Citation : 2016 Latest Caselaw 1708 Bom
Judgement Date : 21 April, 2016
mca44.16
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH : NAGPUR
Misc. Civil Application [Arb.] No. 44 of 2016
M/s. Khare & Tarkunde
Infrastructure Pvt. Ltd.
through its Director Shri
Makarand S. Bhagwat, having
its Registered Office at 1st and
2nd floor, Shivaji Complex,
235, West High Court Road,
Dharampeth, Nagpur. ..... Applicant.
Versus
Municipal Council, Malkapur,
through its Chief Officer,
Opp : Telephone Exchange,
Nandura Road,
Distt. Buldana. ..... Non-Applicant.
*****
Shri A.V. Khare, Adv., for the Applicant.
Shri N.R. Saboo, Adv., for the Non-applicant.
*****
CORAM : Z. A. HAQ, J.
Date : 21st April, 2016
ORAL JUDGMENT:
01. Heard Shri A. V. Khare, learned Adv., for the applicant and
mca44.16
Shri N.R. Saboo, learned Adv., for the Non-applicant.
02. Rule. Rule is made returnable forthwith.
03. The applicant has filed this application under Section 11 of
the Arbitration & Conciliation Act, 1996, praying that an Arbitrator be
appointed to resolve the dispute between the parties.
04. According to the applicant, he has undertaken the
construction of a Shopping Complex and Departmental Stores for the
Non-applicant as per the Work Order dated 12th July, 2007. The
applicant claims that the amount of Rs. 1,57,71,410/- receivable by the
applicant is not paid by the Non-applicant. The applicant claims further
amount of Rs.3,60,15,228-00. The applicant issued notice dated 26th
October, 2015 through his Advocate, calling upon the Non-applicant to
pay the amount of Rs.5,17,86,638-00. This notice was not replied by
the Non-applicant and, therefore, the applicant sent the
communication dated 10th November, 2015 proposing that the matter
be referred for arbitration to Shri Dilip N. Potdukhe, Retired Chief
Engineer, Public Works Department. The dormancy on the part of the
Non-applicant continued and there was no response from the Non-
applicant and, therefore, the applicant approached this Court by this
mca44.16
application.
05. The application is opposed on the ground that the dispute is
not covered by Clause 24 of the Special Conditions of the Contract and
the claim made by the applicant cannot be referred to arbitration
under Clause 25.3 of the Special Conditions of Contract. Shri N.R.
Saboo, learned Adv., for the Non-applicant, has submitted that under
the Special Conditions of Contract, arbitration can be only in matters
arising out of a decision of the Engineer; but the claim of the applicant
is for unpaid bills for the works alleged to have been done by him and,
therefore, the claim made by the applicant is not arbitrable as per the
Special Conditions of Contract. It is further submitted that the
applicant has made claim for four items, out of which two items are
covered by the bid document and two claims are not covered by the
bid document and, therefore, the applicant cannot resort to Clause
25.3 of the Special Conditions of Contract to seek arbitration of the
dispute. In support of the submission, reliance is placed on the
Judgment given in the case of Wellington Associates Ltd., Vs. Kirit
Mehta reported in (2000) 4 SCC 272.
06. After hearing learned Advocates for the respective parties, I
find that the claim made by the applicant is not a stale claim. The
mca44.16
parties are not ad idem on the point that the dispute is required to be
referred for arbitration as per the Special Conditions of Contract. The
existence of contract between the applicant and the non-applicant is
not disputed. Shri A.V. Khare, learned Adv., for the applicant, has
rightly relied on the Judgment given in the case of SBP & Co. Vs.
Patel Engineering Ltd. & another reported in (2005) 8 SCC 618,
and has submitted that the dispute between the parties is arbitrable or
not as per the Special Conditions of Contract will have to be decided by
the Arbitrator. Hence, in my view, arbitrator is required to be
appointed.
07. The applicant had proposed the name of Shri D.N. Potdukhe,
Retired Chief Engineer, Public Works Department, to be the Arbitrator.
The Non-applicant has filed reply before this Court opposing the claim
of the applicant for referring the matter to arbitration, but has not
stated that Shri D.N. Potdukhe cannot be appointed as the Arbitrator.
08. The learned Adv., for the applicant has referred to Clause
25.3 (a) of the Special Conditions of Contract, and has submitted that
the dispute has to be considered by Arbitral Tribunal of three
Arbitrators, one to be appointed by the applicant, one to be appointed
by the Non-applicant and the third Arbitrator shall be
mca44.16
Consultant/Engineer as Presiding Arbitrator. It is submitted that if at all
this Court is of the opinion that the dispute between the parties is
required to be resolved by arbitration, the Arbitral Tribunal of three
Arbitrators has to be appointed as per Clause 25.3 (a) of the Special
Conditions of Contract.
In my view, this submission cannot be accepted, as the Non-
applicant has not acted as per the Special Conditions of Contract, and
has not taken any action to refer the dispute to arbitration within thirty
days of receipt of the notice sent by the applicant requesting for
referring the dispute for arbitration. Non-applicant lost right to appoint
the Arbitrator and, therefore, this Court has to exercise jurisdiction
under Section 11 (4) of the Arbitration & Conciliation Act, 1996.
09. In the facts of the case, the following order is passed:-
[a] Shri D.N. Potdukhe, Retired Chief Engineer, Public Works Department, resident of 207, 208, Govind Apartments, 4, Shankar Nagar, Nagpur-440 010,
[Mob. No. 9822473674; Land Line No. 0712-
2549551] is appointed as Arbitratot to examine and resolve the dispute between the applicant and the Non-applicant.
mca44.16
[b] The Arbitrator may deal with the objection raised by the Non-applicant that the dispute raised by the applicant is not arbitrable and/or part of the claim
made by the applicant cannot be considered in arbitration proceedings.
[c] The Applicant and the Non-applicant shall deposit
Rs.50,000-00 [rupees fifty thousand only] each with
the Registry of this Court within four weeks towards the security of fees of the Arbitrator.
[d] The applicant and the Non-applicant shall pay the fees to the Arbitrator directly as would be determined by him.
[e] The applicant shall deposit Rs.10,000-00 [rupees ten
thousand only] with the Registry of this Court within four weeks towards the Processing Charges.
10. Rule is made absolute in the above terms. In the
circumstances, parties to bear their own costs.
Judge
-0-0-0-0-
|hedau|
mca44.16
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!