Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Shree Ram Construction, ... vs Amravati Housing And Area Devp. ...
2016 Latest Caselaw 1668 Bom

Citation : 2016 Latest Caselaw 1668 Bom
Judgement Date : 20 April, 2016

Bombay High Court
M/S. Shree Ram Construction, ... vs Amravati Housing And Area Devp. ... on 20 April, 2016
Bench: B.P. Dharmadhikari
     Judgment.                                                          wp5958.15

                                          1




                                                                                
                                                        
           IN THE HIGH COURT OF JUDICATURE AT BOMBAY, 
                      NAGPUR BENCH, NAGPUR.




                                                       
                       WRIT PETITION NO. 5958 OF 2015.




                                          
     M/s. Shree Ram Construction,
                             
     a Partnership Firm through its
     Partner Vaibhav s/o Sahebrao Lendhe,
     r/o. Ashraya Niwas, Rajshree Shahu
                            
     Nagar, Daryapur Road,
     Anjangaon (Surji),
     District Amravati.                                       ..... PETITIONER.
      


                                     VERSUS 
   



     1. Amravati Housing and Area 
     Development Board, (A Regional Unit





     of MHADA), through its Executive
     Engineer having  office at : Griha
     Nirman Bhavan, Tope Nagar,
     Amravati.





     2.M/s. Halko Infra Projects,
     Mumbai, 14, Goraji Chinmaya, C.H.S.
     Ltd. Off Gorai Road, Near Zoor Plaza,
     Opp. Shanti Daan, Plot no.3, R.S.C.I.
     Gorai-III, Boriwali (W)
     Mumbai 400 092.
     e-mail : [email protected]         ..... RESPONDENTS.




    ::: Uploaded on - 22/04/2016                        ::: Downloaded on - 29/07/2016 23:02:49 :::
      Judgment.                                                           wp5958.15

                                            2




                                                                                 
                                                         
                             --------------------------

Shri Firdos Mirza, Advocate for the Petitioner. Shri P.N. Kothari, Advocate for the Respondent No.1. Shri A.M. Kukdey, Advocate for the Respondent No.2.

--------------------------

CORAM : B.P. DHARMADHIKARI

& P.N. DESHMUKH , J J.

ig DATE : APRIL 20, 2016

ORAL JUDGMENT : (Per : B.P. Dharmadhikari, J.)

Considering the nature of controversy, and with

consent of the learned Counsel for the parties present Writ

Petition is taken up for final disposal. Rule is issued in the

matter, and the same is made returnable forthwith.

2. Notice inviting tender published on 02.06.2013 is,

questioned by the petitioner on the ground that on 01.01.2014,

the notice itself was dropped. However, thereafter

surreptitiously work order has been issued to respondent no.2

on 01.04.2015. Respondent no.2 does not satisfy the condition

Judgment. wp5958.15

no.17 of NIT, as he has not completed 50% of the work of any

residential building independently.

3. Shri Mirza, learned Counsel for the petitioner

submits that the alleged communication dated 04.07.2014,

pressed into service by the respondents to urge that petitioner

has withdrawn its objection against respondent no.2, is denied

by the petitioner, as it is a false and fabricated document.

4. Shri Kothari, learned Counsel for the respondent

no.1 is relying upon the reply-affidavit. He submits that the

petitioner has withdrawn the objection raised against

respondent no.2, and as such the petition, as filed is, without

any locus. He points out that in any case even before the

objection was raised, respondent no.2 was found to be the

lowest bidder.

5. Shri Kukday, learned counsel appearing for

respondent no.2 adopts the argument of Shri Kothari, learned

Judgment. wp5958.15

counsel for respondent no.1. He submits that completion of

50% of work by the respondent no.2 as per clause 17 is

sufficient, and after verification of documents, as respondent

no.1 is satisfied about it, work order has been issued to

respondent no.2.

6.

We have heard the respective counsel. We find that

the requirement of clause no.17 is not in dispute. If the plea or

defence of withdrawal of objection raised by the petitioner to

participation of respondent no.2 is to be accepted, the said

withdrawal is on 04.07.2014. However, record show that on

20.10.2014, the respondent no.1 has sent a communication to

the committee appointed by it to expedite the process of

verifying the entitlement of eligibility of respondent no.2. This

communication mentions the first letter by which the

Committee was approached on 02.09.2014. If on 04.07.2014

itself petitioner has withdrawn his grievance, and given no

objection for allotting work to respondent no.2, there was no

need to appoint any such Committee or then, to call upon that

Judgment. wp5958.15

Committee to expedite its report.

7. In any case, if such an objection is raised, the

respondent no.1 is duty bound to look into it independently.

Perusal of the report submitted by the 4 responsible officers of

respondent no.1 shows a conclusion at page no.4 that

respondent no.2 has not completed any such work. On next

page, other work completed on plot no.2 of CTSO No.3/A, RSG

22 and 24, Sector 8, Charcop Kandiwali (West) Mumbai has

been mentioned. The area of work is reported as 1647.68. It is

not very clear, whether it is square feet or square meter.

Similarly, thereafter it is added that this work is standing in the

name of 'Prime Civil Infrastructures Pvt. Ltd.' Thus, credit for

this work cannot be given to respondent no.2 only on the basis

of this report.

8. Having obtained this report, it was incumbent on the

part of respondent no.1 to produce before this Court some

material to show that the credit for that work could have been

Judgment. wp5958.15

given to respondent no.2 in view of the subsequent verification

undertaken by it, however, no such material is being pressed

into service.

9. Apart from this, it is important to note that earnest

money deposited by all participants, was returned to them on

01.04.2014 itself. In this situation, return of earnest money

deposit, report of enquiry mentioned supra, all militate with the

story that the petitioner has withdrawn his complaint against

the respondent no.2. Even if it is presumed that the petitioner

had withdrawn the said complaint, that does not absolve the

respondent no.2 from its responsibility of satisfying itself about

said eligibility.

10. We therefore, find the entire exercise undertaken

and completed by respondent no.1 invalid and unsustainable.

11. During hearing we found that the time for

completion of the project is 18 months. According to the

Judgment. wp5958.15

respondent no.1, period of 18 months starts only after building

plan is sanctioned by the Planning Authority and it is yet to be

sanctioned. Shri Mirza, learned Counsel for petitioner disputes

this. In the light of the finding reached above, we are not

inclined to pronounce upon this aspect of time limit.

12.

Accordingly, we quash and set aside the work order

issued to respondent no.2. Writ Petition is partly allowed.

Rule is made absolute in the aforesaid terms, with no order as

to costs.

                            JUDGE                                  JUDGE

     Rgd.






 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter