Citation : 2016 Latest Caselaw 7236 Bom
Judgement Date : 15 December, 2016
WP No. 7502/14
1
IN THE HIGH COURT AT BOMBAY
APPELLATE SIDE, BENCH AT AURANGABAD
WRIT PETITION NO. 7502 OF 2014
Godavari Marathwada Irrigation
Development Corporation,
Through Executive Engineer,
Majalgaon Project Division,
Kesapuri Camp, Majalgaon,
Beed. ....Petitioner.
Versus
M/s. Ghai Construction Engineers
and Contractors, Plot No. 289, N-3,
CIDCO, Aurangabad. ....Respondent.
WITH
WRIT PETITION NO. 7503 OF 2014
Godavari Marathwada Irrigation
Development Corporation,
Through Executive Engineer,
Majalgaon Project Division,
Kesapuri Camp, Majalgaon,
Beed. ....Petitioner.
Versus
M/s. Ghai Construction Engineers
and Contractors, Plot No. 289, N-3,
CIDCO, Aurangabad. ....Respondent.
Mr. P.M. Shah, Senior Counsel i/b. Shri. S.G. Bhalerao, Advocate
for petitioner.
Mr. A.K. Gawali, Advocate for respondent.
CORAM : T.V. NALAWADE, J.
DATED : 15th November, 2016.
ORAL JUDGMENT :
1) Rule. Rule made returnable forthwith. By consent,
WP No. 7502/14
heard both the sides for final disposal.
2) The proceedings are filed to challenge the order of
dismissal made by Ad-hoc District Judge, Beed in proceedings
which were filed under section 34 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as 'the Act' for
short).
3)
The proceedings were filed by present petitioner to
challenge the award given by Arbitrator in favour of the
contractor. The award was given on 14.2.2002 and the
proceedings under section 34 the Act were filed on 4.5.2002.
Thus, the proceedings were filed within 90 days, as per the
period mentioned in section 34 of the Act. It appears that office
of the District Court had raised four objections during scrutiny
and they were as under :-
"01. That, applicant not shown para of valuation for jurisdiction and court fees.
02. That, applicant not mentioned name as he Executive Engineer in capacity file this application.
03. Court fees affix Rs.50/- and application is setting aside order of award as application is in a monetary grain.
04. That, application filed beyond the limitation i.e. date of award 14.02.2002 and filed on
WP No. 7502/14
04.05.2002 The concern advocate be heard on above
points as tenability"
After that, following orders were made
"ORDER DT. 25.06.2002 Advocate be heard as sought in office note, within two weeks."
"ORDER DT. 30.12.2003
the
The office objections are not removed by that time proceeding shall dismissed for want of compliance."
Sd/-
IInd Ad-hoc Addl. Dist. Sessions Judge, Beed."
4) The learned Senior Counsel for petitioner submitted
that the objections were not valid objections. The learned Senior
Counsel submitted that so far as objection No. 1 is concerned,
there was no question of showing valuation for jurisdiction and
Court fees as every award needs to be challenged under section
34 before the Court mentioned in section 34 of the Act and that
jurisdiction is given irrespective of value of the award. The
learned Senior Counsel submitted that there was no meaning in
the second objection as the title of proceeding filed under
section 34 shows that Executive Engineer of the concerned
project had signed the proceedings and through him, the
WP No. 7502/14
petitioner had filed the said proceedings. The learned Senior
Counsel submitted that there was no need to mention the name
of Executive Engineer and this power is given to the persons by
virtue of the post and the persons holding the post do change.
5) The learned Senior Counsel submitted that the third
objection could not have been raised as the Court fees was not
payable in such proceedings and first time, due to the
amendment made in the year 2009 in the Court Fees Act, the
Court fees became payable on the basis of valuation of the
matter.
6) The learned Senior Counsel submitted that there was
no room to take fourth objection as in section 34 itself, the
period of 90 days is given for filing proceeding under section 34
of the Act and the proceeding was filed within this period.
7) This Court holds that all the aforesaid submissions
made by the learned Senior Counsel need to be accepted. It is
not disputed that prior to year 2009, the Court fees was not
payable for such proceedings and so, objection at Sr. Nos. 1 and
3 could not have been raised. The Corporation like petitioner can
authorize its officer by naming the post to file the proceeding
WP No. 7502/14
and so, there cannot be insistence of naming officer. Thus, all
the four objections could not have been raised. It is unfortunate
that the Court considered all the four objections as valid
objections. When the Court passes order of dismissal for not
removing office objections, the Court is expected to apply mind
and even when the counsel for applicant or plaintiff is absent.
The Court is expected to ascertain as to whether the objections
are valid. The objections raised by the clerical staff are accepted
as they are and aforesaid circumstances are not considered and
so, it can be said that the Court did not apply judicial mind. In
any case, the aforesaid objections could not have been raised
and as the proceedings were filed within 90 days, the
proceedings ought to have been registered.
8) The learned counsel for respondent, contractor
raised objection to the tenability of the present proceedings. The
learned counsel submitted that the order dated 30.12.2003
made by the District Court was one under provision of Order 7,
Rule 11 of Civil Procedure Code. He submitted that in view of the
definition of 'decree' given in section 2 (ii) of Code of Civil
Procedure, such order needs to be treated as 'decree' and so,
the appeal ought to have been filed. On this point, the learned
Senior Counsel for petitioner drew the attention of this Court to
WP No. 7502/14
provision of section 37 of the Act and submitted that appeal is
not tenable. The provision of section 37 is as under :-
"37. Appealable orders.- (1) An appeal shall lie from the following orders and from no others to the Court authorised by law to hear appeals from
original decrees of the Court passing the order, namely:-
(a) refusing to refer the parties to
arbitration under section 8;
(b) granting or refusing to grant any
measure under section 9;
(c) setting aside or refusing to set aside
an arbitral award under section 34.
(2) An appeal shall also lie to a Court from an
order of the arbitral tribunal-.
(a) accepting the plea referred to in sub-
section (2) or sub-section (3) of section 16; or
(b) granting or refusing to grant an interim measure under section 17.
(3) No second appeal shall lie from an order passed in appeal under this section, but nothing in this section shall affect or take away any right to appeal to the Supreme Court."
When there is Special Legislation, the provisions made for
particular purpose in Special Legislation need to be used and the
general law made available in Civil Procedure Code cannot be
used. The provision of section 37 of the Act shows that no appeal
WP No. 7502/14
is provided under this section, under Special Law to challenge
the present order of Ad-hoc District Judge. On this point, the
learned Senior Counsel for petitioner placed reliance on the
observations made by the Division Bench of this Court in case
reported as 2006 (6) Mh.L.J. 678 [State of Maharashtra and
Anr. Vs. Ramdas Construction Co. and Anr.]. In that case,
the order of rejection of delay condonation application made by
the District Court was challenged by filing appeal under section
37 of the Act. This Court held that under section 37, no appeal is
provided to challenge the order made on delay condonation
application. The learned Senior Counsel submitted that these
observations can be used for the present purpose also in view of
the nature of order made and the specific provision of section 37
of the Act. This submission need to be accepted. Thus, the
petition is tenable.
9) The learned counsel for respondent submitted that in
the past, only filing of proceeding under section 34 was sufficient
for employer or contractor as the fact of filing proceeding itself
was making the award unenforcable and the filing of proceeding
was giving automatic stay to the execution of the award. The
learned counsel for respondent submitted that there is possibility
that the petitioner intentionally did not take steps before the
WP No. 7502/14
District Court. The learned counsel for respondent submitted
that the present proceeding came to be filed after about 11
years and due to latches, the petitioner is not entitled to any
relief.
10) The learned Senior Counsel submitted that the
petitioner Corporation first time realized that the aforesaid order
was made in matter filed by it, when order of attachment came
to be made in execution proceeding filed by the contractor in the
year and when show cause notice was issued for attachment of
Bank account. The learned Senior Counsel submitted that the
Corporation then deposited the amount of Rs. one Crore in each
matter to show bonafides. The learned Senior Counsel submitted
that this circumstance also needs to be taken in to consideration
in the present proceeding.
11) The aforesaid circumstances of the present matters
show that it is a peculiar case. Though the present proceedings
came to be filed after about 11 years to challenge the order, the
fact remains that the order under challenge could not have been
made by the learned Ad-hoc District Judge. In view of these
circumstances and as the public money is involved in the matter,
this Court holds that the order needs to be set aside. No loss will
WP No. 7502/14
be caused to contractor as interest meter will continue to run.
12) The learned counsel for respondent placed reliance
on some observations made by the Apex Court in the case
reported as 2013 ALL SCR 3236 [Esha Bhattacharjee Vs.
Managing Committee of Raghunathpur Nafar Academy
and Ors.]. The Apex Court has quoted the considerations which
are required to be kept in mind while dealing with the application
filed for delay condoantion. There cannot be dispute over the
proposition made by the Apex Court in the case cited supra. The
facts and circumstances of each and every case are always
different. Peculiar facts of the present case are already quoted
by this Court.
12) In the result, the petitions are allowed. The orders
made by the learned Ad-hoc District Judge by which the
proceedings filed under section 34 of the Act by the present
petitioner were dismissed are hereby set aside. The proceedings
are to be treated as proceeding filed under section 34 of the Act
on 4.5.2002 and registration date is to be shown as 4.5.2002. As
the proceedings were filed in the year 2004 itself, the law which
was prevailing in the year 2004 will be applicable. The amount
deposited by petitioner as per the order made by this Court is
WP No. 7502/14
allowed to be withdrawn by petitioner.
Rule is made absolute in aforesaid terms.
Time of four weeks is given to the other side to
challenge the order made by this Court.
[ T.V. NALAWADE, J. ] ssc/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!