Citation : 2016 Latest Caselaw 4176 Bom
Judgement Date : 27 July, 2016
PVR 1/11 app409-16.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 409 OF 2016
IN
ARBITRATION PETITION NO. 1363 OF 2010
Fugro Survey (India) Pvt. Ltd. )
Fugro House, D-222/30, TTC Industrial )
Area, MIDC, Nerul, Navi Mumbai-400706 )
rep. By its Authorised representative )
Mr.Anant Keshav. )...Appellant
versus
Oil And Natural Gas Corporation Ltd. )
having its office at 11 High, 7th Floor )
Bandra-Sion Link road, Sion, )
Mumbai-400017. )... Respondent
---
Mr.Rajiv K.Pandey i/b. PRS Legal, for the Appellant.
Mr.Pradeep Sanchedi, Senior Counsel with Mr.Subhash Bhalwal i/b. Vyas
Bhalwal, for the Respondent.
----
CORAM : ANOOP V. MOHTA &
G.S. KULKARNI, JJ.
Reserved on : 25th July, 2016.
Pronounced on : 27th July, 2016
----
JUDGMENT: (Per G.S.Kulkarni, J.)
1. This appeal under Section 37 of the Arbitration and
Conciliation Act,1996 (for short 'the Act'), arises from the order dated 6
May 20165 passed by the learned Single Judge whereby the
PVR 2/11 app409-16.doc
Appellant's/Claimant's petition under Section 34 of the Arbitration Act
challenging the award of the Arbitral Tribunal, has been dismissed.
2. The Appellant is the original claimant and the Respondent is
the original Respondent before the Arbitral Tribunal. The dispute
between the parties arose in respect of a contract awarded to the
Appellant by the Respondent for which tenders were invited namely the
contract of "Current Wind and Wave Observations at 6 locations on the East
Coast in India namely KG-KD 8, KG-KD 9, KG-KD 10, KG-KD 11, GD-SW
and GD-NW". The Appellant's offer was accepted by what is termed as a
notice of Award dated 29 October 2003 for the said work of "Current,
Wind and Wave Observation." On 23 December 2013 the parties signed a
formal contract. There is no dispute that the contract which was awarded
was a lump sum/fixed price contract. The agreement in clause 1.1.1
recites that it shall be deemed to have come into effect on the date of
notice of award i.e. 29 October 2003.
3. The Appellant has relied on certain events which have taken
place prior to the execution of the formal contract namely meeting held
on 12 December 2003 between the Appellant and Mr.Bhatnagar, the
representative of the Respondent. This meeting was called as "Basin
PVR 3/11 app409-16.doc
Group Meeting". The case of the Appellant was that a detailed schedule
of the work was prepared in Basin Group Meeting keeping in mind the
actual dates on which drilling operations were to commence at each of the
locations where wind, wave and current operations were to be carried
out, as observations were required to be undertaken prior to
commencement of the drilling work.
4. Also a further event dated 16 December 2003 is relied upon
to state that a team of officers of Indian Navy inspected the vessel to be
used by the Appellant for the work contracted at Vishakapatnam. The
Appellant states that the naval team did not give clearance to the vessel
immediately but stated that such clearance would have to be obtained
from naval headquarter, Ministry of Defence, Delhi. The Appellant's case
is that on 9 January 2004 the naval team once again inspected the
Appellant's vessel and granted partial clearance for wind and wave
observation work and for current observation work upto a maximum
observation period of 48 hours. On 10 January 2004 the naval team also
cleared the deployment of wave buoys. On 11 January 2004 the vessel
hired by the Appellant set sailed for carrying out wind and wave
observation work at the KG-KD-8 and KG-KD-9 locations. Thereafter on 9
February 2004 again the Naval authorities granted clearance for carrying
PVR 4/11 app409-16.doc
out current observation work for 30 days period as per the terms of the
agreement between the parties. Accordingly, on 10 February 2004 the
vessel hired by the claimant set out to sail at KG-KD-10 location for
deploying equipment for "current" observation work at that location. On
11 February 2004 by a fax letter of the Respondent, the Appellant was
informed that drilling operations at KG-KD-10 were to commence by 19
February 2004 and therefore, the Appellant was asked to discontinue the
"current" observations work latest by 18 February 2004. The Appellant
thereafter deployed the observations equipment and moorings at the other
locations. The contract was accordingly performed by the Appellant
during the stipulated period. The Appellant raised invoices dated 1 st/3rd
June 2004 and 22nd June,2004 which were duly paid by the Respondent.
5. The Appellant thereafter raised a dispute claiming certain
additional charges and balance amount due and payable to the Appellant
by the Respondent. These claims were rejected by the Respondent and
the dispute in regard to these claims was thereafter referred for
arbitration before a three member Arbitral Tribunal. The Appellant raised
four claims. Admittedly the only issue as urged and considered by the
learned Single Judge was in respect of claim no.(iv) as raised before the
learned Arbitrator. Claim No.(iv) was as under:-
PVR 5/11 app409-16.doc
"(iv) Claim for balance amount of invoices raised for current observation work on KG-KD-10 for
Rs.47,21,772.25 (admittedly, as against the aggregate amount claimed of Rs.58,25,642, the Respondent has paid
an amount of Rs.12,36,950/- as full and final payment for the 8 days of current observation work that was
carried out by the Claimant.)."
6. Before the Arbitral Tribunal, the parties filed their detailed
pleadings as also documents. The parties led oral evidence and the
witnesses were also cross examined. The Arbitral Tribunal taking into
consideration the relevant clauses under the agreement and more
particularly clause 4.1.1 (Annexure II of the contract) held that the
obligation of taking clearance from the Naval authorities and other
Governmental authorities, for the project work was cast upon the
Appellant as the contractor. After considering the evidence which had
come on record the Arbitral Tribunal rejected the contention as raised on
behalf of the Appellant that the delay in obtaining the clearance was on
account of any breach of the obligation of the Respondent. However
considering the stand of the Respondent reasonable, the Tribunal in
rejecting the Claim No.(iv) (supra) has observed as under:-
"49.... ... ... The Respondent is, therefore, justified in its stand that the contract having been breached by the Claimant, the Claimant is not entitled to any part of the
PVR 6/11 app409-16.doc
lump sum consideration agreed for the 30 days current observation work at KG-KD-10. Nonetheless, the
Respondent has taken a reasonable stand and paid pro- rata a sum of Rs.12,36,950/- for 8 days of the said work
done. Although the Claimant accepted it in full and final settlement when the payment was made, the Claimant has
subsequently raised a dispute for the balance amount of Rs.34,84,822/-. In the view of the Tribunal,the claim for the balance amount is also not justified."
The Arbitral Tribunal thus made the following Award in respect of claim
no.(iv):-
"... ... ...
(iv) Claim for balance amount of invoices raised for current observation work on KG-KD-10 for
Rs.47,21,772.25 (admittedly, as against the aggregate amount claimed of Rs.58,25,642/-, the Respondent has
paid an amount of Rs.12,36,950/- as full and final payment for the 8 days of current observation work that
was carried out by the Claimant) stands rejected."
(emphasis supplied)
7. In rejecting the Section 34 petition as filed by the Appellant,
the learned Single Judge agreed in totality to the above findings as
recorded by the Arbitral Tribunal and held that the delay was fully
attributable to the Appellant and therefore claim No.(iv) was not
justifiable.
PVR 7/11 app409-16.doc
8. The Appellant in assailing the impugned order passed by the
learned Single Judge submits that there was an error on the part of the
Tribunal as also the learned Single Judge in interpreting clause 4.1.1 of
the contract. It is submitted that in fact clause 4.1.1 would pertain to
preparation of vessel for the purpose of contract work to be undertaken.
It is submitted that the finding as recorded by the Tribunal, that there was
some delay on the part of the Appellant to secure clearance from the
Naval authorities is not correct, inasmuch as the Appellant had discharged
its obligation and hence, the delay could not have been made attributable
to the Appellant. It is submitted that both the Arbitral Tribunal and the
learned Single Judge have misconstrued the clauses of the contract and
particularly clause 4.4.1. He, therefore, prays that the appeal be allowed.
9. On the other hand, the learned Senior Counsel appearing for
the Respondent in supporting the finding as recorded by the Arbitral
Tribunal as also the learned Single Judge would submit that the Tribunal
has appropriately taken into consideration the consequences which would
flow from the relevant clauses of the contract. It is submitted that the
forums below after taking into consideration the documents and the
evidence as placed on record, have come to a conclusion that the
PVR 8/11 app409-16.doc
Appellant could not have raised Claim no.(iv)(supra), after receipt of full
and final payment. Learned Senior Counsel would submit that the
obligation was clearly on the Appellant under the relevant clauses of the
contract to obtain those clearances in time. Any expenditure incurred in
relation to the same and / or consequences falling thereunder could not
have been the liability on the Respondent under the contract which was a
fixed contract. The learned Senior Counsel has taken us through the
relevant observations as made in the Award as also the clauses in the
contract in support of his submissions.
10. After having perused the findings as recorded by the Tribunal
in regard to claim No.(iv) as also having gone through the relevant
clauses of the contract, more particularly clause 4.1.1 as also the findings
which are recorded by the learned Single Judge, we are surely not
persuaded by the submissions as made on behalf of the Appellant. The
contract in question was admittedly a fixed price contract or a lump sum
contract and thus, it was not subject to any kind of variation. It was,
therefore, quite natural for the Appellant in agreeing to fixed price
contract to take into consideration all consequential heads of expenditure
on all account when the Appellant agreed to enter into a fixed price
contract. A perusal of the contract also does not support the case of the
PVR 9/11 app409-16.doc
Appellant that the Appellant can sustain any independent / separate claim
under any of the heads. As regards Claim no.(iv), the Appellant has
admittedly raised an invoice after the full and final payment was made by
the Respondent of an amount of Rs.12,36,950/-. The Arbitral Tribunal
has observed that in fact the Appellant had accepted the recovery of
liquidated damages by the Respondent from the Appellant in view of
failure on the part of Appellant in obtaining necessary clearances resulting
in delay in mobilization. The Arbitral Tribunal also held in this regard
that the Appellant never took a position that the delay was not
attributable to it but to the Respondent or by any breach on the part of the
Respondent. It is thus quite clear that the Appellant in raising claim No.
(iv) (supra) has taken a reverse position.
11. The submission on behalf of the Appellant as regards
interpretation of clause 4.1.1 also, in our opinion, is untenable. What
would be relevant, is to note sub-clause (iv) under clause 4.1.1 which
reads thus:-
"4.1.1 It shall be the responsibility of the Contractor to fully comply with the following Security Provisions: ... ... ... ...
(iv) The schedule(s) prescribed in the foregoing paras for advance submissions of details regarding vessel/ personnel clearance is (are) indicative only as the
PVR 10/11 app409-16.doc
clearances are to be accorded by the concerned departments of the Govt. of India. Hence, company will
not be liable for any time and cost impact due to any delays on this account or due to change of procedures etc.
in this regard."
In not accepting the contention as urged on behalf of the Appellant, the
Tribunal as also the learned Single judge has, in our opinion,
appropriately interpreted the contract. The delay in seeking appropriate
approvals was clearly a matter with which only the Appellant was
concerned and that there is no evidence to show that there is any breach
whatsoever or an obligation in that regard on the part of the Respondent
in obtaining of the clearances from the Naval Authorities. The
interpretation of the clause as undertaken by the Tribunal and accepted by
the learned Single Judge is a possible interpretation completely in
consonance to the contract clauses and within the framework of the
contract. Further the Arbitral Tribunal has held that there was no dispute
between the parties that after obtaining clearances the observation work
as regards KG-KD 10 commenced from 10 February 2004. As by letter
dated 11 February 2004 the Respondent requested to stop the work at
KG-KD 10 by 19 February 2004. A finding of fact has been recorded that
there was no dispute that work of "current" observation site location was
carried out by the Appellant only for eight days for which the Appellant
PVR 11/11 app409-16.doc
came to be compensated by making payment of Rs.12,36,950/- and thus,
no amount was due and payable to the Appellant as claimed under Claim
no.(iv). Also the contentions as urged on behalf of the Appellant would
amount to re-appreciation of evidence and coming to a different
conclusion which could not have been the scope, of the proceedings,
under Section 34 of the Arbitration Act.
12. In view of the above deliberation, we are of the clear opinion
that the present appeal does not call for any interference. The findings
which are recorded by the Arbitral Tribunal as confirmed by the learned
Single Judge are within the framework of the contract and the law.
13. As a result, we see no merit in the Appeal. It is accordingly,
rejected. No order as to costs.
(G.S.KULKARNI, J.) (ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!