Tuesday, 21, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

New Bombay Advocates Welfare ... vs State Of Maharashtra And Ors
2015 Latest Caselaw 15 Bom

Citation : 2015 Latest Caselaw 15 Bom
Judgement Date : 7 August, 2015

Bombay High Court
New Bombay Advocates Welfare ... vs State Of Maharashtra And Ors on 7 August, 2015
Bench: A.S. Oka
     ash                                                1          pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                
                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                            CIVIL APPELLATE JURISDICTION
                     PUBLIC INTEREST LITIGATION NO.239 OF 2009




                                                        
                                     ALONG WITH
                      PUBLIC INTEREST LITIGATION NO.10 OF 2008
                                    ALONG WITH 
                           WRIT PETITION NO.5101 OF 2012




                                                       
     PIL NO.239 OF 2009




                                          
     New Bombay Advocates Welfare Association,
     through its President and Another.
                              ig                                 ..       Petitioners
           Vs
     State of Maharashtra and Others.                            ..       Respondents
           -

PIL NO.10 OF 2008

Shri Pramod Mahadeo Thakur. .. Petitioner

Vs The Secretary, The Law and Judiciary Department and Others. .. Respondents

-

WP NO.5101 OF 2012

Ahmednagar City Bar Association. .. Petitioner Vs

The Union of India and Others. .. Respondents

--

Shri A.A. Kumbhakoni, Senior Advocate, appointed as Amicus Curiae along with Shri Amit B. Borkar for the Petitioners. Shri Makarand Kale i/by M/s. M.P. Vashi & Associates for the Petitioner in PIL No.239 of 2009.

Shri Rahul S. Thakur for the Petitioner in PIL No.10 of 2008. Shri A.B. Vagyani, Government Pleader along with Mrs.M.P. Thakur, AGP for the Respondent No.1 in the PIL No.239 of 2009 and for the Respondent Nos.1 to 4 and 7 in PIL No.10 of 2008 and for the Respondent No.5 in WP No.5101 of 2012.

      ash                                                  2          pil-239,10n-wp-5101.12-
     courtinfrastructure

Shri Uday P. Warunjikar for the Petitioner in WP No.5101 of 2012. Shri A.M. Kulkarni along with Shri Sarthak Diwan and Shri Akshay

Kulkarni for the Respondent No.2 in PIL No.239 of 2009. Shri Sanjay Udeshi i/by M/s. Sanjay Udeshi & Co for the Respondent No.3 in PIL No.239 of 2009.

Ms. Pinky M. Bhansali i/by M/s. G.S. Hegde & Associates for the Respondent No.5 in PIL No.10 of 2008.

Shri M.S. Karnik for the Respondent No.8 in PIL No.10 of 2008 and for the Respondent No.4 in WP No.5101 of 2012.

Shri Parag Vyas and Shri D.R. Shah for the Union of India.

--

                                   CORAM  :       A.S. OKA & 




                                           
                                                  REVATI MOHITE DERE, JJ 
                              ig   DATED    :     7TH & 13TH AUGUST 2015


     ORAL JUDGMENT : (PER A.S. OKA,J)
                            
                                       INTRODUCTION

     .                 These three Petitions have been filed inviting the attention 
      


of this Court to the gross delay on the part of the State Government in

commencing and completing the construction of Court buildings. The

Public Interest Litigation No.239 of 2009 concerns construction of a

Court building and Judicial Quarters at Navi Mumbai in Taluka and

District Thane. The Public Interest Litigation No.10 of 2008 concerns

the grievance about the gross delay involved in the commencement of

construction and completion of a Court building as well as judicial

quarters at Panvel in District Raigad. The Writ Petition No.1501 of

2012 contains a grievance regarding failure of the State Government to

commence and complete the construction of District Court Building at

Ahamednagar within a reasonable time. In these three Petitions, from

ash 3 pil-239,10n-wp-5101.12-

courtinfrastructure

time to time, various directions have been issued by this Court. It is

really unfortunate that the Members of the Bar were compelled to file

such Petitions in this Court inviting the attention of the Court to the

gross delay on part of the State Government to commence and complete

the construction of Court buildings.

THE OBLIGATION OF THE STATE TO ESTABLISH COURTS

AND PROVIDE INFRASTRUCTURE

2.

Before we deal with the factual aspects, firstly we propose

to deal with the issue of the obligation of the State Government not

only to establish the Courts, but also to provide adequate infrastructure

to the Courts which are already established. Part IV of the Constitution

of India contains the directive principles of state policy. Article 39A

forming part of Part IV reads thus:-

"39A. Equal justice and free legal aid.- The State shall secure that the operation of the legal system promotes justice, on a basis of equal opportunity, and shall, in particular, provide free legal aid, by suitable legislation or schemes or in any other way, to ensure that

opportunities for securing justice are not denied to any citizen by reason of economic or other disabilities."

3. In the case of Purshottam Manohar Kamone V. State of

Maharashtra1, the issue of obligation of the State Government to

establish Courts was considered. The Division Bench of this Court

reiterated the well settled principle that the speedy justice is an 1 2001(4) Mh.LJ. 320

ash 4 pil-239,10n-wp-5101.12-

courtinfrastructure

ingredient of Article 21 of the Constitution of India and, therefore, each

litigant has a fundamental right to speedy justice. In Paragraph 6 of

the said decision, the Division Bench has held thus:-

"6. It is no longer debatable and rather it is well

settled that the speedy justice is an ingredient of Article 21 of the Constitution of India and, therefore, each litigant has a fundamental right of a speedy justice. That being so, it is the

corresponding obligation of the State to constitute sufficient number of courts, Tribunals and forums

so that a litigant, who has knocked the door of the Court or Tribunal, is able to get justice speedy. Taking into consideration the huge pendency of motor

accident claim cases at Nagpur, expected future filing and slow disposal of such cases, it is necessary for the State Government to provide sufficient Motor Accident Claims Tribunals at Nagpur. This is essential to ensure the speedy disposal of cases and in consonance with

Article 39-A of the Constitution of India, which

provides that the State shall secure that the operation of the legal system promotes justice. As observed by the Apex Court in S.C. Advocates-on-Record v. Union of India,: AIR 1994 SC 268, with reference to Article

216 of the Constitution of India, which deals with the constitution of High Courts, "This is essential to ensure speedy disposal of cases, to 'secure that the operation of the legal system promotes justice' - a directive principle 'fundamental in the governance of the country' which, it is the duty of the State to observe in

all its actions; and to make meaningful the guarantee of fundamental rights in Part III of the Constitution."

The Apex Court further observed that the failure to perform this obligation, resulting in negation of the Rule of law by the laws' delay must be justiciable, to compel performance of that duty. Applying the same principle, in our view, it must be held that the constitution of Motor Accident Claims Tribunal, as required by the State under section 165 of the Motor Vehicles Act is justiciable issue and if it is shown that the existing Tribunal is inadequate to

ash 5 pil-239,10n-wp-5101.12-

courtinfrastructure

provide speedy justice to the people, a direction can be issued to the State Government to take

appropriate steps in discharge of their duty, commensurate with the need to fulfill the State obligation of providing speedy justice to the victims or

the dependent of the victims of motor accident".

(emphasis added)

4. Hence, now the law is crystalized. The law is that the State

Government is under obligation to constitute sufficient number of

Courts, Tribunals or Forums so that a litigant, who has knocked the

door of the Court or Tribunal, is able to get speedy justice. Even the

access to justice is a facet of fundamental right available under Article

21 the Constitution of India.

5. Our attention is invited to a decision of the Apex Court in

the case of Brij Mohan Lal v. Union of India and Others 1. It will be

necessary to make a reference to Paragraphs 136 and 137 of the said

decision which reads thus:-

"136. However, as far as functioning of the courts i.e. dispensation of justice by the courts is concerned, the Government has no control over the courts. Further, in relation to matters of appointments to the judicial services of the States and even to the higher judiciary in the country, the Government has some say, however, the finances of the judiciary are entirely under the control of the State. It is obvious that these controls should be minimised to maintain the independence 1 (2012)6 SCC 502

ash 6 pil-239,10n-wp-5101.12-

courtinfrastructure

of the judiciary. The courts should be able to function free of undesirable administrative

and financial restrictions in order to achieve the constitutional goal of providing social, economic and political justice and equality

before law to the citizens."

"137. Article 21 of the Constitution of India takes in

its sweep the right to expeditious and fair trial. Even Article 39-A of the Constitution recognises the right of citizens to equal justice and free legal aid. To put it simply, it is the constitutional duty of the Court to provide

the citizens of the country with such ig judicial infrastructure and means of access to justice so that every person is able to receive an expeditious, inexpensive and fair trial. The plea of financial limitations

or constraints can hardly be justified as a valid excuse to avoid performance of the constitutional duty of the Government, more particularly, when such rights are

accepted as basic and fundamental to the human rights of citizens."

(emphasis added)

6. The Apex Court also relied upon its earlier decision in the

case of Hussainara Khatoon v. State of Bihar1 wherein the Apex Court

observed that it is also the constitutional obligation of the Apex Court to

enforce setting up new Court buildings and Court houses providing

more staff and equipment to the Courts and to take all measures

calculated to ensure speedy trial. The Apex Court in the said decision

observed that the Government cannot plead financial or administrative

1 (1980)1 SCC 98

ash 7 pil-239,10n-wp-5101.12-

courtinfrastructure

inability to avoid its constitutional obligation to provide speedy trial to

an accused.

7. The Apex Court has reiterated that it is the constitutional

duty of the Government to provide to the citizens of the country with

such judicial infrastructure and means of access to justice so that every

citizen is able to receive an expeditious, inexpensive and fair trial.

What is more important is the categorical declaration made by the Apex

Court that the plea of financial limitations or constraints cannot be a

valid excuse to avoid the performance of the constitutional duty of the

Government to provide a proper judicial infrastructure. The

fundamental right to access to justice and right to speedy justice

available to the citizens can be effectively exercised by them provided

adequate judicial infrastructure is available. The said right can be

effectively exercised provided adequate number of Courts are

established and a proper infrastructure is provided therein for the

litigants, Judges, the members of the Bar and the Court staff. The

existence of aforesaid fundamental right creates a corresponding

obligation in the State Government to ensure that adequate number of

Courts are established as may be decided by the High Court and a

proper infrastructure is provided therein for the litigants, Judges, the

members of the Bar and the Court staff. The litigants are entitled to

have basic facilities such as clean drinking water, clean toilets and

ash 8 pil-239,10n-wp-5101.12-

courtinfrastructure

proper sitting arrangement in every Court. While performing the

constitutional duty of ensuring that the citizens are able to exercise the

said right, the State Government cannot come out with an excuse of

financial limitations or constraints.

8. When it comes to the construction of new Courts, this

Court on the administrative side takes into consideration number of

relevant aspects, such as, population, pendency of cases, easy

accessibility to the the litigants to the place where Court is proposed to

be established. After having considered all the relevant factors that this

Court submits proposals to the State Government to establish new

Courts.

9. Only by providing lands for establishing Courts, the State

Government does not discharge its constitutional obligation. It is an

obligation of the State Government to provide all the necessary

infrastructure to the newly established as well as the existing Courts, to

the judicial officers, to the members of the staff as well as to the

members of the Bar. The infrastructure has to be provided in such a

manner that the Courts are able to function effectively. The

infrastructure to be provided has to be consistent with the concept of

dignity and decorum of the Court. The speedy disposal of cases in

consonance with Article 39A of the Constitution of India cannot be

ash 9 pil-239,10n-wp-5101.12-

courtinfrastructure

achieved unless adequate number of Courts are established and

adequate and proper infrastructure is provided to all Court premises.

PROCEDURAL ASPECTS:

10. There is one important issue which is common in all these

cases needs to be highlighted. This common aspect is that the

procedure for approval of building plans, approval of estimates for

construction of a Court complex prepared by Public Works Department

(PWD) and sanction of funds is very cumbersome and lengthy. The

files keep on moving from one department to another and by the time

the estimates are approved and the funds are sanctioned and released,

there is a lot of delay which results in delay in commencement of

construction and escalation in the cost of construction. The escalation,

apart from putting the burden on public exchequer, leads to submission

of revised estimates, the approval of which again takes inordinately

long time. Till the approval to revised estimates, the construction

becomes standstill due to lack of funds. In all the three cases which are

before the Court, the funds were belatedly sanctioned and there was a

gross delay in release of funds which led to delay in completion of the

project and naturally led to further cost escalation. Thus, due to such

delays at all stages, it is the State exchequer which ultimately suffers.

In these three cases, it can be safely said that enormous burden has

been put on the public exchequer due to the delay on the part of the

ash 10 pil-239,10n-wp-5101.12-

courtinfrastructure

State Government in sanctioning the revised estimates and in releasing

the funds. That is the reason why under the order dated 8 th May 2015,

this Court directed the State Government to constitute a Committee of

Senior Officers headed by the Chief Secretary to look into all the aspects

of construction of various Courts and accordingly, a Committee has

been constituted. There is an urgent need to streamline the procedure

which is followed for preparation and sanction of plans and estimates as

well as for the preparation and sanction of revised estimates. The

movement of files has to be curtailed which will ultimately save the

money of the State. Moreover, when there is a delay in completion of a

project, the State Government must hold an inquiry and fix the

responsibility for the delay as the delay puts burden on the State

exchequer. Unless the element of accountability is introduced, the

projects would not be completed within the outer limit fixed. It is

mandatory that the procedural delays are curtailed.

11. Apart from these three Petitions, there are 7 to 8 Writ

Petitions assigned to this Bench dealing with the issue of infrastructure

available in various Courts and Tribunals in the State. A general

observation which can be made on the basis of the pleadings and the

documents on record as well as the orders passed by this Court in all

the Petitions is that the State Government has failed to perform its

constitutional obligation of providing requisite infrastructure to the

ash 11 pil-239,10n-wp-5101.12-

courtinfrastructure

Courts and Tribunals. The extent of failure of the State Government to

perform its constitutional obligations can be well demonstrated by

adverting to the facts of the PIL No.239 of 2009.

PIL NO.239 OF 2009

12. PIL No.239 of 2009 concerns establishment of Civil and

Criminal Courts at Navi Mumbai. It is with the object of reducing

congestion in the City of Mumbai, in the late 1960s, the State

Government took a policy decision to form a satelite City of Navi

Mumbai. On 20th March 1971, a Notification was issued in exercise of

powers under Section 113 of the Maharashtra Regional and Town

Planning Act, 1966. By the said Notification, the site of a new town of

Navi Mumbai was specified which was to include about 96 villages

situated within the adjoining Districts of Thane and Raigad. The City

and Industrial Development Corporation of Maharashtra Limited

(CIDCO), a Government of Maharashtra Company was appointed as a

New Town Development Authority for the city of Navi Mumbai. Both

the State Government and the CIDCO advertised that the City of Navi

Mumbai will be a model City or a dream City. The area of site of Navi

Mumbai extends to 344.5 sq. Kilometers. The said area covers a large

industrial area as well as the area available for urban development. The

city of Navi Mumbai started developing and growing very fast from the

last decade of the 20th century and there was enormous residential,

ash 12 pil-239,10n-wp-5101.12-

courtinfrastructure

commercial and Industrial growth. In the year 1991, the Navi Mumbai

Municipal Corporation was established under the Maharashtra

Municipal Corporations Act, 1949 and started functioning with effect

from 1st January 1992. The jurisdiction of the Navi Mumbai Municipal

Corporation was confined to 44 villages. By 2001, the population of the

new city crossed 11,00,000 mark. There was overall growth in terms of

construction of residential and commercial buildings. There was also

enormous growth in terms of industrial and commercial activities in the

New City which lead to rise in the prices of lands. All this growth lead

to filing of large number of litigations. It is on this background that we

will have to appreciate the manner in which the matter of construction

of a Court building and the judicial quarters in Navi Mumbai has been

dealt with by the State Government. In this PIL No.239 of 2009, we are

dealing with the establishment of a Court complex in a model and so

called dream City of Navi Mumbai which which has become a hub of

commercial and industrial activity. If the record of the said Petition is

perused, it can be safely said that but for the intervention of this Court,

even a plot for construction of a Court building and judicial quarters

would not have been allotted.

13. It all started with the PIL No.18 of 2007 filed by the

Association known as "New Bombay Advocates' Welfare Association"

which is also the Petitioner in the present PIL. On 28th March 2007

ash 13 pil-239,10n-wp-5101.12-

courtinfrastructure

when the said earlier PIL came up before a Division Bench of this Court,

the CIDCO made a statement that the area of 19,000 sq. meters has

been earmarked for construction of a Court building. This Court

directed the State Government to take necessary action. In the very

order, this Court expected that the Principal Secretary of the Urban

Development Department to file an affidavit in the matter stating as to

what was the impediment in allotting the land free of cost for the

purposes of Court buildings by the CIDCO considering the financial

constraints that are faced by the State Government. This Court was

conscious of the fact that all the plots in Navi Mumbai had been

acquired by the State Government and were placed for disposal of the

CIDCO which is the Government of Maharashtra Company. Even

thereafter, no steps were taken. Therefore, by the order dated 3 rd May

2007, this Court directed the CIDCO to allot a plot having an area of

19,488.20 sq. meters within a period of four weeks from the said date.

The order dated 3rd May 2007 records that under no circumstances, the

project of raising a judicial complex on the plot in question shall be

delayed. On 21st August 2008, a statement of the learned Assistant

Government Pleader was recorded that the possession of the land has

been already given to the concerned Department in the Government for

construction of a judicial complex and the Chief Architect has already

prepared the drawings which has been approved by this Court. By

accepting the said statement that the said PIL was disposed of.

      ash                                                14         pil-239,10n-wp-5101.12-
     courtinfrastructure

Notwithstanding the said orders, as no further steps were taken by the

State Government, the present PIL was required to be filed in which

more than a dozen orders were required to be passed from time to time.

The present PIL has been filed by the same Association of the Advocates

seeking a writ of mandamus directing the Government to undertake

construction of a Court complex and to sanction adequate funds for the

project. Right from 4th October 2010, several directions were issued

by this Court from time to time. One of the material directions is in the

order dated 4th April 2014. The order dated 1st September 2014 records

a very crucial aspect. As the CIDCO did not transfer the land to the

State Government, the Navi Mumbai Municipal Corporation did not

grant regular water supply for construction of the Court building. As a

result, the water was required to be procured by tankers. By consuming

the contaminated water procured by the tankers, the construction

workers staying at the site fell ill. Therefore, this Court directed the

Navi Mumbai Municipal Corporation to release the water supply both

for the purpose of construction and for the purpose of consumption by

the workers at site. This order which was passed more than 15 months

back records that a lease has not been executed by the CIDCO in favour

of the State Government. Only after this order was passed that the Navi

Mumbai Municipal Corporation provided the water supply. The order

dated 3rd November 2014 records that there was a gross delay on the

part of the State Government in completing the construction of the

ash 15 pil-239,10n-wp-5101.12-

courtinfrastructure

Court building and judicial quarters. The order dated 24 th November

2014 also deals with the aspect of gross delay in completion of the

Court complex at Navi Mumbai. The requirement of the funds for

completing the construction was noted and the State Government was

directed to file an affidavit setting out the manner in which the funds

will be made available. Thereafter, again a detailed order was passed

on 13th January 2015 dealing with various aspects. Further order dated

8th May 2015 again notes the delay involved in completion of the

project. Even as of today, the CIDCO has not executed a lease deed in

respect of the said plot in favour of the State Government. The first

reason for the delay is that till this Court passed the order in the present

PIL, no steps were taken to execute a lease. The second reason is that a

huge amount by way of a lease premium was demanded by the CIDCO

and ultimately, this Court has passed the order in the present PIL

directing the State Government to consider of reducing the amount of

lease premium payable to the CIDCO and accordingly, the said amount

was brought down to Rs.9.75 Crores. This amount will be payable by

the State Government to the CIDCO by way of lease premium. As

pointed out earlier, in the earlier PIL being PIL No.18 of 2007, as back

as on 3rd May 2007, this Court expressed a view that the State

Government should file an affidavit stating as to why the CIDCO cannot

hand over the plot for Court complex free of cost. After several orders

were passed by this Court, now there is an affidavit filed on 30 th July

ash 16 pil-239,10n-wp-5101.12-

courtinfrastructure

2015 by Shri Mansing Namdeo Pawar, Deputy Secretary of the Law and

Judiciary Department in which it is stated that the demand of Rs.9.75

Crores was sanctioned by the Legislative Assembly and the said amount

will be released to the CIDCO very soon. We propose to issue directions

to the CIDCO to execute the lease on receiving payment from the State

Government. The State Government on acquiring the lands at its own

cost has placed the CIDCO in possession thereof for establishment of the

City. Therefore, even today, the State Government should consider the

option of taking over the plot of land free of any premium.

14. Before we deal with the issue of the outer limit within

which the construction of Court complex /judicial quarters will have to

be completed, we must record here with some emphasis that even the

present stage of construction could not have been reached if there were

no PILs filed by the Petitioners. From the stage of allotment of plot for

the project of construction of a Court complex in Navi Mumbai, more

than two dozen orders were required to be passed by this Court right

from the year 2007 till 2015. Therefore, this is a classic illustration of

a case where the State Government has failed to perform its obligation

of establishing a proper Court complex and of providing infrastructures

to the said Court. For all these years, the Courts are functioning in

premises taken on rent which are very inconvenient for litigants,

lawyers and Judges.

      ash                                                 17         pil-239,10n-wp-5101.12-
     courtinfrastructure

15. As far as Navi Mumbai Court Complex is concerned, there

are certain assurances incorporated in the affidavit dated 30 th July, 2015

of Shri Mansing Namdeo Pawar, Deputy Secretary, Law and Judiciary

Department. From the said affidavit, it appears that still the amount of

Rs.13.75 Crores is required to be budgeted which can be done only in

the winter session of Legislature in December 2015. The other issue as

far as the Court Complex and judicial quarters in Navi Mumbai are

concerned, there is already an assurance recorded that both the

buildings will be completed by the end of June 2016. The said

assurance can be found in the affidavit of Shri Salim Gulab Shaikh,

Executive Engineer of the Public Works Department, which is dated 30 th

July 2015. Thus, the construction of the Court building as well as the

judicial quarters in Navi Mumbai will be completed by the end of June

2016. Considering the fact that the construction of the Court complex is

inordinately delayed, the Public Works Department will have to prepare

plans and/or estimates of the internal work such as plumbing,

sanitation, electrification as well as the plan of internal roads, gardens,

drainage system etc. on or before 30 th November 2015 to enable all the

Departments including the administrative side of the High Court to

approve the same. When we say that the buildings will be completed

by the end of June 2016, we clearly mean that the buildings shall be

completed in such a manner that the user of the buildings can be

commenced effectively from 1st July 2016.

      ash                                                     18         pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                     
                               WRIT PETITION NO.5101 OF 2012




                                                             

16. Now it will be necessary to consider the stand taken as

regards the Court Building at Ahmednagar. There is an affidavit filed by

Shri Dayanand Bhimrao Vibhute, the Executive Engineer, Public Works

Department, Ahmednagar. In the said affidavit, he has stated that the

outer limit for construction of the Court has been extended till the end

of September 2016. He has annexed at Exhibit-1 to the said affidavit,

the tentative schedule of work which ends with the site cleaning on 30 th

September 2016. Therefore, the construction of Court building at

Ahmednagar will have to be completed by 30 th September 2016. The

construction will have to be completed in such a manner that with

effect from 1st October 2015, the entire building can be used for

functioning of the Court in effective manner. In this case, the additional

estimates and/or plans for carrying out internal work of plumbing,

sanitation etc as well as external work such as internal roads, drainage,

gardens etc shall be submitted latest by 30 th November 2015 by the

Public Works Department so that after completing the process,

necessary funds can be released. We make it clear that considering the

fact that the work of construction has been already delayed, no

extension shall be ordinarily granted.

      ash                                                  19         pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                  

17. As far as the issue of the Court building at Ahmednagar is

concerned, the learned counsel appearing for the Petitioner has raised

two additional issues. His contention is that the Bar room of adequate

size will have to be provided in the said building both for male and

female Advocates. His submission is that while finalizing the size of

the Bar room, even the possibility of future increase in the number of

members of the Bar will have to be taken into consideration. The High

Court Administration will have to take a policy decision on this aspect.

We accept the contention that the Bar rooms of adequate size will have

to be provided. However, as far as the area to be provided is concerned,

it is a matter of policy decision to be taken by the High Court

Administration.

ISSUE OF ACCOMMODATING NOTARIES IN THE COURT

BUILDING/COMPLEX:

18. Another issue raised by the learned counsel appearing for

the Petitioner in the Writ Petition No.5101 of 2012 in case of the

Ahmednagar Court is regarding accommodating the Notaries appointed

under the Notaries Act, 1952 ( for short "the said Act of 1952") in the

Court premises. It is contended that the notaries who are members of

the Bar sit in the Advocates' Bar rooms and carry on their occupation

which obstructs the use of Bar rooms by other members of the Bar.

      ash                                                  20         pil-239,10n-wp-5101.12-
     courtinfrastructure

Once the Bar rooms are allotted to the Bar Associations, it is the

responsibility of the Bar Associations and its members to ensure that the

Bar rooms are used strictly for the purpose for which the same are

allotted. If any member of the Bar is using a Bar room for the purposes

which are not contemplated, it is for the concerned Bar Association to

take action against its own erring member in accordance with law.

There is a submission made that a separate premises be allotted in each

Court complex to the Notaries. Therefore, it will be necessary to

consider the provisions of the said Act of 1952. Under Sub-section (1)

of Section 8 of the said Act of 1952, the functions of the Notaries are set

out. Apart from the attestation of instruments and administering the

oath for the purposes of affidavits, the Notaries perform several other

functions. Most of the functions are under the provisions of the

Negotiable Instruments Act, 1881. Attestation of the documents and

administering oath for the purposes of affidavits are only few functions

of the Notaries. Our attention is invited to the provisions of the Notaries

Rules 1956 ( for short "the said Rules"). The Rule 8 of the said Rules

provides that appointment of a Notary can be made in respect of a

specific area. The Rule 15 provides that each Notary shall have an

office within the area mentioned in the certificate issued to him/her

under Rule 8 of the said Rules. Thus, the said Rules contemplate that

each notary should have an office within the area of his jurisdiction.

Considering the requirement of the said Rules of each Notary of having

ash 21 pil-239,10n-wp-5101.12-

courtinfrastructure

an office within the area of his jurisdiction, it will not be appropriate to

provide separate premises to the notaries in the Court buildings.

Moreover, the role of a Notary is not confined to administering oath for

affidavits. It is only a small part of his functions. Therefore, the said

submission made by the learned counsel for the Petitioners cannot be

accepted.

PIL NO.10 OF 2008

19. As far as the Court building and judicial quarters at Panvel

is concerned, Shri Vilas Laxmanrao Kamble, the Executive Engineer of

the Public Works Department, Alibag, has filed an affidavit dated 30 th

July 2015. In Paragraph 7 of the affidavit, he has stated that the Court

building can be completed by the end of March 2016 provided that the

balance amount of Rs.214.36 lakhs will be made available as per the

demand made by the Public Works Department. The said amount shall

be made available by the State as per the demand of the PWD. Even as

regards the judicial quarters, he has stated that the construction thereof

can be completed by the end of March 2016. In fact, he has given an

assurance that an endeavour will be made to complete the same by the

end of January 2016. We propose to grant time up to the end of March

2016 to complete both the judicial quarters and the Court building. As

in case of other buildings, the additional estimates and/or plans for

carrying out internal work such as plumbing, electrification, etc and the

ash 22 pil-239,10n-wp-5101.12-

courtinfrastructure

work such as the internal roads, drainage system, gardens, etc. shall be

submitted by 30th September 2015 which will have to be approved by

the concerned department including the High Court Administration so

that in the winter session of Vidhan Sabha in December 2015, the

approval can be granted to the additional estimates.

20. As noted earlier, but for the intervention of the judicial side

at every stage, commencement of construction of the Court complex at

Navi Mumbai would not have commenced. Even in case of Courts at

Ahmednagar and Panvel, but for the judicial intervention, no progress

would have been made in the work of construction.

NEED TO STREAMLINE PROCEDURE AND TO GIVE PRIMACY TO THE VIEWS OF THE HIGH COURT ADMINISTRATION

21. In some detail, we have already discussed constitutional

obligation of the State Government of establishing the Courts in the City

and of providing all the infrastructures to the Courts. As far as the

decision of establishing the Courts is concerned or as far as the

requirement of constructing new Court buildings or new judicial

quarters is concerned, the same will have to be taken by the High Court

Administration after considering all the relevant factors. The

views/opinion of High Court Administration on the aspect of

ash 23 pil-239,10n-wp-5101.12-

courtinfrastructure

establishing new Courts must get primacy. However, as laid down by

the Apex Court in the case of Brij Mohan Lal, once the High Court

Administration decides to set up a new Court or to construct a new

building for housing the Courts or new building for the judicial

quarters, the plea of financial constraints or financial limitations is not

available to the State. The Courts should be free of undesirable

administrative and financial restrictions. The State cannot refuse to

perform its constitutional obligation of providing adequate judicial

infrastructure and means of access to justice to citizens. As pointed out

by Shri Kumbhakoni, the learned senior counsel appointed as Amicus

Curiae, there are delays involved at every stages right from the sanction

of the initial proposal for construction of Court building. At every stage,

the State Government comes out with an excuse of financial constraints.

In view of the law laid down by the Apex Court in the decision in the

case of Brij Mohan Lal, the said excuse is no longer available to the

State Government. As held therein, the Courts should be free of

undesirable financial restrictions.

22. We have pointed out in the earlier order passed in these

three Petitions that there is invariably a gross delay in processing the

proposals/estimates for construction of new Court buildings. Normally,

there are various objections raised by the Finance Ministry. The High

Court administration is told to justify the necessity of construction of

ash 24 pil-239,10n-wp-5101.12-

courtinfrastructure

new buildings. By way of illustration, we may state that in some cases,

when construction of a judicial quarter is already approved, justification

is demanded as to why a compound wall is necessary. Even after the

funds are budgeted, invariably here is a delay in release of the funds. If

proposals are not approved within the reasonable time from the date on

which estimates are prepared, by the time the approvals are granted by

the State and tender is floated, there is always an escalation in the cost

of construction. There is further delay involved as the sanctioned

amount is normally not released in the required time frame. Therefore,

supplementary proposals/estimates are required to be submitted. At

that stage also the Finance Ministry invariably raises all sorts of

objections and demands justification which again causes the delay. That

is how, apart from defeating constitutional obligation of the State

Government, the delays put enormous burden on the State exchequer.

Therefore, as rightly submitted by Shri Kumbhakoni, the procedure for

grant of approval will have to be streamlined and the procedure should

be such that within a time bound schedule, the decisions are taken and

implemented.

23. The delays start from the stage of acquisition of the land.

There are several instances where from the date on which the High

Court Administration moves the Government for initiating the

acquisition proceedings for taking over the land for the Court complex,

ash 25 pil-239,10n-wp-5101.12-

courtinfrastructure

the acquisition takes a decade or more. The provisions of the

Maharashtra Regional and Town Planning Act, 1966 are applicable to

the entire State. In those municipal areas where the Court

premises/residential quarters may be required to be constructed in

future or where the existing Courts/quarters are in rental premises or

where the premises available to the existing Courts are insufficient, it is

advisable that the State Government provides for reservations on

suitable lands in the sanctioned development plans for the Court

complexes including the judicial quarters. If such reservations are

provided, it will facilitate early acquisition of the lands needed for the

Court buildings or judicial quarters. By way of illustration, we may state

that in the City of Mumbai, in the existing sanctioned Development

Plan, there are more than 10 sites earmarked for the Court complexes.

We are informed across the Bar that the Revised Development Plan has

been published. It is the duty of the Law and Judiciary Department to

ensure that if the revised development plan proposes deletion of some

of the said reservations, the appropriate objections are raised. This will

apply to Development Plan of all the Municipal Authorities. Before

finalizing Development Plans, it is necessary for the State to consider

the requirements of Judicial department.

24. After a suitable land is placed in possession of the Law and

Judiciary Department for construction of a Court building and judicial

ash 26 pil-239,10n-wp-5101.12-

courtinfrastructure

quarters, the first step which is to be undertaken by the local public

works department is of preparation of drawings of the proposed

building as per the requirement of the judiciary. After the drawings are

approved, the estimates are prepared by the Public Works Department.

From the various orders already passed and the affidavits on record, we

find that there is an inordinate delay in grant of administrative approval

to the said proposals. After the hurdle of the administration approval is

cleared, then the proposals are sent to the Finance Department for

approval. From the record, it appears to us that various queries are

raised by the Finance Department including seeking justification for the

construction of the Court buildings and judicial quarters. As stated

earlier, the opinion of the High Court Administration has primacy in all

these matters. Hence, when the proposal is approved by the High Court,

normally, there is no reason to doubt the necessity of constructing a

new Court building or new judicial quarters. Once a conscious decision

is taken by the High Court Administration, in view of the law laid down

by the Apex Court in the case of Brij Mohan Lal, the financial

constraints cannot be an excuse to defeat the requirement of

construction of a Court building and judicial quarters as well as

provision for necessary infrastructure therein. Therefore, norms will

have to be laid down as regards the category of the objections which

can be raised by the Finance Ministry. The Ministry cannot impose

undesirable financial and administrative restrictions on Courts. A time

ash 27 pil-239,10n-wp-5101.12-

courtinfrastructure

bound schedule is required to be laid down for administrative approvals

to the project of construction and for financial approval. Unless all this

is done in a time bound manner the delays will result in further

escalation of cost. After all approvals are granted, even tender process is

required to be completed in a time bound manner.

25. Then comes an issue of submitting supplementary

estimates. The occasion for submitting supplementary estimates arises

when there is a delay in granting financial approval and there is a delay

in releasing the amount to the Contractors which results into delay in

completion of construction. In such cases, the approvals have to be

granted in much lesser time than the time which is required for the

grant of approval to the original proposals. Then comes the practice

which is followed consistently as regards the proposals for the internal

work such as plumbing, electrification etc as well as the external work

such as work of gardening, drainage system, compound wall etc. There

may be some valid reasons for not getting the estimates of the said

work approved at the outset. The logic may be that only when the

building is on the verge of completion that the appropriate decision can

be taken as regards the said requirements and by that time, invariably

there is an escalation of cost. A procedure will have to be laid down that

such estimates and proposals shall be submitted at least six months

prior to the proposed date of the completion of the construction of the

ash 28 pil-239,10n-wp-5101.12-

courtinfrastructure

buildings. As regards the furniture to be provided in the Court complex

as well as judicial quarters, it will be appropriate if the State

Government permits the High Court Administration/concerned

Principal District Judges to procure furniture by following e-tender

process.

NEED TO PREPARE A SCHEME CONSIDERING THE CONSTITUTIONAL OBLIGATIONS

26.

Considering all the aforesaid aspects, the State Government

will have to take appropriate policy decision laying down a standard

procedure to be adopted for sanctioning proposals for construction of

the Court buildings/ judicial quarters as well as the financial approval

to the estimates. A procedure is also required to be laid down for the

grant of approvals to the work of repairs or additions and alterations to

the existing buildings. The State Government will have to lay down the

procedure with a view to ensure that all the approvals are granted

within a time bound limit considering the Constitutional obligation of

the State to provide infrastructure to the Judiciary. The procedure

which may be designed by the State Government must ensure that

unnecessary correspondence and unnecessary movement of the files

from one department to another is avoided. A single window system is

required to be adopted when it comes to grant of approvals as it is

found that the High Court Administration is required to run from pillar

ash 29 pil-239,10n-wp-5101.12-

courtinfrastructure

to post for getting the proposals approved. The State Government will

have to consider one more aspect. In several cases which have come

before this Court, it is noticed that the sanctioned funds are released at

the fag end of the financial year and, therefore, it becomes impossible

for the judicial department or the Court to use the said funds before the

end of the financial year and invariably the funds lapse and that is how

the requirement arises of again obtaining fresh financial approvals.

Such practice of releasing the funds at the fag end of the financial year

must be forthwith discontinued. We propose to direct the State

Government to take appropriate policy decision laying down a

comprehensive scheme dealing with the preparation of plans and

estimates, sanction thereof, release of funds as well as completion of

projects of the judiciary within a time bound schedule. We propose to

grant reasonable time to the State Government to come out with a

concrete scheme and policy decision on this aspect. Our suggestion to

the State Government is that before a policy decision is taken, the State

Government should involve a Registrar nominated by the High Court

Administration as well as Shri Kumbhakoni, the learned senior counsel

appointed as Amicus Curiae as well as the learned Government Pleader

in the process of consultation. The policy decision to be taken must also

provide a mechanism for fixing responsibility on the concerned officials

in the event of delays in completion of projects of the Court buildings

and judicial quarters.

      ash                                                         30           pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                         

27. We must record our appreciation of the assistance rendered

by the learned counsel appearing for the Petitioners, the learned

counsel representing the High Court Administration, the learned

Government Pleader as well as the learned Senior Counsel Shri

Kumbhakoni who has been appointed as the Amicus Curiae. We must

note that the learned Government Pleader has assisted the Court as an

Officer of the Court and therefore, no Officer of the State shall treat it

as an objectionable conduct.

28. Considering the aforesaid discussion, we dispose of these

three Petitions by passing the following order:

ORDER :

(a) We hold that it is the duty of the State Government

to ensure that the Court complex and judicial

quarters are constructed and all necessary

infrastructure is provided as per the decisions taken

by the High Court Administration on the

administrative side. It is the obligation of the State

Government to maintain the existing buildings in

proper condition. It is the duty of the State to

ensure that all the necessary infrastructure is

ash 31 pil-239,10n-wp-5101.12-

courtinfrastructure

provided in all Courts for the Litigants, Advocates,

Judges and members of the staff. The obligation will

include the work of carrying out repairs to the

existing buildings. We make it clear that in the

matter of providing infrastructure to the Courts

including, the requirement of construction of new

buildings, the decisions of the High Court

ig administration shall have primacy ;

(b) We hold that it is the constitutional duty of the State

Government to ensure that such judicial

infrastructure is provided which ensures that every

citizen has the benefit of an expeditious, inexpensive

and speedy trial. The State is under an obligation to

provide easy access to Justice to the Citizens. This

obligation includes making available basic facilities

to the Litigants in each Court Complex such as clean

and modern facility of toilets and washrooms, clean

drinking water and a proper sitting arrangement.

The Litigants have a right to have a clean and well

maintained Court Building ;

(c) We hold that the plea of financial limitations or

constraints cannot be normally an excuse to avoid

ash 32 pil-239,10n-wp-5101.12-

courtinfrastructure

performance of the aforesaid constitutional duties of

the Government;

(d) As observed in the earlier part of the judgment and

order, we direct the State Government to take a

policy decision and to formulate a scheme for

effectively dealing with the proposals for

ig construction of Court complex and judicial quarters,

work of expansion or extension of existing buildings

and the work of carrying out the repairs to it;

(e) The scheme shall be framed in such a manner that

all the unnecessary delays are curtailed and the

administrative as well as financial sanctions are

granted within a time bound schedule in case of

each proposal. The Scheme should provide for a

standardized procedure. The endeavour shall be to

provide a single window system. The Scheme shall

be formulated after taking into consideration the

law laid down by this Judgment and the

observations made herein. A policy decision shall be

taken on the aspect of permitting the Courts to

acquire furniture required for the Court buildings

ash 33 pil-239,10n-wp-5101.12-

courtinfrastructure

and the judicial quarters directly be adopting e-

tender process without the intervention of the PWD;

(f) Before taking a policy decision, the State

Government shall consult the Registrar/s nominated

by the High Court Administration as well as the

learned senior counsel Shri Kumbhakoni appointed

ig as an Amicus Curiae The learned Government

Pleader who has appeared in all the three cases shall

be a part of the process of consultation ;

(g) Appropriate decision shall be taken by the State

Government and the scheme shall be formulated by

the State Government as expeditiously as possible

and in any event on or before 31st October 2015;

(h) We direct the State Government to ensure that the

construction of the Court as well as judicial quarters

at Panvel in the District Raigad, is completed on or

before 31st March 2016;



                      (i)          We   make   it   clear   that   the   construction   shall   be 

                                   completed   in   such   a   manner   that   the   Court 



      ash                                                         34         pil-239,10n-wp-5101.12-
     courtinfrastructure

                                   complexes   as  well   as  judicial     officers'  quarters  at 




                                                                                         

Panvel become fully functional with effect from 1st

April 2016;

(j) Considering the grievance made that there is no

appropriate access road to the new Court complex at

Panvel and considering the grievance that there is

ig no adequate parking facility proposed, the State

Government shall take all possible steps to ensure

that appropriate access road having adequate width

is provided to the Court complex and adequate

parking facilities are provided-the State Government

shall also take into consideration the fact that during

the last few years, there is enormous rise in the

filing of Civil and Criminal cases in the Court at

Panvel ;

(k) We direct the State Government to ensure that the

construction of Court building at Ahmednagar is

completed in all respects on or before 30 th

September 2016 and the building becomes fully

functional for functioning of the Court with effect

from 1st October 2016.

      ash                                                       35          pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                        
                      (l)          A policy decision shall be taken by the High Court 

Administration as regards the standard size of the

Bar rooms;

(m) We direct the State Government to complete the

construction of the Court building as well as the

judicial officers' quarters at Navi Mumbai as

ig expeditiously as possible and in any event on or

before 30th June 2016;

(n) As in case of other Courts, the State Government

shall ensure that the construction is completed in all

respects on or before 30 th June 2016 so that actual

user thereof can start on or before 1st July 2015;

(o) In case of all the three projects, the estimates for

internal and external works shall be submitted as

indicated in this Judgment at least six months before

the scheduled outer date for completion. We Make it

clear that the time to complete the process of

construction of the buildings fixed under this

Judgment will not be normally extended;

      ash                                                        36          pil-239,10n-wp-5101.12-
     courtinfrastructure

                      (p)          We   direct   the   State   Government   to   ensure   that   a 




                                                                                         
                                   lease   is   executed   by   the   City   and   Industrial 

Development Corporation of Maharashtra Limited in

respect of the plot below the Court building and

judicial officers' quarters in New Bombay in favour

of the State Government in the Law and Judiciary

Department as expeditiously as possible and in any

ig event on or before 30th November 2015. The State

Government shall also explore the possibility of

getting the plot re-transferred to it without payment

of premium;

(q) As far as the payment of stamp duty on lease is

concerned, it will be open for the State Government

to avail of exemption under Sub-section (3) of

Section 3 of the Maharashtra Court Fees Act, 1958;

(r) A far as compliance with the directions to frame the

scheme and to take a policy decision as well as

compliance with the direction of execution of the

lease is concerned, the appropriate officer of the

State Government shall file compliance affidavit on

or before 20th November 2015;

      ash                                                       37         pil-239,10n-wp-5101.12-
     courtinfrastructure




                                                                                       
                      (s)          A separate compliance affidavit shall be filed stating 

                                   the   arrangement   which   the   State   Government 




                                                               

proposes to make as regards the access to the Court

building at Panvel and for providing adequate space

for parking at the Court premises at Panvel;

(t) ig For consideration of the aforesaid compliance, place

these three Petitions under the caption of

"Directions" on 30th November 2015;

(u) The Rule issued in the aforesaid three Petitions is

disposed of on above terms.

              (REVATI MOHITE DERE, J)                                   ( A.S. OKA, J ) 






 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter