2012 Latest Caselaw 409 Bom

Citation : 2012 Latest Caselaw 409 Bom
Judgement Date : 29 November, 2012

Bombay High Court
Housing Development And ... vs Mumbai International Airport ... on 29 November, 2012
Bench: S. J. Kathawalla
                                                      1                ARBPL 1538-12-Judgment.doc

                       IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                         
                             ORDINARY ORIGINAL CIVIL JURISDICTION 
                           ARBITRATION PETITION (L) NO.1538 of 2012




                                                                 
    Housing Development and Infrastructure Limited. ]                      ... Petitioner




                                                                
                       Versus

    Mumbai International Airport Private Limited                   ]
    and others.                                                    ]       ... Respondents              




                                                   
    Mr. T. N. Subramaniam,  Senior Advocate, a/w Mr. Gaurav Joshi, Mr. Piyush 
                                        
    Raheja, Mr. Satyen Vora, Mr. Atul Kshatriya, Mr. Sanmish Gala & Mr. Chetan 
    Yadav i/b Markand Gandhi & Co. for Petitioner.
                                       
    Mr. Virag Tulzapurkar, Senior Advocate, a/w Dr. Birendra Saraf, Ms. Shoma 
    Maitra & Mr. Atharva Dandekar i/b Wadia Gandhy & Co. for Respondent No1.

    Mr. Snehal Shah a/w Ms. Dipti Panda & Ms. Amita Jasani i/b Purnanand & 
    Co. for Respondent No.2 - Punjab & Maharashtra Co-operative Bank Limited.
           
        



    Mr. A. Ketkar for Respondent No.4.


                                                   CORAM :-    S. J. KATHAWALLA, J. 
                                                   DATE     :-    NOVEMBER 29, 2012


    ORAL JUDGMENT :-





    1.       Mentioned.  Not on board, taken on board.


2. The Petitioner has filed the above Arbitration Petition under Section 9 of the Arbitration and Conciliation Act, 1996, inter alia, for an order and injunction restraining the Respondent No.1 from invoking or encashing or receiving payments under the Bank Guarantee No.3023/4018/152/07-08

URS 1 of 25

2 ARBPL 1538-12-Judgment.doc

read with Extension Bank Guarantee No.3023/4018/229/09-10 dated 11th

May 2012 or further extended bank guarantees as may be furnished to the Respondent No.1 from time to time. The Petitioner has also sought an order

and injunction against the Respondent No.2 bank from making payment or otherwise causing payment to be made under the said Bank Guarantees.

3. An application for urgent orders was made before this Court today at 11.00 a.m. by the learned Senior Advocate appearing for the Petitioner without giving notice to the Respondents. However, the Respondent No.1

appeared through their Advocates and informed the Court that a copy of the

petition should be served on them, and necessary orders be passed only after giving them a hearing in the matter. The matter was therefore kept at 3.00

p.m. and it was ordered that in the meantime, the Respondent No.2 Bank shall not act on the letter received from Respondent No.1 dated 27 th November 2012. The matter was taken up at around 5.00 p.m., and it was

decided by consent that the arbitration petition be decided finally. In view

thereof, the Respondents have not filed any Affidavits-in-Reply and are allowed to proceed in the matter on the basis of denials.

4. The facts, as narrated by the Petitioner, are briefly set out herein :

5. The Petitioner - Housing Development and Infrastructure Limited

(HDIL) is a renowned real estate company which is executing several large residential and commercial projects in the city of Mumbai, including various SRA projects. The Respondent No.1 Mumbai International Airport Private Limited (MIAPL) is a Private Limited Company selected by the Airports Authority of India (AAI) to operate, manage, develop, design, upgrade and modernize the Chhatrapati Shivaji International Airport ('the Airport') at

URS 2 of 25

3 ARBPL 1538-12-Judgment.doc

Mumbai. Respondent No.2 Punjab and Maharashtra Co-operative Bank

Limited is a Bank which has provided the performance guarantee ('the said bank guarantee') to the Respondent No.1, at the request of the Petitioner in

the circumstances set out hereinafter. Respondent No.3 is Mumbai Metropolitan Regional Development Authority (MMRDA) and has been appointed by the Respondent No.1 as the project implementation agency for

undertaking slum clearance. Respondent No.4 is the State of Maharashtra joined as a party through the Collector, Mumbai Suburban District. According to the Petitioner, it is the duty of the Respondent No.4, inter alia, to determine

the eligibility of slum dwellers who are entitled to be rehabilitated in the

premises constructed/to be constructed by the Petitioner under its Agreements with the Respondent No.1. The Respondent No.5 is Slum Rehabilitation

Authority established under the Maharashtra Slum Areas (Improvements, Clearance and Redevelopment) Act, 1971 and acts as the planning authority for the slum rehabilitation project.

6. According to the Petitioner, as already stated hereinabove, under an Agreement dated 4th April 2006 executed between the AAI and the Respondent No.1, AAI granted to the Respondent No.1 exclusive right to

operate, maintain, develop, design, construct, upgrade, modernize finance and manage the Airport. Thereafter AAI also executed a Lease Deed dated 26th April 2006, in favour of Respondent No.1 wherein certain land (the

Airport Land) was leased in favour of the Respondent No.1. At the time of the aforesaid Agreement, nearly 276 acres of the Airport Land was encroached upon by the slums. Accordingly Respondent No.1 desired to have the said slums cleared from the Airport Land.

    URS                                                                                            3 of 25




                                                    4                ARBPL 1538-12-Judgment.doc

7. Pursuant to an Agreement dated 12th December 2006, the Respondent

No.1 appointed MMRDA as the project implementation authority for undertaking slum clearance. Thereafter on 18th April 2007, the Respondent

No.1 issued an invitation seeking expression of interest from bidders for undertaking a slum rehabilitation project for clearing the said encroachments on the Airport Land. The Petitioner responded to the said invitation and by a

Letter of Intent dated 15th October 2007, the Respondent No.1 awarded the said slum rehabilitation project to the Petitioner. Simultaneously on the same day i.e. on 15th October 2007, the Petitioner and the Respondent No.1 entered

into an Agreement (the said Agreement) setting out the terms and conditions

for execution of the said slum rehabilitation project by the Petitioner, a copy of which Agreement is annexed at Exhibit 'D' to the petition.

8. Clause 3 of the said Agreement sets out the scope of work which was to be undertaken by the Petitioner for completion of the said slum rehabilitation

project, which work included eviction of ineligible slum dwellers and

rehabilitation of protected slum dwellers, demolition of hutments, construction of rehabilitation buildings and handing over of vacant land to Respondent No.1. Clause 4 sets out the consideration to be received by the

Petitioner for executing the said slum rehabilitation project. The said clause provided that the Petitioner is entitled to receive 65.20 acres of land from the Airport Land, upon the same being released from the encroachments. No

monetary consideration was payable under the said Agreement to the Petitioner.

9. Clause 8 of the said Agreement provided for a performance security and reads as under :

    URS                                                                                       4 of 25




                                                     5                ARBPL 1538-12-Judgment.doc




                                                                                        
          "8.     PERFORMANCE SECURITY
          8.1     The  Developer  has submitted  an unconditional  irrevocable  




                                                                

and on demand bank guarantee dated October 15, 2007 for Rs.25 (Twenty Five) crores from Punjab and Maharashtra Co-operative Bank Limited in favour of MIAL and an on demand promissory

note dated October 15, 2007, for Rs.275 (two hundred and seventy five) crores as performance security, for performance of its

obligations hereunder. The said bank guarantee and promissory note shall be retained as security for performance by the Developer

of its obligations (including warranties). The Developer shall, no later than 12 (twelve) months from the date of the LOI, replace the

bank guarantee and the said promissory note by an interest free cash deposit of Rs.300 (three hundred) crores. Such deposit shall be made by way of a demand draft / pay order or wire transfer

and the said bank guarantee and promissory note shall be released

simultaneously with the receipt of the demand draft / pay order or, in the case of a wire transfer, simultaneously with the cash deposit being received by MIAL (the said bank guarantee together with the

promissory note or the interest free cash deposit in lieu thereof is hereinafter referred to as the "Performance Security"). The Performance Security shall be refunded to the Developer, subject to

such set offs and deductions as MIAL may be entitled to make under this Agreement or otherwise, 5 (five) years from the date of deposit or 12 (twelve) months after Project Completion, whichever is later or upon the earlier termination of this Agreement.

    URS                                                                                          5 of 25




                                                  6                ARBPL 1538-12-Judgment.doc




                                                                                    
          8.2    The   Performance   Security   may   be   invoked,   drawn   down,  

appropriated or adjusted by MIAL at the sole discretion of MIAL for

non performance by the Developer, and non performance includes the following events :

(i) Breach of or failure by the Developer to comply with any of

the terms and conditions of this Agreement or any further agreement to be executed between MIAL and the Developer

amounting to a material breach of this Agreement or such further agreements; and

(ii) Failure of the Developer to replace the bank guarantee and

the promissory note by the cash deposit as mentioned in this Clause hereinabove.

8.3 If at any time the Performance Security is invoked, drawn

down, appropriated or adjusted, the Developer shall ensure that the value of the Performance Security is always maintained at the level indicated hereinabove by replenishing or issuing additional

security as above Invocation, draw down, appropriation or adjustment of the Performance Security does not absolve the Developer from its obligations to perform the Scope of Work, under

the agreement."

10. As agreed under said Clause 8, the Petitioner furnished to the Respondent No.1, a Bank Guarantee dated 15th October 2007 for Rs.25 crores, issued by the Respondent No.2 Bank. A copy of the said Bank Guarantee is annexed and marked as Exhibit 'E' to the petition. The Petitioner has also

URS 6 of 25

7 ARBPL 1538-12-Judgment.doc

furnished a Demand Promissory Note of Rs.275 crores to the Respondent No.

1. According to the Petitioner, the said Bank Guarantee has been continuously renewed by the Petitioner at the request of Respondent No.1, the last renewal

being made in May 2012.

11. Clause 24 of the said Agreement sets out the events of default, and

Clause 25 pertains to termination of the Agreement.

12. Clause 35 of the said Agreement provides for resolution of disputes

between the parties by arbitration which clause is reproduced hereunder :

"35. ARBITRATION Any and all claims, disputes, questions or controversies involving

the Parties and arising out of or in connection with or relating to this Agreement, or the execution, interpretation, validity, performance, breach or termination hereof (including, without

limitation, the provisions of this Clause (collectively, (Disputes")

shall, in the first instance be resolved by mediation by the mediators namely the Managing Director of MIAL and, the Chairman of the Developer. In the event that the Dispute is not

resolved through mediation then it shall be submitted to arbitration in accordance with the Arbitration and Conciliation Act, 1996 and any rules, regulations made thereunder, or

amendments thereto or re-enactment thereof".

13. Mr. T. N. Subramaniam, the Learned Senior Advocate appearing for the Petitioner submitted that upon execution of the said Agreement, pursuant to Clause 8.1 thereof, the Petitioner, through Respondent No.2, furnished a Bank Guarantee in the sum of Rs.25 crores and also executed a Demand Promissory

URS 7 of 25

8 ARBPL 1538-12-Judgment.doc

Note of Rs.275 crores in favour of Respondent No.1. The Petitioner, with all

earnestness, also commenced the work of the said rehabilitation project. The Petitioner constructed 7,000 tenements and is completing construction of

20,000 flats. The Petitioner has incurred an expenditure in excess of Rs.3000 crores in respect of the said project, including money expended for acquisition of lands, construction of tenements, provision of facilities to the Respondent

No.4 and its officers to carry out eligibility surveys etc. The Petitioner also shifted approximately 650 slum dwellers and provided permanent alternate accommodation to them. However the Respondent No.1, along with

Respondent Nos. 3 to 5, has failed and neglected to fulfill their various

statutory obligations, as a result whereof the list of eligible slum dwellers is not finalized, due to which more than approximately 7,000 tenements which

are fully constructed by the Petitioner are lying vacant. It is submitted that the Petitioner was required to give a cash deposit of Rs.300 crores to the Respondent No.1 in place of the said Bank Guarantee of Rs.25 crores and the

Demand Promissory Note of Rs.275 crores, within 12 months from the date of

the said Agreement. However, the said condition came to be waived by Respondent No.1 who repeatedly accepted renewal of the said Bank Guarantee without protest, the last renewal was on 11th May 2012. It is

submitted that as late as in October 2012, in a meeting held with Respondent No.4, the issue regarding the submission of the list of slum dwellers through Respondent Nos.1 and 3 to the office of the Collector for verification was

discussed, inter alia, in order to enable the Collector to determine the eligibility of the slum dwellers particularly in the priority areas determined by Respondent No.1. The Minutes of the said meeting are annexed and marked as Exhibit 'B' to the petition. It is submitted that Respondent No.1 and its representatives who attended the said meeting, never disputed the obligations set out thereunder, but thereafter have not complied with what was agreed.

    URS                                                                                           8 of 25




                                                      9                ARBPL 1538-12-Judgment.doc

14. Mr. Subramaniam on behalf of the Petitioner further submitted that

despite the aforestated facts, the Respondent No.1 without any notice as contemplated under the contract between the parties or even otherwise, has

sought to surreptitiously invoke the bank guarantee by its letter 27th November 2012 addressed to the Respondent No.2. alleging non performance by the Petitioner herein. Relying on the decision of the Hon'ble Supreme

Court in the case of Hindustan Construction Co. Ltd. Versus State of Bihar And Others, reported in (1999) 8 Supreme Court Cases 436, Mr. Subramaniam submitted that the said bank guarantee issued by the Respondent No.2 in

favour of the Petitioner, at the instance of the Respondent No.1 is a

conditional bank guarantee and the same has been invoked without complying with the condition contained therein viz. to establish that the

Petitioner has failed to perform any of its obligations (including warranties), under the Letter of Intent or the said Agreement. Mr. Subramaniam has submitted that therefore the Respondent No.1 has sought to fraudulently and

unjustifiably enrich itself at the expense of the Petitioner. He submitted that

the fraudulent conduct of Respondent No.1. is further fortified by Clause 8.3 of the said Agreement which requires the Petitioner, after invocation of the said guarantee, to give further securities/guarantees to the Respondent No.1

which again Respondent No.1 is entitled to invoke. Mr. Subramaniam has submitted that therefore the fraud perpetrated by the Respondent No.1 is of such an egregious nature that it would vitiate the very foundation of the

contract as well as the bank guarantee and render the bank guarantee ineffective, null and void. He submitted that in any event, irretrievable injustice would be caused to the Petitioner if the invocation of the bank guarantee is not stayed, inter alia, as the invocation is not attributable to any fault of the Petitioner. Relying on the decision of the Hon'ble Supreme Court in the case of Svenska Handelsbanken Versus M/s. Indian Charge Chrome And

URS 9 of 25

10 ARBPL 1538-12-Judgment.doc

Others, reported in (1994) 1 Supreme Court Cases 502, he submitted that even

the special equities in the present case are in favour of the Petitioner. He therefore submitted that the arbitration petition be allowed and the

Respondent No.1 be restrained from invoking or encashing or receiving payments under the said bank guarantee.

15. Mr. Virag Tulzapurkar, the Learned Senior Advocate appearing for Respondent No.1, without prejudice to the contention of the Respondent No.2 submitted that since the Respondent No.2 Bank is not a party to the main

contract dated 15th October 2007, and that the contract of guarantee does not

contain an Arbitration Agreement, the present petition filed by the Petitioner under Section 9 of the Act is not maintainable, proceeded to make his

submissions on behalf of the Respondent No.1 on merits. Mr. Tulzapurkar first submitted that the reliance placed by the Petitioner upon the Judgment of the Hon'ble Supreme Court in Hindustan Construction Co. Ltd. Versus State of

Bihar And Others (supra) is misplaced, as the language of the guarantee in

that case was materially different from the language of the guarantee in the present case. He therefore submitted that the submission made on behalf of the Petitioner that the suit guarantee is conditional and the conditions

stipulated therein have not been met, are untenable and baseless and that the guarantee is in fact unconditional and irrevocable, containing an unequivocal promise to pay a sum of Rs.25 crores to the Respondent No.1 without any

demur or protest, and the same ought to be encashed.

16. Mr. Tulzapurkar has, without prejudice to his contention that an unconditional and irrevocable bank guarantee is an independent contract and whether encashment of the same ought to be permitted or not has to be considered without any reference to the underlying or main contract or to the

URS 10 of 25

11 ARBPL 1538-12-Judgment.doc

disputes/claims thereunder, has taken me through some of the provisions of

the said Agreement. Mr. Tulzapurkar, referring to Clause 3.1 of the said Agreement which pertains to the scope of work of the petitioner, pointed out

that the said clause categorically provides that the Petitioner is required to take all the necessary steps for completion of the slum rehabilitation project and make available to the Respondent No.1 the encroached Airport Land, free

of any encroachments/hutments, in accordance with the provisions of the said Agreement, including the time lines prescribed therein. Further, the steps required to be taken by the Respondent No.2 would include completion of the

plane table survey in a timely manner. "Plane Table Survey" is defined in the

Agreement to mean "the survey to determine the eligibility of slum dwellers for rehabilitation and finally verified under the Applicable Law". Mr.

Tulzapurkar submitted that the Petitioner has attempted to give an incorrect interpretation to the Minutes of the Meeting held on 17th October 2012 and that a proper construction and interpretation of the Minutes shows that the

Petitioner has failed to give its submissions and conduct survey qua several

plots of lands as set out in the said Minutes. Mr. Tulzapurkar has also drawn my attention to Clause 4 of the said Agreement wherein the Petitioner has agreed to remove the encroachments in a phased manner. Phase 1 itself is

divided into 3 phases and the Petitioner was obliged to remove at least 28,000 hutments in Phase 1. Mr. Tulzapurkar submitted that the Petitioner has failed to remove a single hutment out of the said 28,000 hutments till date and

construction of 7000 tenements is of no consequence in the absence of removal of the hutments from the lands encroached upon. The 650 hutments allegedly removed by the Petitioner are not part of these 28,000 hutments. Mr. Tulzapurkar has submitted that the Petitioner has agreed under the said Agreement that the scope of work shall be complete at the sole cost and expense of the Petitioner and the Petitioner now cannot make a grievance

URS 11 of 25

12 ARBPL 1538-12-Judgment.doc

about the same and cannot allege that Respondent No.1, not having spent any

amount on the redevelopment project, is fraudulently invoking the bank guarantee. Mr. Tulzapurkar submitted that Respondent No.1 is justified in

invoking the bank guarantee since the Petitioner has failed to perform its obligations under the said Agreement.

17. Mr. Tulzapurkar has further submitted that under Clause 8 of the said Agreement, the Petitioner agreed to furnish an unconditional irrevocable and on demand bank guarantee to Respondent No.1 for Rs.25 crores and an on

demand Promissory Note for Rs.275 crores as performance security for

performance of its obligations under the said Agreement. Under the said clause, the Petitioner also agreed that within 12 months from the date of the

LOI (which is dated 15th October 2007), the Petitioner shall replace the bank guarantee and the said Promissory Note by an interest free cash deposit of Rs. 300 crores and upon the Petitioner providing the said cash deposit, the said

bank guarantee and the said Promissory Note shall be released simultaneously.

Mr. Tulzapurkar has submitted that under Clause 8.2 of the Agreement, the parties have agreed that the performance security may be invoked in the event of breach or failure of the Petitioner to comply with any of the terms and

conditions of the said Agreement including failure of the Petitioner to replace the bank guarantee and the Promissory Note by cash deposit of Rs.300 crores. Mr. Tulzapurkar submitted that under Clause 8.3, the Petitioner has agreed

that if at any time the performance security is invoked, the Developer shall ensure that the value of the performance security is always maintained at the level indicated (i.e. Rs.300 crores), by replenishing or issuing additional security. Mr. Tulzapurkar submitted that having agreed to maintain the level of the performance security up to Rs.300 crores, the Petitioner cannot make a grievance that after invocation of the present bank guarantee, the Petitioner

URS 12 of 25

13 ARBPL 1538-12-Judgment.doc

will have to provide further security, which may also be invoked by the

Petitioner.

18. Mr. Tulzapurkar has, whilst dealing with the submission advanced on behalf of the Petitioner that the Respondent No.1 has failed to show the alleged non performance by the Petitioner, drawn my attention to the letter

written by Respondent No.1 to the Petitioner dated 26th June 2011, inter alia, recording that the Petitioner has failed to perform various obligations required to be performed by it under the captioned Agreements. The obligations set

out in the said letter, which according to the Respondent No.1 were breached

by the Petitioner, are set out hereinbelow :

"

    Sl.                          Obligation                           Agreement Clause Ref.
    No

1. Replacement of bank guarantee of Rs.25 crores 8.1 of the said and promissory note of Rs.275 crores, with a Agreement, as amended

cash deposit of Rs.300 crores, by 30th November, by Deed of Confirmation

2008. dated October 14, 2008.

2. Reimbursement to MIAL of the amount of Rs. 25 3.1(q)(v) of the said crores paid by MIAL to MMRDA under Agreement.

Agreement dated December 12, 2006 between

MIAL and MMRDA by 14th April, 2008

3. Completion of Phase 1(i) (by April 14, 2009), 7.1(a) of the said Phase 1(ii) (by October 14, 2009) and Phase Agreement. 1(iii) (by October 14, 2010).

4. Commencement of Phase 2 by October 14, 2010. 7.1(b) of the said Agreement.

5. Payment of fees to the PMC (M.M. Consultants 3.1(h) of the said Pvt. Ltd.). As on date we have been informed Agreement. that the PMC's invoices for a total amount of Rs.

15 lakhs are outstanding.

    URS                                                                                       13 of 25




                                                     14                ARBPL 1538-12-Judgment.doc

    Sl.                        Obligation                            Agreement Clause Ref.




                                                                                       
    No

6. Payment to M. M. Consultants Pvt. Ltd. of the 3.1(a) read with 301(h)

amount of Rs.16,16,152/- for Plane Table and 3.1(q) of the said Survey, an activity which was to be taken over Agreement. and completed by HDIL under the Agreement.

Failure to make payment has resulted in M. M.

Consultants Pvt. Ltd. not refunding equivalent

amount which was paid to M. M. Consultants Pvt. Ltd. by MIAL.

7. Amount of Rs.25 crores to be paid to MMRDA as 3.1(q)(v) of the said per MMRDA's letter No.Airport/Cost/2001/ 72 Agreement."

dated 21st April 2011 which has till date not been paid by HDIL.

By the said letter, the Respondent No.1 further informed the Petitioner that,

"In view of the non compliance of your various obligations under the captioned Agreements, you are called upon within a period of 30 days to comply with the same failing which we will have

no option but to take appropriate recourse under the captioned

Agreements and as available to us under law."

Mr. Tulzapurkar submitted that the Petitioner failed and neglected to reply to the said letter and has, in the present petition, made incorrect submissions viz.

that the Petitioner had, in response to the said letter, purportedly made representations and offered explanations to Respondent No.1 as alleged.

19. Mr. Tulzapurkar has further submitted that the submission advanced on behalf of the Petitioner that the Respondent No.1 has waived the condition qua the Petitioner substituting the bank guarantee of Rs.25 crores and the Promissory Note of Rs.275 crores by a cash deposit of Rs.300 crores, is false and incorrect to its knowledge. Mr. Tulzapurkar has in support of this submission, relied on Clauses 31 and 33 which pertain to "Modifications" and

URS 14 of 25

15 ARBPL 1538-12-Judgment.doc

"Waiver" and has submitted that under the said Agreement the parties have

expressly agreed that no modifications to the Agreement shall be permitted unless they are in writing and signed by both the parties and that any waiver

of any provision of the said Agreement by the Respondent No.1 shall be effective only if it is in writing. Mr. Tulzapurkar has submitted that it is because of these provisions that when the Petitioner was unable to give a cash

deposit of Rs.300 crores to the Respondent No.1 within 12 months from the date of the LOI, i.e. on or before 14th October 2008, and had sought extension of time from Respondent No.1, that an extension up to 30th November 2008

was granted to the Petitioner, by a Deed of Confirmation dated 14 th October

2008 executed between the parties. Mr. Tulzapurkar has submitted that thereafter the Respondent No.1 has not granted any extension to the

Petitioner for replacing the Bank Guarantee and the Demand Promissory Note by cash deposit of Rs.300 crores.

20. Mr. Tulzapurkar further submitted that despite serving the aforestated

notice dated 24th June 2011, the Petitioner has not complied with its obligations set out therein including the replacement of Bank Guarantee of Rs. 25 crores and Promissory Note of Rs.275 crores with a cash deposit of Rs.300

crores till date. He submitted that therefore the Respondent No.1 is fully justified in invoking the said bank guarantee and there is no fraud involved as alleged or otherwise, qua the said invocation. Mr. Tulzapurkar has further

submitted that no case of irretrievable injury or special equities is made out by the Petitioner. Mr. Tulzapurkar submitted that it is a well settled principle that except in cases of established fraud violating the very foundation of the bank guarantee or encashment resulting in irretrievable harm or injustice, which would make it impossible for the guarantor to reimburse itself if he ultimately succeeds, the Court shall not grant any injunction restraining the beneficiary

URS 15 of 25

16 ARBPL 1538-12-Judgment.doc

from invoking/encashing a bank guarantee. In support of his contention, Mr.

Tulzapurkar has relied on the decisions of the Hon'ble Supreme Court in the cases of Dwarikesh Sugar Industries Ltd. Versus Prem Heavy Engineering Works

(P) Ltd. And Another1 and Himadri Chemicals Industries Ltd. Versus Coal Tar Refining Co.2 Mr. Tulzapurkar has therefore submitted that the arbitration petition deserves to be dismissed with costs.

21. I have considered the submissions advanced by the learned Senior Advocates appearing for Petitioner as well as for Respondent No.1. The first

issue which needs determination by this Court is whether the bank guarantee

issued by Respondent No.2, at the instance of the Petitioner to the Respondent No.1, is an unconditional bank guarantee. Clause 1 of the bank guarantee

provides as under:

"..... We Punjab & Maharashtra Co-op Bank Ltd. (Multi-

State Scheduled Bank ("Guarantor") unconditionally and

irrevocably agree to pay to MIAL immediately on its first

demand, whole or part of Rs.25,00,00,000/- (Rupees Twenty Five Crore Only) (the "Guarantee Amount") without any protest or demur, contestation, reservation, recourse or

reference to the Developer, upon demand by MIAL for the breach or failure of the Developer to perform all or any of the Developer's obligations (including warranties) under the

Letter of intent or the Agreement ..... shall not be questioned and be final and conclusive. Upon written demand by MIAL, the Guarantor shall forthwith make the payment of the sum set out in such demand notice without any conditions,

1 (1997) 6 Supreme Court Cases 450 2 (2007) 8 Supreme Court Cases 110

URS 16 of 25

17 ARBPL 1538-12-Judgment.doc

reservations, protest of requirement of any proof

whatsoever...."

Clause 4 of the said Bank Guarantee further provides,

"We Punjab & Maharashtra Co-op Bank Ltd. (Multi-State Scheduled Bank), the Guarantor, agree and acknowledge that our obligation under this guarantee shall be primary,

absolute, irrevocable, continuing and unconditional. We Punjab & Maharashtra Co-op Bank Ltd. (Multi-State

Scheduled Bank), the Guarantor, also waive presentment to, demand of payment form and protest by MIAL to the

developer before invocation of this guarantee."

From the above terms of the Bank Guarantee, it is clearly established that the Respondent No.1 is entitled to invoke the same in case of failure on part of the Developer to perform all or any of its obligations under the Letter of Intent or

the Agreement. The Respondent No.1 is only required to issue a letter to the

Respondent No.2 Bank stating that the Petitioner has failed to perform all or any of its obligations (including warranties) under the Letter of Intent or Agreement and the Bank shall not question the decision of the Respondent

No.1, which shall be final and conclusive. The Bank has unconditionally and irrevocably agreed to forthwith make payment of the same as set out in the demand notice by the Respondent No.1 without any protest, demur,

contestation, reservation, recourse or reference to the Petitioner or requirement of any proof whatsoever. Therefore the stand taken by the Petitioner that the Bank Guarantee is conditional and that the Respondent No. 1 is obliged to establish that the Developer has failed to perform all or any of its obligations under the Letter of Intent and/or the said Agreement is untenable and baseless. The language of the guarantee in the case of

URS 17 of 25

18 ARBPL 1538-12-Judgment.doc

Hindustan Construction Co. Ltd. Versus State of Bihar And Others (supra) was

materially different from the language of the Bank Guarantee in the present case and would therefore lend no assistance to the Plaintiff. In my view, the

said Bank Guarantee is an unconditional and irrevocable guarantee. The submission therefore advanced on behalf of the Petitioner that the Bank Guarantee is a conditional one or that the invocation is not in keeping with

the same, and is bad in law, therefore cannot be accepted and is rejected.

22. As regards the contention of the Petitioner that the conduct of

Respondent No.1 in encashing the Bank Guarantee is fraudulent, the

Petitioner has relied on the provisions of the said Agreement and has tried to allege that though the Petitioner has performed its obligations under the said

Agreement, it is Respondent No.1 along with Respondent Nos. 3 and 4 who have not complied with their obligations under the said Agreement. The fact remains that the Petitioner has, despite having agreed under Clause 8.2 of the

Agreement to substitute the Bank Guarantee of Rs.25 crores and the

Promissory Note dated 15th October 2007 for Rs.275 crores, by cash deposit of Rs.300 crores initially on or before 14th October 2008 and thereafter on or before 30th November 2008, has not substituted the same till date. The

Petitioner has agreed under Clause 8.2 of the said Agreement that breach of or failure by the Petitioner to comply with any of the terms and conditions of the Agreement including the failure of the Petitioner to replace the bank

guarantee and the Promissory Note by cash deposit as mentioned in Clause 8.1of the Agreement would entitle the Respondent No.1 to invoke the bank guarantee. Failure of the Petitioner to replace the bank guarantee and Promissory Note with interest free cash deposit would also constitute an event of default under Clause 24 of the said Agreement. The Respondent No.1 has, by its letter dated 24th June 2011, set out the breaches committed by the

URS 18 of 25

19 ARBPL 1538-12-Judgment.doc

Petitioner qua several clauses of the said Agreement including Clause 8.1 of

the said Agreement as amended by the Deed of Confirmation dated 14 th October 2008, pertaining to replacement of the bank guarantee and the

Promissory Note with cash deposit of Rs.300 crores and, inter alia, calling upon the Petitioner to cure the said breaches within a period of 30 days from the receipt of the said notice. However, the Petitioner has not even replied to

this letter despite having received the same from the Respondent No.1. The Petitioner has in the petition alleged that after receipt of the letter, the Petitioner had made certain representations to the Respondent No.1 which

allegations are denied by the Respondent No.1. The allegation of the

Petitioner that the clause pertaining to substitution of the bank guarantee and a Promissory Note by cash deposit of Rs.300 crores is waived by the

Petitioner, also cannot be accepted in view of Clauses 31 and 33 of the Agreement which expressly states that no modification to the said Agreement shall be permitted unless they are in writing and are agreed and signed by

both the parties and any waiver of any provision of the Agreement by the

Respondent No.1 to be effective has to be in writing.

23. It is set out in the letter dated 24th June 2011 addressed by the

Respondent No.1 to the Petitioner and also submitted by Mr. Tulzapurkar that the Petitioner has miserably failed to comply with the other provisions of the said Agreement, more particularly the completion of Phase 1(i) by November

14, 2009, Phase 1(ii) by October 14, 2009 and Phase 1 (iii) by October 14, 2010 and commencement of Phase 2 by October 14, 2010, as agreed under Clauses 7.1 (a) and 7.1 (b) of the said Agreement. The Petitioner has not responded to the said letter dated 24th June 2011 and has refuted its contents for the first time only in the present petition i.e. after more than a year, on the ground that after receipt of the said letter dated 24th June 2011, the

URS 19 of 25

20 ARBPL 1538-12-Judgment.doc

Petitioner had made representation and explained the correct position to the

Respondent No.1, which again is denied by Respondent No.1. The said issues qua the compliance of the obligations under the said Agreement shall be

finally decided in the arbitration proceedings. Mr. Subramaniam has submitted that the Petitioner has spent substantial amounts after executing the said Agreement and the Respondent No.1 has not spent any amounts. He

has also submitted that after invocation of the present bank guarantee, the Petitioner is required to give further securities to the Respondent No.1 which again the Respondent No.1 is entitled to invoke. What is forgotten is that the

Petitioner has under the Agreement, agreed to substitute the bank guarantee

of Rs.25 crores and the Demand Promissory Note of Rs.275 crores by a cash deposit of Rs.300 crores and the Petitioner has further agreed to maintain the

value of the performance security at the level agreed i.e. Rs.300 crores by replenishing or issuing additional security. Needless to point out that it is well settled law that Courts cannot rewrite contracts.

24. The Hon'ble Supreme Court has in its decision in the case of Himadri Chemicals Industries Ltd. Versus Coal Tar Refining Co. (supra) observed that the law relating to grant or refusal to grant injunction in the matter of invocation

of a bank guarantee or a letter of credit is now well settled by a plethora of decisions and in the case of U. P. State Sugar Corpn. v. Sumac International Ltd., the Hon'ble Supreme Court made two exceptions for granting an order of

injunction to restrain the enforcement of a bank guarantee or a letter of credit i.e. (i) fraud committed in the notice of the bank which would vitiate the very foundation of the guarantee; and (ii) injustice of the kind which would make it impossible for the guarantor to reimburse himself. So far as the first exception of fraud is concerned, the Hon'ble Supreme Court in paragraph nos. 11 and 12 of the its decision held as follows :

    URS                                                                                         20 of 25




                                                         21                ARBPL 1538-12-Judgment.doc

"11. Except under these circumstances, the courts should not

readily issue injunction to restrain the realisation of a bank guarantee or a letter of credit. So far as the first exception is

concerned i.e. of fraud, one has to satisfy the court that the fraud in connection with the bank guarantee or letter of credit would vitiate the very foundation of such a bank guarantee or letter of credit. So

far as the second exception is concerned, this Court has held in that decision that it relates to cases where allowing encashment of an

unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. While dealing with the

case of fraud, this Court in U. P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. held as follows : (SCC p. 197,

para 53) The fraud must be of an egregious nature such as to vitiate the entire underlying transaction. (emphasis

supplied)

While coming to a conclusion as to what constitutes fraud, this Court in the above case quoted (at SCC p. 197, para 54) with approval the observations of Sir John Donaldson, M. R. in

Bollivinter Oil SA v. Chase Manhattan Bank, All ER at p. 352g-h which is as follows :

"The wholly exceptional case where an injunction may be

granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear, both as to the fact of fraud and as to the bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated

URS 21 of 25

22 ARBPL 1538-12-Judgment.doc

statement of the customer, for irreparable damage can be done to a

bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank

to have it discharged."

12. In Svenska Handelsbanken v. Indian Charge Chrome it has

also been held that a confirmed bank guarantee/irrevocable letter of credit cannot be interfered with unless there is established fraud

or irretrievable injustice involved in the case. In fact, on the question of fraud, this decision approved the observations made by

this Court in U. P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd."

In paragraph no.14 of the said decision, the Hon'ble Supreme Court has set out certain principles which are required to be noted by the Court in the

matter of granting injunction restraining the encashment of a bank guarantee.

In the said paragraph, the Hon'ble Supreme Court has held that in case an injunction restraining the encashment of a bank guarantee or letter of credit is granted on the ground of fraud, the same has to be of an egregious nature,

which would vitiate the very foundation of the bank guarantee or letter of credit and in cases where the beneficiary seeks to take advantage of the situation.

25. It is therefore trite law that the Court can restrain encashment of bank guarantee in cases of established fraud in issuance of the bank guarantee. The fraud has to be absolutely egregious vitiating the foundation of the bank guarantee. In the present case, the Petitioner has failed to make out any case of fraud. The allegations of fraud made by the Petitioner are merely bald

URS 22 of 25

23 ARBPL 1538-12-Judgment.doc

assertions and do not establish a case of fraud much less fraud of an egregious

nature. As set out herein, the bank guarantee is an unconditional and irrevocable guarantee. As held by the Hon'ble Supreme Court, encashment of

an unconditional and irrevocable bank guarantee ought not to be injuncted by Courts unless the case falls within recognized exceptions laid down by the Hon'ble Supreme Court. Again, an unconditional and irrevocable Bank

Guarantee is an independent contract and whether encashment of the same ought to be permitted or not has to be considered without any reference to the underlying or main contract or to the disputes/claims thereunder. The

allegations therefore made by the Petitioner that the invocation of the Bank

Guarantee is vitiated by fraud, cannot be accepted and the said contention is rejected.

26. The Petitioner has also submitted that irretrievable injustice shall be caused to it in case the Bank Guarantee is encashed. In the case of U. P. State

Sugar Corpn. v. Sumac International Ltd. (supra), irretrievable injustice is the

second exception made by the Hon'ble Supreme Court for grant of an injunction restraining encashment of a Bank Guarantee which is referred to in clause 13 of the decision in Himadri Chemicals Industries Ltd. Versus Coal Tar

Refining Co. (supra) and reads thus:

"13. So far as the second exception is concerned, this Court in U. P. State Sugar Corpn. v. Sumac International Ltd. as considered

herein earlier, as SCC para 14 on pp.575-76 observed as follows :

"14. On the question of irretrievable injury which is the second exception to the rule against granting of injunctions when unconditional bank guarantees are sought to be realised the Court said in the above case that the irretrievable injury must be of the kind which was the subject-

    URS                                                                                          23 of 25




                                                      24                ARBPL 1538-12-Judgment.doc

matter of the decision in Itek Corpn. case. In that case an

exporter in USA entered into an agreement with the Imperial Government of Iran and sought an order terminating its

liability on stand by letter of credit issued by an American bank in favour of an Iranian bank as part of the contract. The relief was sought on account of the situation created after

the Iranian revolution when the American Government cancelled the export licenses in relation to Iran and the

Iranian Government had forcibly taken 52 American citizens as hostages. The US Government had blocked all Iranian

assets under the jurisdiction of United States and had cancelled the export contract. The Court upheld the

contention of the exporter that any claim for damages against the purchase if decreed by the American courts would not be executable in Iran under thee circumstances and realisation of

the bank guarantee/letters of credit would cause irreparable

harm to the plaintiff. This contention was upheld. To avail of this exception, therefore, exceptional circumstances which make it impossible for the guarantor to reimburse himself if

he ultimately succeeds, will have to be decisively established. Clearly, a mere apprehension that the other party w ill not be able to pay, is not enough. In Itek case there was a certainty

on this issue. Secondly, there was good reason, in that case for the Court to be prima facie satisfied that the guarantors i.e. the bank and its customer would be found entitled to receive the amount paid under the guarantee."

In the present case, if the Petitioner succeeds in the arbitration proceedings and/or in any other proceedings, it can always seek refund/reimbursement of

URS 24 of 25

25 ARBPL 1538-12-Judgment.doc

the said amount of Rs.25 crores from the Respondent No.1 and it is not the

case of the Petitioner that it will not be possible for the Petitioner to recover the said amount of Rs.25 crores from the Respondent No.1. As correctly

submitted on behalf of the Respondent No.1, the Petitioner has done nothing more than to merely plead fraud of irretrievable injustice and special equities without establishing cogent grounds in respect of the same. In view thereof,

no case is made out by the Petitioner as to how irretrievable injustice will be caused to the Petitioner in case the Bank Guarantee is encashed. Also no special equities have been made out by the Petitioner for grant of injunction

against encashment of the Bank Guarantee. In the case of Dwarikesh Sugar

Industries Ltd. Versus Prem Heavy Engineering Works (P) Ltd. And Another (supra), the Hon'ble Supreme Court held in paragraph 22 as under :

"22. The second exception to the rule of granting injunction, i.e., the resulting of irretrievable injury, has to be such a circumstance which would make it impossible for the guarantor to reimburse

himself, if he ultimately succeeds. This will have to be decisively

established and it must be proved to the satisfaction of the court that there would be no possibility whatsoever of the recovery of the amount from the beneficiary, by way of restitution."

No such circumstance exists in the present case.

27. In the light of the above circumstances, in my opinion, the Petitioner

has not made out any case to restrain the Respondent No.1 from invoking the said Bank Guarantee. The Arbitration Petition is therefore dismissed with costs.


                                                                (S. J. KATHAWALLA, J.) 



    URS                                                                                      25 of 25




 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter