm 9 9-app123.16.sxw

"20. ....This Court or even the Appellant Court would not look into the finding of facts unless

they are perverse."

16 Therefore, taking overall view of the matter and as there is

no perversity. The learned Single Judge has passed the reasoned

order referring to the clauses and conditions so referred above and

interpreted the same correctly. Considering the total rival

submissions, including the clauses and the provisions so read and

referred, we see no reason to interfere with the order passed by the

learned Single Judge.

    17                 Hence, the Appeal is dismissed. No costs.
      



         

             (A.S. GADKARI, J.)                                            (ANOOP V. MOHTA, J.)











 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter