Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Lakshmi Machine Works Ltd vs Marathe Textiles Mills And Anr
2013 Latest Caselaw 199 Bom

Citation : 2013 Latest Caselaw 199 Bom
Judgement Date : 25 November, 2013

Bombay High Court
Lakshmi Machine Works Ltd vs Marathe Textiles Mills And Anr on 25 November, 2013
Bench: Anoop V. Mohta
                                           1     18-ao-1105-13 with caa-1332-13.sxw


    dgm




                                                                              
             IN THE  HIGH COURT OF JUDICATURE AT BOMBAY




                                                      
                        CIVIL APPELLATE JURISDICTION

                   APPEAL FROM ORDER NO. 1105  OF 2013
                                 WITH




                                                     
                             CAA/1332/2013


    Lakshmi Machine Works Ltd.                  ....   Appellant 




                                         
         vs
    Marathe Textiles Mills and anr
                            ig                        ....    Respondents


    Mr.Raju Subramanian, Senior Advocate with Mr. Paritosh Jaiswal with 
                          
    Mr. Ashok Purohit and Shalaka Mali i/by M/s. Ashok Purohit & Co. for 
    the Appellants.
    Mr.   Rashid   Khan   with   Ms.   Priyanka   Kothari   and   Mr.   Balasaheb 
    Deshmukh i/by Mr. Balasaheb Deshmukh for respondent No.1.
        


    Mr. Paritosh Jaiswal i/by Mr. Prashant Kulkarni for respondent No.2. 
     



                                   CORAM:  ANOOP V. MOHTA, J.

DATE : November 25, 2013

ORAL JUDGMENT:

The Appellant/original Defendant has filed the present

Appeal from Order challenging Order dated 11.12.2012 passed by the

learned Joint Civil judge, Senior Division, Sangli, whereby

Applications at Exhibits 20 and 31, under Section 34 of the Arbitration

Act, 1940 (Act of 1940) were rejected and thereby directed the parties

to proceed expeditiously in the Suit. The Plaintiff filed the Suit on

2 18-ao-1105-13 with caa-1332-13.sxw

22.03.1993 for the breach of contract by mis-performance/delay in

supplying the machineries so agreed. The prayers are joint and

several against both the Respondents (Defendants). An mandatory

injunction was also sought against them to continue to supply the

spares of the machinery supplied by them and to provide service

maintenance.

Both the contesting Respondents/Defendants filed these

Applications within reasonable time i.e. 17.06.1994 and thereby

requested to stay the civil proceedings till the disposal of arbitration

proceedings in view of Section 34 of the Act of 1940. By the

impugned order, both the Applications were rejected. We are not

concerned at this stage the delay in rejecting such Applications which

is practically more than 19 years.

3 Admittedly, two Revisions filed by the Appellants within

limitation and thereafter challenged common order dated 11

December 2012. On 13 September 2013, the learned Judge, after

recording the submissions, permitted the Appellants to file an Appeal

from Order and thereby continued the ad interim reliefs granted in the

Revisions for four weeks. The Revision Applications were accordingly

3 18-ao-1105-13 with caa-1332-13.sxw

disposed of with liberty to the Applicants to file appropriate Appeals

from Orders. The Appeal is therefore preferred by the Appellants only

and not the Agents/Respondent No.2. There is no dispute with regard

to the acceptance of order/offer in question subject to the enclosed

General Conditions of Sale of Goods (Reference No. 771-D). Letter

dated 23 August 1989 also refers to "the enclosed General Conditions

of Sale of Goods". There is no dispute that the parties, based upon

proposal and offer, accepted the contract and proceeded accordingly.

There was no objection raised at any earliest point of time

immediately after receipt of the order of acceptance where reference

is made to the General Conditions of Sale of Goods. The objection

was raised for the first time only in reply filed to the Applications filed

by the Appellant about the non-receipt of General Conditions and

specifically the last pages which reflects arbitration clause in question.

The arbitration clause is reproduced as under :

"X ARBITRATION

Any dispute whatsoever touching the quotation/contract including any dispute arising out of resale under Clause VII (b) shall be referred to two arbitrators each residing in Coimbatore holding responsible position in a firm or company which is a member of the Indian Chamber of Commerce Coimbatore, one to be appointed by each party to the dispute. The arbitrators shall before proceeding with the arbitration, nominate an umpire qualified as above

4 18-ao-1105-13 with caa-1332-13.sxw

mentioned and in the event of their inability to agree on an umpire the arbitrators will request the President

of the Indian Chamber of Commerce Coimbatore to recommend an umpire and the umpire suggested by

the said President can be chosen by two arbitrators. The arbitration will be held in accordance with the provisions of the Indian Arbitration Act 1940 and/or any then subsisting statutory modifications thereof."

Respondent No.1/Plaintiff submitted that as there was denial to the

acceptance and/or receipt of these Conditions including arbitration

clause, the submission that there exists no arbitration agreement

between parties, rightly accepted by the learned Judge and thereby

rejected those Applications is, in my view, unacceptable, specially

when there is nothing on record to show and/or justify and/or any

objection taken immediately after receipt of the acceptance of order

dated 23 August 1989 including the terms and conditions having

arbitration clause. Admittedly, it is a commercial contract between

the parties. The regular practice and/or usage and such terms and

conditions in the market while dealing with such goods is not new

and/or foreign to any of the parties. The dispute, if any, touching the

quotation/contract including the terms required to be referred to the

Arbitrator as prescribed under the Indian Chamber of Commerce

Coimbatore Rules, Regulations and/or Conditions. The arbitration

required to be held in accordance with the provisions of the Indian

5 18-ao-1105-13 with caa-1332-13.sxw

Arbitration Act 1940 and/or any other subsisting statutory

modification thereof.

4 The learned Judge, in my view, overlooked the basic

principle specially in view of the present facts and circumstances when

there was no objection raised at earliest point of time about the

written documents and the non-receipt of the General Conditions in

question. The basic burden lies upon the Plaintiff to prove otherwise.

At ad interim stage, the Court, in my view, failed to consider the

following observations and the principles so announced by the

Supreme Court.

5 The Apex Court in Food Corporation of India and anr v.

Yadav Engineer and Contractor,1 has observed referring to Section 9

of Code of Civil Procedure (CPC) and Arbitration Act in the following

words :-

"4 ...................... No two contracting parties are under any legal obligation to provide for an arbitration agreement. If the parties enter into an arbitration agreement implying that they would like that the disputes covered by the agreement will be resolved by a forum of their choice, the approach of the Court must be that parties to the

1 AIR 1982 SUPREME COURT 1302

6 18-ao-1105-13 with caa-1332-13.sxw

contract are held to their bargain. If in breach or derogation of a solemn contract a party to an

arbitration agreement approaches the Court and if the other side expeditiously approaches the Court

invoking the Court's jurisdiction to stay the proceedings so that by this negative process the Court forces the parties to abide by the bargain, ordinarily the Court's approach should be and has

been to enforce agreements rather than to find loopholes therein. More often it is found that solemn contracts are entered into on the clearest understanding that any dispute arising out of the

contract and covered by the contract shall be referred to arbitration. It may be that one or the

other party may not have entered into the contract in the absence of an arbitration agreement. Therefore, when in breach of an arbitration

agreement a party to the agreement rushes to the Court, unless a clear case to the contrary is made out the approach of the Court should be to hold parties to their bargain provided necessary

conditions for invoking S. 34 are satisfied."

6 Therefore, in view of above clear position of law and in the

present facts and circumstances, I see there is no reason for the

learned Judge to reject such Applications for the reason so recorded.

7 The learned Judge, in my view, therefore, is wrong while

rejecting those Applications mainly on the ground that the agreement

was not signed by the Plaintiff and Defendants and, therefore,

overlooked the arbitration clause in the agreement. It is further

observed that this can be decided by recording evidence by both the

7 18-ao-1105-13 with caa-1332-13.sxw

parties. The learned Judge is wrong in holding that the relief so

prayed cannot be granted by the Arbitral Tribunal. The injunction so

sought in prayer clause (bb), even if, is a matter of discussion for the

Arbitral Tribunal to grant relief, but considering the facts and

circumstances, now practically in view of lapse of more than 20 years,

the mandatory injunction so sought need to be tested and can be

tested even by the learned Arbitrator. Prayers (a) and (b), if we take

note of and there was delay and the reason for the damages was delay

in supply of machinery and, therefore, unless the same is considered

by the learned Arbitral Tribunal, the grant of protection as prayed in

prayer (bb) required to be tested even by the learned Arbitrator.

8 The learned counsel appearing for the Appellant, on

instructions, makes statement that they have no objection, if they

make submission before the learned Arbitral Tribunal with regard to

prayer (bb). Let the learned Arbitral Tribunal to consider the same in

accordance with law.

9 The scope, purpose and object of arbitration proceedings

in view of above decisions and the pronouncements made by Hon'ble

Supreme Court from time to time and in the present facts, case is

8 18-ao-1105-13 with caa-1332-13.sxw

made out by the Appellant to interfere with the order . Order

accordingly.

10 Even considering the submissions so raised by the learned

counsel appearing for the Plaintiffs that let trial be proceeded

expeditiously and there is no point now referring to the Arbitral

Tribunal is also unacceptable. I am inclined to observe that

considering the contract between the parties, apart from the terms

and conditions and the fact of having provisions to settle such

disputes, through the agreed Tribunals, would assist the Plaintiffs to

get the dispute resolved at earliest rather than resorting to the Civil

Court jurisdiction as done in the present case. The tenure of the

order, even if accepted, during the trial and/or after leading evidence

by and between the parties, if Court comes to conclusion that there

exists arbitration clause, the proceedings again required to be

transferred and/or stayed, as it would be for the Arbitrator to decide

the claim so raised by the Plaintiff in the Suit. There will be further

delay if the course as adopted and/or insisted by the learned counsel

appearing for the Plaintiff and/or by the Plaintiffs. This observation

is only because the learned counsel appearing for Respondent No.1

also opposing the present Appeal on the ground of delay and insisted

9 18-ao-1105-13 with caa-1332-13.sxw

to contest the matter before the Civil Court. Both the parties by

consent can proceed accordingly, but once the Application is filed

under Section 34 of Arbitration Act and submission is made and as a

case is made out, the Court cannot overlook the provisions so referred

above, merely because Respondent No.2 (Agent) failed to challenge

the order by filing separate Appeal from order, though he was party to

the order passed by the learned Judge in Revisions dated 13

September 2013. Once the common order goes, in view of above, the

submission even if any would not be sufficient to grant relief so

prayed by the Appellant in the Application as well as in the Appeal

from Order. In view of order dated 13 September 2013, the

submission that there was no separate Application filed for

condonation of delay in filing the present Appeal is of no assistance to

reject the Appeal as this Court granted liberty to the Applicant to file

appropriate Appeal from order on 13 September 2013 itself. There

was no issue with regard to the delay and now in the present Appeal,

in view of above admitted position, there is no delay in filing the

Appeal itself.

11 Considering the pendency of the dispute between the

parties, I am inclined to observe that having once allowed the

10 18-ao-1105-13 with caa-1332-13.sxw

Application filed by the Appellant under Section 34 of the Act of 1940,

the effect will be of staying the Suit and the Arbitral Tribunal will

decide the main dispute between the parties. It is therefore desirable

that the Arbitral Tribunal to adjudicate and resolve the dispute

preferably within a year. Both the parties to cooperative for early

disposal. The parties to take steps accordingly.

    12            In the result, the following order :
                               
                                O R D E R
                              
            (i) The   Appeal   from   Order   is   allowed.       The 
            impugned order is quashed and set aside.

(ii) The Applications at Exhibits 20 and 31 are

allowed.

(iii) The Arbitration proceeding is expedited. To be disposed of within one year.

(iv) Both the parties to cooperate for early disposal of

even before arbitral tribunal.

            (v)    No costs.





    13            The   learned   counsel   appearing   for   Respondent/Plaintiff 

    seeks stay of this order.    As the request is to stay its own proceedings, 

the learned counsel appearing for the Appellant submitted that the

Suit should not be proceeded further in view of this order passed by

this Court.

                                         11    18-ao-1105-13 with caa-1332-13.sxw




                                                                           
    14         The order   passed by this Court is accordingly stayed for 




                                                   

four weeks, but the Suit of Appellant will not be proceeded till further

order.

15 In view of disposal of Appeal from Order, Civil Application

No. 1332 of 2013 is also disposed of accordingly. No costs.

(ANOOP V. MOHTA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter