Citation : 2016 Latest Caselaw 3587 Bom
Judgement Date : 5 July, 2016
Rng 1
APP.233.15.AP736.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL (L) NO.233 OF 2016
IN
NOTICE OF MOTION (L) No.1829 OF 2016
in
ARBITRATION PETITION NO.736 OF 2016
V.Krishnamurthy }
running sole proprietor business
in the name and style of }
M/s Meena Advertisers
having his office at A-11, 3rd floor,
Shree Siddhivinayak Plazaig }
Near Orritel Hotel, Off New Link Road
Andheri (W) Mumbai-400 053 .. Appellant
vs
1. Union of India }
through the Ministry of Law and Justice
Aikar Bhavan, New Marine Lines
Churchgate, Mumbai-400 020. }
2. The General Manager
Western Railways,
Churchgate, Mumbai-400 020 }
3. The Sole Arbitrator
cum Senior Divisional Operating }
Manager,
Western Railways,
Churchgate, Mumbai-400 020. }
.. Respondents
(Ori.Respondents)
Mr.Shailesh Shah Sr.Advocate with Mr.Aditya Chitale
I/b M/s MNSQ Legal for Appellant
Mr.Induprakash Tripathi for Respondents
...
CORAM: ANOOP V.MOHTA & G.S.KULKARNI,JJ
APP.233.15.AP736.16
JUDGMENT RESERVED ON: 27TH JUNE, 2016 JUDGMENT PRONOUNCED ON: 5TH JULY, 2016
ORAL JUDGMENT (Per G.S.Kulkarni, J)
1. This appeal under section 37 of the Arbitration and
Conciliation Act, 1996 (for short the 'Act') is directed against the
order dated 8th June 2016 passed by the learned Single Judge
whereby the appellant'/claimant's petition under section 34 of the
Act has been dismissed upholding the award passed by the learned
sole Arbitrator.
2. The appellant was the beneficiary of a three year
contract of "bulk advertising rights" awarded by the respondents
namely General Manager, Western Railways, Churchgate, Mumbai
for the Andheri, Jogeshwari and Goregaon Railway Stations in
Mumbai. Disputes had arisen between the parties in relation to the
said contract.
3. The appellant inter alia had raised a claim for
Rs.51,88,135/- along with interest against the respondents. The
prayer clauses in the statement of claim, read thus :
" The claimant therefore prays :
APP.233.15.AP736.16
(a) that this Hon'ble Tribunal be pleased to grant an award in terms of the Particulars of Claim annexed at Exhibit N hereto amounting to Rs.51,88,135/- (Rupees
Fifty One Lakh Eighty Eight Thousand One hundred thirty five only) that this Hon'ble Tribunal be pleased to direct the respondent to pay interest and/or compensation and also loss of reputation by invoking bank guarantee on the amount to be awarded under the Statement of Claim from the date of Award till payment
and/or realization at an exemplary rate to be fixed and/or decided by the Hon'ble Tribunal being not less than 18% per annum simple rate of interest;
(b) that this Hon'ble Tribunal be pleased to award
costs of this Arbitration Reference and of all the proceedings precedent thereto by directing the respondent
to pay the same to the claimant;
(c) this Hon'ble Tribunal may be pleased to pass further necessary orders as this Hon'ble Tribunal may deem fit
and proper."
4. The dispute underlying the above claim of the
appellant was on the basis of an interim contract awarded by the
respondents for the said advertisement work for a period of three
months till finalization of the main contract under the tender issued
by the respondents. In this regard the appellant by its letter dated 5
September 2006 offered to take up advertisement rights from the
respondents-railways at the above stations on interim basis. This was
at the same rate as for the main three year contract, namely at
Rs.1,32,00,000/- which came to Rs.11,00,000/- per month as stated
by the appellant in the said letter. In this letter, the appellant
requested the respondents to provide 15 days gestation period from
APP.233.15.AP736.16
the date of the contract for business arrangement to be undertaken at
these three stations. The appellant also stated that the interim
award period be fixed till a final award letter in respect of the main
tender is issued in favour of the appellant.
5. The respondents by their letter dated 13 September
2006 accepted the above offer of the appellant. It would be useful
to refer to the contents of the said letter, as the controversy between
the parties in the arbitration proceedings revolve around the
"gestation period" as agreed between the parties. This letter of the
respondents reads thus:
" The competent authority has sanctioned the awarding of contract for Bulk Advertising Rights of
Andheri station alongwith Goregaon and Jogeshwari as one whole cluster for an interim period on month to
month basis till finalization of tender or maximum of 03 months at the same rate as bidded in the above referred tender and offered by you i.e. Rs,.11,00,000/- per month.
The administration has agreed your request
for granting 15 days as gestation period for putting up displays subject to condition that after finalization of tender, the contract period will start from the date of letter of acceptance and no gestation/grace period would be given."
(emphasis supplied)
6. It is clear from the above letter of acceptance that the
respondents had agreed to the request of the appellant for granting
15 days as gestation period for installation of the advertisement
subject to the condition that after finalization of the main three year
tender, the contract period would start from the date of letter of
APP.233.15.AP736.16
acceptance and no gestation/grace period would be given. As can be
seen, this letter of the respondents reiterated that the interim
contract would commence after 15 days of the receipt of the above
letter or date of display whichever is earlier on the same tender
terms and conditions. There is no dispute on the fact that for the
interim contract the appellant had made payment of Rs.11,00,000/-
to the respondents for the first month, in pursuance of the
respondents' above letter dated 13 September, 2016.(supra).
7. Under this interim contract, the appellants were
accordingly granted a gestation period from 9 October 2006 till 28
October 2006. Thereafter, on 12 December 2006 another contract
came to be awarded to the appellant under which the gestation
period up to 28 December 2006 was granted and thereafter the
appellant removed its display on 28 December 2006.
8. On 19 January 2007 the appellant was informed by
the respondents about the acceptance of the appellants offer under
the main tender and was called upon to make payment under the
same. On 27 January 2007 the appellant paid an amount of
Rs.66,00,000/- to the respondents.
APP.233.15.AP736.16
9. As regards the main tender which was for three
years, an agreement dated 13 April 2007 came to be executed
between the parties. This agreement in clause 5.2 provided for
commencement period which provided as under :
"5.2 Commencement period
D: Day of issue of Letter of Acceptance
D+10 days: (1) Payment of full annual licence fee in ig case of the annual licence fee quoted is less than Rs.One crore/annum.
(2) In case annual Licence fee quoted is
more than Rs.One crore per annum
payment of 50% of annual Licence fee
D+15: Issue of Authority letter
D+30: Submission of Bank guarantee
D+40: Signing of the Agreement with Railway
Administration.
D+45: Commencement of the contract
(maximum)"
(Emphasis supplied)
10. The contention on behalf of the appellant before
the learned Arbitrator was that the appellant had not utilized
gestation period of 15 days under the interim Award and that the
appellants by their letter dated 14 September 2006 had intimated
respondent that the appellant would not be utilizing 15 days
gestation period under the said interim award of the contract. The
appellant therefore, asserted that under the main award of the
contract the appellant was entitled to gestation period of 30 days as
APP.233.15.AP736.16
per condition 5.1,D+45 (supra) and accordingly raised a claim.
11. On the other hand, it was the respondent's case before
the learned Arbitrator that the appellant had accepted the contract
on interim basis based on the gestation period of 15 days as informed
to the appellant in the respondent's letter dated 13 September 2006
(supra) which was nothing but the appellant's offer as accepted by
the respondents. The appellant thus would not be entitled to any
gestation in the main contract awarded by the respondents. As the
appellant did not make payment of the contractual amount and
within the time prescribed thus the respondent nos. 1 and 2 also
demanded compensation in terms of the contract and in that regard
raised a counter claim before the learned Arbitrator.
12. The learned Arbitrator however, did not find any
merit in the claim as made by the appellants on the basis of the
gestation period and rejected the appellant's claim.However, the
respondent's counter claim in regard to the outstanding licence fees
at Rs.97,73,030/- was awarded.The learned Arbitrator in awarding
the counter claim in favour of the respondents has observed as under
:
APP.233.15.AP736.16
" The claimant in his affidavit did not opted to contest
the statement submitted by the respondent which stipulates the period of contract amount due, amount paid, delayed days, period of delayed days, interest on
late payment tabulated for the entire contract which amounts to Rs.97,73,030/-"
13. On a challenge being raised by the appellant to
the award of the learned Arbitrator, the learned single Judge having
examined the issues rejected the appellants' Section 34 petition,
upholding the award of the learned Arbitrator.
14. ig Mr.Shah learned senior counsel for the appellant
in support of the appellants plea, would submit that the learned
arbitrator as also the learned single Judge have failed to appreciate
that by the appellant's letter dated 14 th September 2006, the
appellant had informed the respondents of not utilizing 15 days
gestation period in respect of the interim award and that the
appellant would be utilizing the gestation period as per the terms
and conditions of the regular award of the tender. It is therefore,
submitted that clause 5.2 of the main tender which provides for
commencement period to be D+45 was required to be considered
and benefit of 30 days gestation period ought to have been entitled
to the appellant. It is submitted that the learned Arbitrator therefore,
ought to have allowed the appellant's claim. No other issue was
APP.233.15.AP736.16
raised on behalf of the appellant in assailing the impugned orders
passed by the learned Single Judge.
15. We are not persuaded to accept the submissions
as urged on behalf of the appellant. From the facts which we have
noted above, it is clear that the appellant was a beneficiary of an
interim award which was on the appellant's own offer as made under
its letter dated 5 September 2006. In this letter, the appellant had
categorically offered that the respondents should provide 15 days
gestation period from the date of interim contract for business
arrangements to be made at these three railway stations. The
respondents by their letter dated 13 September 2006 accepted the
offer of the appellant for the interim award, of the said advertisement
contract, for three months at the same rate as per the bid in the
main tender and accepted the offer of the appellant for granting 15
days gestation period for putting up the display. However, this was
subject to a condition that after finalization of the main tender the
contract period would start from the date of the letter of acceptance
and no gestation/grace period would be given. It is therefore, clear
that the award of the main contract was subject to this condition of
the appellant availing 15 days gestation period under the interim
APP.233.15.AP736.16
contract and that the main contract would start from the date of
letter of acceptance and no gestation/grace period would be given.
This was the manner and/or method in which the parties agreed to
treat the gestation period in regard to the final contract. The
contention of the appellant that after award of the final contract the
letter of acceptance dated 13 September 2006 of the respondents for
the interim award should be discarded and as regards gestation
period full benefit under clause 5.2 of the main agreement dated 13
April 2007 (supra) be granted to the appellant cannot be accepted.
The interim award of the contract was inter-linked to the main
contract in relation to the gestation period as we have discussed
above. This was the agreement between the parties. Before the
learned arbitrator the appellant was not permitted to take a position
reverse and/or contrary to what it had agreed namely that the main
contract would start from the letter of acceptance and no gestation
period would be availed, in asserting its claim.
16. We also cannot accept the submission as made on
behalf of the learned counsel for the appellant on the basis of the
appellants' letter dated 14 September 2006 for the reason that the
letter dated 5 September 2006 was the offer of the appellant for the
APP.233.15.AP736.16
interim award which came to be accepted by the respondents-
railways by their letter dated 13 September 2006. (supra).
17. The appellants' letter dated 14 September 2006 was
post-acceptance of the appellant's offer by the respondent, and
contained conditions in deviation from what was accepted by the
respondents in the acceptance letter dated 13 September 2006.
Significantly, the conditions as put by the appellant in this letter
dated 14 September 2006 were never accepted by the respondents.
This being the position the appellant would not be correct in
contending that the counter condition as asserted on behalf of the
appellant in letter dated 14 September 2006 be enforced against the
respondents. The learned Arbitrator has appropriately recorded
findings of fact in regard to the gestation period and declined to
accept the claim as made by the appellant as also confirmed by the
learned Single Judge.
18. In view of the above discussion, we are of the clear
opinion that the appeal is devoid of any merit and it is accordingly
rejected. No order as to costs.
APP.233.15.AP736.16
19. In view of the order passed in the appeal, notice of
motion (L) No.1829 of 2016 does not survive and is accordingly
disposed of.
G.S.KULKARNI, J ANOOP V.MOHTA, J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!