Citation : 2012 Latest Caselaw 487 Bom
Judgement Date : 14 December, 2012
ssm 1 arbp59.12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO. 59 OF 2012
Bharat Lakhotya,
an adult, of Calcutta
Indian Inhabitant,
sole Proprietor of
M/s. Salasar Hanumanji Industries,
by the hands of his Constituted
Attorney, Mohini Mahendra Kabra
having addres at 23-A, Netaji
Subhas Road, 8th Floor, Suite No.32,
Kolkata (West Bengal)
Pin Code-700 001. .....Petitioner.
V/s.
Bharat Sanchar Nigam Ltd.,
a Public Limited Company duly
registered under
the Companies Act, 1956 through
its Principal General Manager (Development),
Maharashtra Telecom Circle,
having its office at New Admn. Bldg.,
Behind CTO Compound Juhu Road,
Santacruz-(W), Mumbai-400 054. ....Respondent.
Mr. A.L.N. Khatri for the Petitioner.
Ms. Martina Sapkal i/by M/s. Arun Sapkal & Co. for the
Respondent.
CORAM : ANOOP V. MOHTA, J.
JUDGMENT RESERVED ON : 5 DECEMBER 2012.
JUDGMENT PRONOUNCED ON : 14 DECEMBER 2012.
ssm 2 arbp59.12
JUDGMENT :-
The Petitioner, under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short, the Arbitration Act), has
challenged award dated 22 July 2010, thereby dismissed the
claim of the Petitioner.
The operative part of the award is as under:-
Award:-
I, Shri G.K. Lodha, DGM (NWP-IT), BSNL, Pune as Sole Arbitrator appointed in the dispute between M/s Salasar Hanumanji Industries, Kolkata and BSNL, Mumbai in
exercise of powers vested under Section 31 of Arbitration and Conciliation Act, 1996, pass the order today i.e. on
22.7.2010 at Pune that the LD charges which are claimed by BSNL, Mumbai, are correct and no refund should be made to the claimant, M/s Salasar Hanumanji
Industries, Kolkata. The claim of Sales Tax by the claimant M/s Salasar Hanumanji Industries, Kolkata is quashed."
3 The basic events as per the Petitioner are as under:-
In the year 2000, the Petitioner responded to the
Respondent's tender for supply of Galvanized Tapered Steel
Tubes (for short, "the goods"). The tender of the Petitioner for
ssm 3 arbp59.12
supply of goods was accepted by the Respondent for the total
consideration of Rs.56,30,100/-. The supply contract was
governed by purchase order which stated various terms of the
contract. General Instructions to the purchase order contained
various stipulations for supply of goods. The goods were to be
delivered by 15 December 2000. There was complete labour
strike in the Petitioner's factory premises which went on from
20 September 2000 till 15 November 2000. On 25 September
2000, the Petitioner by letter "Under Certificate of Posting"
informed the concerned officer of the Respondent about the
said strike.
4 On 11 January 2001, the Assistant Labour Commissioner,
Government of West Bengal issued certificate, certifying that the
Petitioner's factory was visited and was non functional due to
stoppage of work reverted by workers. On 19 February 2001,
the Petitioner requested for extension of time for supply of
goods and the Respondent extended time with payment of
liquidated damages clause without taking into consideration
strike at Petitioner's factory. In the month of March/April, 2001,
ssm 4 arbp59.12
the Petitioner supplied goods to the Respondent. The total
value of goods were Rs.56,30,100/- after adding the Sales Tax
of Rs.2,01,946/- totaling to Rs.58,32,046/-. The Respondent
made payment of Rs.49,00,276/- leaving balance of
Rs.9,32,770/- which was deducted as liquidated damages.
5 In the year 2002, the Petitioner made request for waiving
the liquidated damages and sent various letters for release of
the balance amount.
6 In the year 2005-2006, the Petitioner moved Delhi High
Court and Hon'ble Supreme Court by filing various legal
proceedings claiming balance amount. However, the said
proceedings came to be rejected on technical grounds, for want
of jurisdiction etc..
7 On 9 August 2008, the learned Arbitrator was appointed
by the Chief General Manager of the Respondent, after lengthy
correspondences. In the year 2009 the Arbitration proceedings
were conducted.
ssm 5 arbp59.12
8 On 22 July 2010 the Arbitrator passed an award and
rejected the Petitioner's claim. Therefore, the present Petition.
9 There was delay in delivery as per the purchase order as
the Petitioner unable to complete the delivery by 15 December
2000. Supply was commenced from 4 April 2001 and
completed by 22 May 2001. The Petitioner requested for
extension of time to supply the material on 17 November 2000
on the ground of labour problem. The extension was
accordingly granted upto 15 January 2001 with LD (Liquidated
Damages) charges. The extension was again sought and it was
granted on 19 January 2001 upto 25 February 2001 again with
LD charges. Third time extension was asked and it was granted
upto 31 March 2001 with LD charges. Further extension was
also sought and it was granted upto 15 May 2001 with LD
charges. As per the terms, payment of Rs.49,00,276/- was
made from time to time subject to receipt of the goods. The
request was made by the Petitioner to waive the LD charges and
also payment of Sales-Tax at the rate of 4%. The Petitioner
ssm 6 arbp59.12
therefore claimed that balance amount due and payable was
Rs.9,31,770/- and 18% interest on the said amount from 1 June
2001 to 15 February 2009 was Rs.12,93,045/- and thereby
claimed total amount of Rs. 22,21,814/-, by raising the dispute
in question, which the learned Arbitrator, in the present facts
and circumstances and considering the LD charges clause,
maintained the action of Respondent in view of undistputed
position on record read with the permissible clause as agreed by
and between the parties. The learned Arbitrator has considered
the fact that the delayed portion of the supply materially
hampered the installation and commissioning of other systems
and thereby the charge so levied on the total value of the
purchase order, in no way can be stated to be contrary to law
and/or the record.
10 Another aspect is that the Petitioner filed the Writ Petition
in Delhi High Court and thereby challenged the amount of
liquidated damages. The Single Judge of Delhi High Court
rejected the Writ Petition. The Division Bench by order dated
10 July 2007 also rejected the Appeal against the same. The
ssm 7 arbp59.12
Supreme Court on 28 January 2008 dismissed the SLP also.
Thereby, in view of Clause 24 of the agreement, the issue of
jurisdiction was upheld by further observing that Delhi High
Court has no jurisdiction to decide and dealt with the matter,
apart from the Arbitration clause. As noted, cause of action in
the matter arise some time in the year 2000-2001. Inspite of
Arbitration clause, the Writ Petition was filed and ultimately the
same was rejected and confirmed by the Supreme Court on 28
January 2008. Thereafter, the Arbitration proceedings were
initiated and the matter proceeded to the Arbitrator for
adjudicating the same. Though there is no specific reason
and/or objection raised with regard to the limitation, but
undisputed position on record itself shows that the Petitioner
having knowledge of Arbitration clause, still had invoked writ
jurisdiction and thereby challenged the deduction of amount
towards the LD charges. The contention was raised that in view
of Section 14 of the Limitation Act as the Writ Petition was
disposed of in the year 2008 and thereafter Arbitration
proceedings were initiated and conducted accordingly, the
Arbitrator therefore, did not decide and as other side also did
ssm 8 arbp59.12
not raise any objection and therefore, on that ground, there is
no reason to discuss further the issue of limitation. The aspect
of delay and limitation just cannot be overlooked. Section 3 of
the Limitation Act is mandatory. In the present case, the facts
are not in dispute about the late invocation of the arbitration
proceedings.
What remains is the issue of "Force Majeure" as provided
in clause 21 of the Agreement. In view of this clause, it is
necessary for the Petitioner to give intimation/notice of
happening of the events, in the present case the strike/labour
problem. There is no material on record to show that such
intimation was sent and served within 21 days from the date of
occurrence. Though averments are made, the learned
Arbitrator has observed that the strike was from 20 September
2000 to 15 November 2000, but as there was no
communication received the LD charges so deducted and/or
action so taken also cannot be interfered. The learned
Arbitrator therefore, right in coming to the following
conclusion:-
ssm 9 arbp59.12
"After considering the facts and materials put
forth for conciliation by both BSNL, Mumbai as well as
by the claimant, M/s Salasar Hanumanji Industries,
Kolkata, and applying the principle of natural justice, it
is concluded that the LD charges which were claimed by
BSNL, Mumbai, is correct. The rate of material in P.O.
Was composite and inclusive of all the taxes, so claim of
Sales Tax by claimant M/s Salasar Hanumanji
Industries, Kolkata does not arise."
12 Therefore, taking overall view of the matter, I see there is
no case made out by the Petitioner to interfere with the
reasoned award so passed.
13 Resultantly, the Petition is dismissed.
14 There shall be no order as to costs.
(ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!