Citation : 2016 Latest Caselaw 1986 Bom
Judgement Date : 28 April, 2016
mub 1 7 wp 10044.15.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 10044 OF 2015
The Central Board of Trustees ... Petitioner
Vs.
M/s. Hotel Leelaventure Ltd. ... Respondent
.....
Mr. Suresh Kumar for the petitioner.
Mr. Mr. S.C. Naidu a/w. Mr. T.R. Yadav a/w. Mr. Aniket Poojari i/b.
C.R. Naidu & Co. for the respondent.
....
CORAM : S.C. GUPTE, J.
DATE : 28.04.2016.
ORAL JUDGEMENT:
1. Heard learned counsel for the parties. The subject matter of
challenge in this petition is an order passed by the Provident Fund
Appellate Tribunal. The controversy before the Appellate Tribunal
consisted of calculation of damages that could be levied on the
Respondent-employer for the delay in payment of provident fund dues.
The dues included employees' contributions which were deducted by the
Respondent-employer but not deposited with the provident fund
authorities. The impugned order directed payment of damages under
Section 14-B of the Employees Provident Funds and Miscellaneous
Provisions Act 1952 ("the Act") and simple interest, addition to these
damages under section 7-Q of the act, calculated on the basis of the
payment by the Respondent-employer reflected in the bank certificate.
2. The basis of the challenge by the provident fund
organisation is that Section 14-B of the Act empowers the Central
mub 2 7 wp 10044.15.odt
Provident Fund Commissioner to recover from the employer an amount
not exceeding the amount of arrears by way of penalty, if a default is
made in payment of any contribution by the employer. It is submitted, in
the first place, that there was no reason for the Appellate Tribunal to
restrict the quantum of damages to 25%. Secondly, it is submitted that
the order of the Regional Provident Fund Commissioner, which was
varied in the appeal by the Appellate Tribunal, correctly required the
calculation of the damages under Section 14-B payable upto
25/09/2008 at the rate of upto 37% in accordance of paragraph 32-A of
the Employees Provident Fund Scheme, 1952, which was applicable as
on the date of 25/09/2008 and thereafter at the rate of upto 25% under
amended paragraph 32-A of the scheme introduced with effect from
26/09/2008.
3. Insofar as damages payable under Section 14-B of the Act
are concerned, there is an authority in the Provident Fund
Commissioner to recover a maximum amount not exceeding the amount
of arrears as and by way of penalty. This is an outer limit of any penalty
that may be charged. The provision of penalty is further circumscribed
by the expression "as may be specified in the scheme", appearing in
Section 14-B. The net result of the two limitations, namely, the upper
limit of 100% of arrears and the specification of the scheme, is that the
amount of damages could only be upto 100% of the amount of arrears
or the damages specified in the scheme, whichever is lower. The
mub 3 7 wp 10044.15.odt
scheme as it operates today provides for the maximum rate of damages
as 25% of the arrears per annum. Thus, the damages could not exceed
25% of the arrears per annum. The judgment of the Division Bench of
Delhi High Court in the case of Systems and Stamping and Anr. V/s.
Employees Provident Fund, Appellate Tribunal and Ors., 1 accordingly,
awarded damages at the flat rate of 25% per annum. This judgment was
affirmed by the Supreme Court when the matter was carried before it in
a Special Leave Petition. In another case, Delhi High Court in a Full
Bench decision in Roma Henny Security Services Pvt. Ltd. Vs. Central
Board Trustees2 once again awarded a flat rate of 25% based on the
provident fund scheme as amended by the new paragraph 32-A.
4. The next contention urged by the Petitioner's counsel is that
damages ought to be calculated upto 25/09/2008 under paragraph 32-A
of the scheme as it then subsisted (providing for damages @ 37%). With
effect from 26/09/2008 a new paragraph 32-A was introduced in the
scheme (providing for the rate of 25%). Accordingly, it is submitted
that damages should be upto 37% of arrears per annum upto
25/09/2008 and thereafter at the rate of 25% per annum, in both cases
in addition to interest at the rate of 12% per annum under Section 7-Q
of the Act. Even this contention was considered by Delhi High Court in
the two cases noted above. The Division Bench of Delhi High Court in
the case of Systems and Stamping (Supra) held that interest was to be
1 2008-II-LLJ-939 2 2012 (135) FLR 799
mub 4 7 wp 10044.15.odt
calculated even for the period prior to 25/09/2008 at the flat rate of
25% per annum together with simple interest at the rate of 12% per
annum under section 7-Q (after 01/07/1997) and not damages at the
rate of 37% per annum together with interest at the rate of 12%. The
position was further explained by Delhi High Court in its Full Bench
judgment in the case of Roma Henny Security Services Pvt. Ltd.
(Supra). The Court explained the position thus:
"11. It is not in dispute that if the judgment of M/s.
System and Stamping (supra) is to be followed, the case is covered in favour of the petitioner. However, we find substance in the submission of learned Counsel for the
respondent that in the said judgment the Division Bench entirely rest upon the Office Memorandum dated 29.05.1990 on the basis of which the Bench came to the conclusion that interest element chargeable under section 7-Q of the Act was included in the table prescribing
damages payable under section 14-B of the Act. As we will demonstrate hereinafter, there were various other
subsequent Circulars which were not taken into account. In the first instance, it needs to be pointed out that the Office memorandum referred to by the Division Bench was
dated 29.05.1990. It was issued at the time when section 7-Q was not made effective. Pertinently, this provision was introduced in the Act in the year 1988 but was made effective only from 01.07.1997. Since the provision was not in force as on 29.05.1990, it appears that by that
mechanism which was applied administratively was to include the component of interest while imposing the damages under section 14-B of the Act. However, the position changed after section 7-Q of the Act was in force w.e.f. 01.07.1997. The interest on delayed contribution of provident fund became payable statutorily. While this was so, the aforesaid table continued to operate which has now been modified and replaced by the another table made effective from 26.09.2008 and the rates of damages as per the revised table are as under:-
12. It is clear from the above that w.e.f. 26.09.2008 the damages under section 14-B of the Act are charged on
mub 5 7 wp 10044.15.odt
the aforesaid basis which would show, for example if the period of default is less than two months, the damages
payable are 5%. However, the table which was governing upto this date and is noted in the judgment of M/s. System and Stamping (supra), the damages for the period of
default of less than two months were 17%. Same is the position in respect of other periods of default when the two tables are kept in juxtaposition it would clearly revealed that the damages are now reduced by 12% at every stage
meaning thereby component of interest under section 7-Q is now removed. The comparison of the aforesaid two would show that upto 26.09.2008 the earlier table continue to govern which included the element of interest
under section 7-Q of the Act. From 26.09.2008 onwards, however the two are segregated. This would clearly bolster
the stand of the petitioner that if the earlier table is applied which was so done, interest payable under section 7-Q of the Act was already included."
5. I am in respectful agreement with the view expressed, and
reasons indicated, by Delhi High Court in the above cases.
6. In that view of the matter, there is no merit in either of the
challenges before this Court. The order of the Appellate Tribunal
requiring that quantum of damages to be restricted to 25% of arrears
per annum with simple interest under Section 7-Q of the Act re-
quantified in accordance with the bank certificate submitted by the
Respondent-employer, cannot be found fault with. The petition is,
accordingly, dismissed. No order as to costs.
(S.C. GUPTE, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!