Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of Maharashtra & 3 Others vs Deorao Manikrao Malve
2016 Latest Caselaw 4729 Bom

Citation : 2016 Latest Caselaw 4729 Bom
Judgement Date : 19 August, 2016

Bombay High Court
State Of Maharashtra & 3 Others vs Deorao Manikrao Malve on 19 August, 2016
Bench: B.R. Gavai
                                           1                  WP3568-04.odt         



             IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                           
                               NAGPUR BENCH : NAGPUR




                                                   
                              Writ Petition No.3568/2004
                                           ...




                                                  
    1. The State of Maharashtra,
       through its Secretary,
       Irrigation & Power Department,
       Mantralaya, Mumbai -32.




                                               
    2. The Superintending Engineer,
       Upper Wardha Project Circle,
                             
       Shivaji, Amravati.

    3. The Superintending Engineer,
       Nagpur Irrigation Project Circle,
                            
       Irrigation Department,
       Sinchan Sewa Bhavan, Nagpur.

    4. The Superintending Engineer,
       Akola Irrigation Circle (Zone),
      


       B & C Compound Area, Akola.                ..         PETITIONERS
   



                                   .. Versus ..





    Deorao Manikrao Malve,
    Aged about 60 years,
    Occupation: Retired,
    R/o C/o G.M. Malve,
    Plot No.193, Omnagar,
    Sakkardara, Nagpur.                           ..         RESPONDENT





    Mr. M.K. Pathan, AGP for Petitioners.
    Mr. G.N. Khanzode, Advocate for Respondent.

                                   ....


                  CORAM : B.R. Gavai & V.M. Deshpande, JJ.

DATED : August 19, 2016.

2 WP3568-04.odt

ORAL JUDGMENT (per B.R. Gavai, J. )

1. The petitioner has moved Civil Application No.1807 of

2016 for early hearing. The application is allowed. The petition is

taken up for hearing forthwith.

2. The petition challenges the order passed by the learned

Maharashtra Administrative Tribunal in Original Application No.

1081/1994 thereby partly allowing the original application filed by

the respondent.

3. The respondent had approached the learned Tribunal

vide Original Application No. 1081 of 1994 contending that since he

had passed the examination of Sub-Overseer on 3.8.1974, he

should have been promoted as Sub-Overseer from that date. It

was further contended that the promotion granted to the applicant

as Sub-Overseer with effect from 1.8.1979 was not legal and he

should have been granted the said promotion from 3.8.1974. It

was further the contention of the original applicant that he had

appeared for the professional examination for Junior Engineer held

during October, 1983 and he was declared successful vide

communication dated 27.02.1984. It was, therefore, contended

that the original applicant was entitled to be promoted as Junior

Engineer with effect from 15.2.1986. It was also contended by the

original applicant that the juniors to him in the cadre of the Sub-

                                               3                         WP3568-04.odt         


    Overseers         were promoted as Junior Engineers prior to him,

therefore, he was entitled to the promotion of Junior Engineer with

retrospective effect.

4. The learned Tribunal partly allowed the original

application and held that the applicant was entitled to be absorbed

on the post of Sub-Overseer from 3.8.1974. Insofar as the rest of

the reliefs are concerned, the learned Tribunal granted liberty to

the original applicant to make representation to the authorities

within the specified period.

5. Mr. Pathan, learned AGP appearing on behalf of the State

submitted that the learned Tribunal has grossly erred in partly

allowing the original application. It is submitted that at the relevant

time there were vacancies available and as such the order passed

by the learned Tribunal giving retrospective effect is not

sustainable in law.

6. Mr. Khanzode, the learned counsel appearing on behalf

of the petitioner-original applicant submitted that no interference is

warranted with the sound reasonings given by the learned Tribunal.

7. The perusal of the record would reveal that it is an

admitted position that the respondent had passed the examination

of Sub-Overseer on 3.8.1974. The learned Tribunal has further

4 WP3568-04.odt

found that as per the provisions of the relevant Government

Resolution, the learned Tribunal upon perusal of the relevant

Government Resolution came to the conclusion that it was not the

case of the State that the respondent was considered for promotion

by the Departmental Promotion Committee and was not found to

be suitable. The learned Tribunal further found that the G.R. dated

19.12.1963 provides absorption of the Technical Assistants/Work

Inspectors as Sub-Overseers after qualifying the departmental

examination meant for Sub-Overseers. As such no fault could be

found with the finding of the learned Tribunal that the original

applicant was entitled to be absorbed in the cadre of Sub-Overseer

with effect from 3.8.1974 i.e. the date on which the original

applicant was found to be qualified in the qualifying examination.

8. In that view of the matter, no error could be found with

the approach adopted by the learned Tribunal. The petition is

found to be without merit. The same is, therefore, rejected. Rule is

discharged.

9. Since there was no interim order operating in the present

writ petition, the order passed by the learned Tribunal ought to

have been complied with by the State. However, it is submitted in

the application which was filed in the present writ petition for early

hearing that the dues to which the respondent was entitled are not

paid to him. We, therefore, direct the State to give effect to the

5 WP3568-04.odt

judgment and order passed by the learned Tribunal If not already

given along with the interest @ 6 % P.A., within a period of three

months from today. It is made clear that all arrears to which the

respondent is entitled as per the judgment and order passed by the

learned Tribunal shall be paid to the respondent-employee within a

period of three months in any case.

        (V.M. Deshpande, J. ) ig            (B.R. Gavai, J.)
                                        ...
                            
      
   







                                              6                      WP3568-04.odt         




                                                                                 
                                   Certificate




                                                         

I certify that this judgment uploaded is a true and correct copy of original signed Judgment.

Uploaded by : R.G. Halwai, Uploaded on : 23.08.2016

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter