Citation : 2010 Latest Caselaw 313 Bom
Judgement Date : 21 December, 2010
VBC 1 wp2456.10-21.12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
O. O. C. J.
WRIT PETITION NO.2456 OF 2010
Prognosys Medical Systems Ltd. ...Petitioner.
Vs.
Mumbai Municipal Corporation & Ors. ...Respondents.
....
Ms.Rajni Iyer, Sr.Advocate with Ms.PoojaPatil and Mr. H.K.
Bhalerao i/b. M/s.Rajesh Kothari & Co. for the Petitioner.
Mr.A.Y.Sakhare, Sr. Advocate with Ms.V.S. Gharpure for
Respondent Nos.1 and 2.
Mr.Rafeeq Peermohiddin i/b. Dholakia Law Associates for
Respondent No.3.
.....
CORAM : DR.D.Y.CHANDRACHUD AND
ANOOP V. MOHTA, JJ.
December 21, 2010.
ORAL JUDGMENT (PER DR.D.Y.CHANDRACHUD, J.) :
The Municipal Corporation invited tenders on 25
January 2010 for the supply and installation of four Flat Panel
Digital Radiography Systems at KEM Hospital. On 10 March
2010, the technical bids were opened. The Municipal Corporation
received six bids of which four were considered as being
responsive. After scrutiny of the contents of the technical bids, the
report of the scrutiny was placed before the Technical Scrutiny
Committee on 23 August 2010. Dr.Hemant Deshmukh, Professor
VBC 2 wp2456.10-21.12
in the Department of Radiology observed a demonstration
together with the Executive Engineer in the Medico Electronic Cell
in June and July 2010. A report was prepared by these two
officials and by the concerned Heads of Department at KEM, Nair
and Sion Hospitals. During the course of the scrutiny, a letter was
received from the Third Respondent on 7 May 2010 offering a
demonstration of the system installed by it in South Korea and
Turkey. This request was approved by the Competent Authority. A
team of officials visited South Korea to observe the demonstration.
Commercial bids were opened on 4 September 2010. The bid of the
Third Respondent was found to be the lowest. The report was
thereafter placed before the Common Purchase Committee,
Technical Screening Committee and Common Tender Committee
on 13 September 2010. These Committees recommended the
award of the contract to the Third Respondent. The
recommendation was approved by the Standing Committee of the
Municipal Corporation on 7 October 2010. A letter of acceptance
was issued to the Third Respondent on 11 October 2010. The
contract was executed on 19 October 2010. On 2 November 2010,
the Municipal Corporation opened an irrevocable letter of credit for
VBC 3 wp2456.10-21.12
80% of the contract amount, in the total value of US$ 784,000
equivalent to Rs.3.55 crores. The Petition before this Court was
instituted on 16 November 2010.
2. The challenge in this Petition to the award of the contract
to the Third Respondent, is on the ground that the Third
Respondent failed to meet the conditions of eligibility. Counsel
appearing on behalf of the Petitioner submitted that: (i) There was
no basis or justification for the Municipal Corporation to permit a
demonstration by the Third Respondent in South Korea since the
tender specifications provided that if needed, the tenderer would at
his cost arrange for demonstration of the equipment quoted for in
the tender in India; (ii) An essential requirement of the tender was
that the bidder must achieve a DQE (Detective Quantum
Efficiency) of at least 65% at zero line pair per millimeter.
According to the Petitioner, the Third Respondent quoted a DQE of
69% at 0.1 line pair per millimeter which did not meet the tender
specifications; and (iii) Contrary to the tender condition, the Third
Respondent had not submitted a data sheet from the manufacturer
of the equipment.
VBC 4 wp2456.10-21.12
3. Affidavits were filed originally, in these proceedings, on
behalf of the Municipal Corporation by Dr.Hemant Deshmukh,
Professor, Department of Radiology and on behalf of the Third
Respondent. In the affidavit filed on behalf of the Municipal
Corporation, the allegation as regards the failure of the Third
Respondent to fulfill the DQE parameters was denied in the
following terms:
"I say that Respondent no.3 are supplying Samsung detectors having maximum availability of maximum '69% DQE' and hence, the same meet with the
specification of minimum requirement of 65% DQE."
The affidavit of the Third Respondent was silent on whether the
requirement was duly fulfilled. By an order of this Court dated 9
December 2010, an opportunity was granted to the Municipal
Corporation and to the Third Respondent to file further affidavits
clarifying as to whether the Third Respondent fulfilled the tender
conditions.
4. In his affidavit which has been filed on 13 December
2010, in pursuance of the directions of this Court, Dr.Deshmukh
VBC 5 wp2456.10-21.12
has explained the relevance of the DQE specification as follows in
paragraph 2:
"I say that as per the tender specifications for D.R. Systems, DQE >=65% at 0 lp/mm was one of the tender specifications asked for. DQE means Detective Quantum Efficiency and ">=" sign stands for more than or equal
to. "0 lp/mm" stands for zero line pair per millimeter. This denotes spatial frequency. DQE is neither a physical component nor an accessory of the D.R. system. It is a figure expressed in percentage which is arrived after
complex mathematical calculations. Detective Quantum Efficiency is not an explicitly inscribed number on the
Equipment or the Detector, but has been the most commonly used metric of the 'overall' image quality of D. R systems. It describes how efficiently a D R system
translates incident X-ray photons into useful signal within an X-ray image. DQE is regarded as a convenient, reasonably accurate and widely accepted metric of image quality. Our specifications asking for DQE at 0 lp/mm
allows for the best chance for evaluation of DQE expressed by the Petitioner and other tenderers without
quoting non zero frequencies, while the Respondent No.3 specifically has given DQE of 69% at 0.1lp/mm."
Dr.Deshmukh has stated that the Third Respondent had given a
technical specification of DQE as more than 69% at 0.1 line pair
per millimeter. The tender specification was at zero line pair per
millimeter while Samsung, whose equipment was supplied by the
Third Respondent, had quoted for 0.1 line pair per millimeter.
The affidavit clarifies that the DQE of 69% of the Third Respondent
VBC 6 wp2456.10-21.12
technically will be more than what is asked for by the technical
specification. A graph is annexed to the affidavit.
5. In the affidavit which has been filed by the Third
Respondent, it has been stated that in the data sheet submitted by
the Third Respondent to the Municipal Corporation, there is a
column showing X-ray performance rate. A decrease in the line
pair per millimeter increases the DQE. According to the Third
Respondent, the requirement of DQE of at least 65% was achieved
by the Third Respondent at 0.1 line pair per millimeter. According
to the Third Respondent, the measurement of DQE at zero line pair
per millimeter is only an extrapolation to estimate the value
outside the known range.
6. On behalf of the Petitioner it has been submitted that
neither in the affidavits as originally filed, nor in the further
affidavits that have been filed, have the Respondents established
the fulfillment of the tender condition by the Third Respondent.
7. At the outset, while evaluating the submission, the Court
VBC 7 wp2456.10-21.12
must be mindful of the fact that in an area involving technical
expertise, the Court must be conscious of the limitations on its own
jurisdiction to enquire into disputed factual issues particularly
involving a scientific bearing. The Court in such cases is essentially
concerned with the decision making process. There are well settled
parameters for the exercise of judicial review. The award of a
contract can be set aside on grounds of illegality, irrationality or
procedural impropriety. There is an element of judicial restraint in
judicial review of administrative action and the Court rarely if ever
sits as a court of appeal. Unless there is a patent illegality in the
assessment of a tender evaluation committee of the technical
qualifications of a selected bidder, the Court would not ordinarily
interfere under Article 226 of the Constitution. These principles
emerge from several judgments of the Supreme Court, among
them being the judgment in Siemons Public Communication Pvt.
Ltd. vs. Union of India.1 The Supreme Court there reviewed the
body of law on the subject, including the earlier decision of the
Court.
1 A.I.R.2009 SC 1204
VBC 8 wp2456.10-21.12
8. Now, the data sheet which was submitted by the Third
Respondent reflected a DQE of 69% at 0.1 line pair per millimeter.
At 0.1 line pair per millimeter, the required parameter of a DQE of
at least 65% is achieved and in fact exceeded. The fact that the
Third Respondent achieved the parameter at o.1 line pair per
millimeter does not lead to the acceptance of the contention of the
Petitioner that the DQE of the product which is to be supplied by
the Third Respondent would fail to meet the tender specification of
a minimum of 65% DQE at zero line pair per millimeter. The data
sheet which has been placed on the record by the Third
Respondent in Exhibit 'B' to the affidavit filed before this Court on
14 December 2010, in fact, shows that as the DQE reduces from
3.5 line pair per millimeter to 0.1 line pair per millimeter, the
measured DQE value increases from 20.7 to 69.0. On this basis,
particularly when in the affidavit which has been filed on behalf of
the Municipal Corporation by Dr.Deshmukh, it has been stated that
the DQE of 69% of the Third Respondent will be more than what
is asked for in the technical specification, there is no reason for the
Court to sit in judgment in the manner of an appeal. That would
not be the proper scope of the exercise of the writ jurisdiction. The
VBC 9 wp2456.10-21.12
Third Respondent, as the record before the Court indicates,
submited a data sheet and the only question was as to whether that
the data sheet which had been submitted fulfills the technical
specifications of the First Respondent. We do not find any
perversity in the administrative decision that was taken in this
regard.
9. The tender specification contained a requirement that
when needed the tenderer at his cost should arrange for the
demonstration for the equipment quoted for in India within fifteen
days from the intimation of a request for demonstration. The
Third Respondent has, in the affidavit dated 1 December 2010 filed
in these proceedings, explained the reason why, it had suggested to
the Municipal Corporation to permit a demonstration to be held in
South Korea of a D.R. system installed by the Third Respondent.
The relevant part of the affidavit reads as follows :
"The 1st Respondent has sought for certain specific
additional features like Auto positioning, auto collimation etc. It is significant to mention that these additional features are optional in nature and the existing customers of this respondent did not opt for them in the DR Systems supplied to them in India.
Hence, what differs is only some additional features (which the first respondent opted), while in respect of technology, the DR systems (offered by this respondent)
VBC 10 wp2456.10-21.12
are exactly similar to the one which are already supplied/installed by this respondent to their existing
customers in India. Hence, though the DR systems with similar technologies supplied/installed by this
respondent are available in India for inspection, this respondent requested the first respondent for inspection of the DR systems (with additional features sought for by the first respondent) abroad. It was only in these
circumstances, the necessity for inspection abroad arose and the first respondent thought it fit and agreed to inspect the machine abroad as well, wherein a customer had installed the machine with all these features."
10.
One of the tender specifications was that only those
tenderers who have installed and successfully commissioned at
least two Digital Radiography Systems in India in the previous
three years would be eligible to apply. The Third Respondent did,
as a matter of fact, fulfill this requirement. In its affidavit, the
Third Respondent has stated that at the time of the submission of
the tender, it had more than twelve installations in large hospitals
and medical colleges such as Apollo Hospitals at Chennai, Delhi,
Bangalore and Kolkata, at five medical college hospitals run by
Uttaranchal Government and at three Mumbai Municipal
Corporation hospitals. Counsel appearing on behalf of the
Municipal Corporation has also, in order to establish the bona fides
VBC 11 wp2456.10-21.12
of the administrative decision, adverted to a certificate dated 10
March 2010 issued by Apollo Hospital and another certificate
issued by Godavari Imaging Science and Research Centre Pvt.Ltd.
to the Third Respondent. The Third Respondent had also supplied
a list of all the installations where it had provided Digital
Radiography Systems.
11.
The bid of the Third Respondent was accepted since it
was lower than the bid of the Petitioner. As we have already
noted earlier, following the acceptance of the bid, a contract was
signed on 19 October 2010. The Municipal Corporation has
opened an irrevocable letter of credit of 2 November 2010 for an
amount of about Rs.3.55 crores. The Petition has been filed only
on 16 November 2010 after this process was completed. Hence,
the Court must in addition, weigh in balance the circumstance that
intervention at this stage, is liable to result in the invocation of the
letter of credit by the supplier. The Petitioner was not unaware of
the fact that the bid of the Third Respondent was found to be
technically responsive for, it was on that basis that the commercial
bids of all the responsive bidders were opened on 4 September
VBC 12 wp2456.10-21.12
2010.
12. For all these reasons, we are of the view that it would
neither be appropriate nor proper for this Court to interfere in the
exercise of the writ jurisdiction under Article 226 of the
Constitution, particularly having regard to the well settled
parameters governing the exercise of this jurisdiction in a matter
relating to the award of public contracts. Even if the Court were to
come to the conclusion that the administrative decision is a
possible decision to be arrived at on the basis of the material on
record, the Court would not be inclined to interfere. In the
absence of any perversity, illegality or procedural impropriety, it
would not be proper for this Court to intervene in a petition raising
the grievances which we have dealt with earlier.
13. The Petition is accordingly dismissed. No costs.
( Dr.D.Y.Chandrachud, J.)
( Anoop V. Mohta, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!