Citation : 2010 Latest Caselaw 283 Bom
Judgement Date : 13 December, 2010
VBC 1 wp8548.10-13,12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
APPELLATE SIDE
WRIT PETITION NO.8548 OF 2010
MIAECT Pvt. Ltd. ...Petitioner.
Vs.
Hindustan Computers & Ors. ...Respondents.
....
Mr.Shriram S.Kulkarni for the Petitioner.
Mr.Ashutosh Kumbhakoni with Mr.Tejas D.Deshmukkh for
Respondent No.1.
Mr.Vijay D.Patil, AGP for Respondent Nos.2 to 6.
.....
CORAM : DR.D.Y.CHANDRACHUD AND
ANOOP V. MOHTA, JJ.
December 13, 2010.
ORAL JUDGMENT (PER DR.D.Y.CHANDRACHUD, J.) :
Rule; by consent returnable forthwith. With the
consent of Counsel and at their request the Petition is taken up for
hearing and final disposal.
2. In these proceedings under Article 226 of the
Constitution, the Petitioner challenges a Government Resolution of
18 August 2010 and an order of 31 August 2010 by which a
VBC 2 wp8548.10-13,12
contract of a total value of Rs.31.86 crores for the supply of
computer hardware and for imparting training to students in 271
Government Hostels across the State has been awarded without
inviting tenders.
3. In the State of Maharashtra, 271 hostels are conducted
for students belonging to the backward classes by the State
Government. The hostels are administered by the Director of
Social Welfare. On 4 July 2003, the Social Welfare Department
issued a Government Resolution in order to make provision for
amenities to students of those hostels. Included in those amenities,
was a provision for four computer sets for each hostel. According
to the Government, though computers were made available to the
hostels, they remained unused or were underutilised in the absence
of adequate training to students. The First Respondent unilaterally
submitted a proposal on 30 March 2010 for imparting computer
training to hostel students. On 26 April 2010, the Desk Officer
forwarded the proposal to the Director of Social Welfare, informing
him that the Government has received a proposal for creating a
Computer Section on a build, operate and transfer (BOT) basis for
VBC 3 wp8548.10-13,12
Government Hostels and for imparting computer training. The
Director of Social Welfare scrutinized the proposal and submitted
his report. The Director of Social Welfare while evaluating the
proposal was categorically of the view that the State Government
should issue a public advertisement and invite offers from
interested bidders. By a letter dated 21 June 2010, the Desk Officer
informed the Director of Social Welfare to submit any other
proposals that he may receive, to the Department. According to
the Government, three other institutions submitted their proposals
to the Director which were forwarded by him to the Principal
Secretary in the Social Welfare Department on 28 June 2010. The
proposals were evaluated. On 17 August 2010, a decision was
taken at a meeting convened by the Minister, (Social Justice and
Special Assistance Department) at which it was decided that from
the proposals which had been received from the Director of Social
Welfare, a contract should be awarded to the bidder who had
offered the lowest rate. Accordingly, on 18 August 2010, a GR was
issued by which a contract for the supply of computers on a BOT
basis for providing computer training for 2010-11, 2011-12 and
2012-13 was awarded to the First Respondent. The total outlay for
VBC 4 wp8548.10-13,12
2010-11 is Rs.14.23 crores, whereas the outlay for the subsequent
two years is Rs.8.81 crores per annum.
4. The award of the contract has been challenged by the
Petitioner who claims that on 23 July 2010, it had submitted a
proposal to the Third Respondent. According to the Petitioner, the
contract was awarded without considering the proposal of the
Petitioner. Broadly speaking, the challenge which has been
preferred before the Court by the Petitioner, is based on the
following submissions:
Firstly, it is urged that no tenders were invited for the
award of the contract. This itself, it is urged, is arbitrary and
violative of Article 14;
Secondly, it has been submitted that there was no
compelling necessity to deviate from the normal rule of the award
of public contracts by inviting tenders. In this case, despite a
specific recommendation that tenders should be invited, the State
Government chose to award the contract without publishing a
notice and without inviting tenders;
Thirdly, it has been submitted that the entire process
VBC 5 wp8548.10-13,12
adopted by the State Government is arbitrary. The Government, it
is urged, had not laid down any specifications of what courses
should be prescribed for imparting computer training to backward
class students staying in hostels. No criteria were laid down in
respect of (i) credentials, (ii) financial capacity; (iii) man power;
(iv) expert teachers; (v) past experience; and (vi) specifications;
infrastructure or the quality of training. As a result, the award of
the contract is based on an offer submitted by the First Respondent
and three other offers alleged to have been received by the State
Government; and
Fourthly, the Petitioner submits that in any event, the
offer which has been made by the Petitioner and which was on the
file of the Government, has not been considered before the award
of the contract.
5. The State Government has filed an affidavit in reply in
these proceedings. The reply, besides adverting to the facts which
have been narrated earlier, states that apart from the proposal of
the First Respondent, Government received four other proposals
which were scrutinized. A submission was prepared together with
VBC 6 wp8548.10-13,12
a comparative statement of all the proposals and it was placed
before the Minister. In pursuance of the directions of the Minister,
a meeting was held on 17 August 2010 when a decision was taken
to approve the proposal at the lowest rate. The Government has
submitted that while the Petitioner has contended that he had
submitted a proposal on 23 July 2010, by that time submissions
were already made by the Section Officer on 8 July 2010. The
proposal of the Petitioner was almost identical, with slight changes,
to the proposal of the First Respondent. The State Government has
admitted in its affidavit that in the present case, tenders were not
invited. However, five proposals which were received by the
Government, were scrutinized and the proposal of the First
Respondent was selected since it was the lowest. In the present
case, imparting of training to students of Government hostels was
taken up on experimental basis and it is only after the receipt of the
proposal that the process of providing such training was started.
The concept of providing training was received from the First
Respondent.
6. The First Respondent, who is the selected bidder, has
VBC 7 wp8548.10-13,12
submitted in his affidavit in reply that it was the First Respondent
who for the first time, came out with an innovative idea of
imparting training to inmates of Government hostels. According to
the First Respondent, monetarily the difference between the
proposal of the Petitioner and the First Respondent is marginal or
almost nil. The First Respondent states that in pursuance of the
work order that was issued on 31 August 2010, steps have been
taken to supply the infrastructure to all the concerned Government
hostels located throughout the State of Maharashtra and the First
Respondent together with its partner, Hinduja International
Pvt.Ltd. has incurred an expenditure of approximately Rs.5.88
crores. The submissions which have been urged for and on behalf
of the First Respondent are two fold. Firstly, it has been submitted
that the First Respondent has taken steps for the purpose of
implementing the contract that was entered into with the State
Government and has incurred substantial investment.
Consequently, it is urged that the interference of this Court under
Article 226 of the Constitution is not warranted at the present
stage. Secondly, it is urged that inviting of tenders is an invariable
but not an inflexible rule and there was valid reason for the
VBC 8 wp8548.10-13,12
Government not to invite tenders. Learned Counsel also submitted
that though the Petitioner claims to have submitted a proposal on
23 July 2010, it is a matter of issue as to whether that proposal was
even placed on the file of the Government prior to September 2010
when the work order was awarded to the First Respondent.
7. While dealing with the merits of the rival contentions,
the first aspect which needs to be emphasized is that Article 14 of
the Constitution mandates that the State when it awards public
contracts must conduct itself fairly and transparently. The award
of Government contracts involves disbursement of substantial
benefit. Article 14 of the Constitution militates against any notion
of an unrestricted largesse which the State can award at its whims
and fancies. The State Government when it decides to award
contracts must ordinarily prescribe the specifications which an
intending bidder must fulfill. These specifications include the
laying down of credentials, experience, financial capacity and other
like facets. The consequence of these norms is that a bidder, who
enters into a contract with the Government, must have a
demonstrable capacity to fulfill the requirements of the contract in
VBC 9 wp8548.10-13,12
terms of technical qualifications and financial commitment.
Technical qualifications are decided on the basis of the availability
of infrastructure, qualified personnel and experience in handling
similar contracts of at least a particular value in the past. Financial
parameters ensure that the Government, when it awards a
contract, deals with a bidder who would have the wherewithal to
fulfill the requirements of Government. The award of public
contracts is part of the process of governance by which the
Government provides facilities and amenities to society at large
and in certain cases, such as the present, to a particular segment of
the society. The inviting of tenders is a salutary norm which
ensures transparency in dealings of the Government. The inviting
of tenders is significant not only from the perspective of making
available to Government the best possible rates but also ensures
that the wide publicity that is ensured by advertising a proposal,
results in Government being able to evaluate the merits of a large
body of rival bidders. Secrecy in the award of Government
contracts is liable to result in the worst possible abuses by
excluding a large segment of the community who may have no
knowledge of the fact that Government is likely to disburse benefits
VBC 10 wp8548.10-13,12
in the form of a particular public contract. Consequently, while
Courts have recognized that the award of public contracts by
inviting tenders is the norm, exceptions have been noted in
compelling situations. The exception, however, cannot be allowed
to become the rule. One such exception was carved out by the
Supreme Court in Kasturi Lal Lakshmi Reddy vs. State of
Jammu and Kashmir,1 where the State Government was
proceeding to award a tapping contract to a party who was
prepared to set up a factory for the manufacturing inter alia of
rosin and turpentine oil. The Supreme Court noted that the
purpose of the contract was not tapping simpliciter, but to
encourage the process of industrialization within the State. In
Netai Bag vs. State of W.B.,2 the Supreme Court once again
reiterated that where the State was conferring a largesse recourse
must be had to a public auction or to a public tender. However, an
exception would not in all cases make the exercise of executive
power arbitrary. However, an exception to the general rule has to
be justified by the State if it is challenged in an appropriate
proceedings. The same principle was reiterated in a judgment of a
1 (1980) 4 SCC 1 2 (2000) 8 SCC 262
VBC 11 wp8548.10-13,12
Division Bench of this Court delivered by the Chief Justice, the
Hon'ble Mr. Justice Swatanter Kumar (as His Lordship then was) in
Vijay Kumar Gupta vs. State of Maharashtra.3 The Division
Bench emphasized that it is only in a case of the compelling
necessity that a breach from the norms of inviting tenders can be
justified.
8.
In the present case, the entire process which has been
adopted by the State Government for the award of a large public
contract for the supply of computer infrastructure and for
imparting training in the 271 Government Hostels is fundamentally
defective. Firstly, there is nothing on the record to indicate that
the Government had even applied its mind to what courses should
be imparted for training to the backward class students. No criteria
were laid down by the Government specifying the credentials,
financial capacity, past experience or expertise which bidders
would have to meet. Government seems to have been moved only
on the receipt of proposals from the First Respondent and by a few
other bidders. The Director of Social Welfare had, in his noting on
3 2008 (4) Mh.L.J. 370
VBC 12 wp8548.10-13,12
the file, expressly cautioned the Government of the necessity of
inviting tenders by publishing an advertisement. There is, in our
view, absolutely no reason or justification why, before proceeding
to award a contract of a total value in excess of Rs.31 crores, the
Government considered it appropriate not to invite tenders. The
Court has been moved undoubtedly in the present case, by a
bidder, who complained that his proposal was not considered.
The issue before the Court is not as to whether the Petitioner is
entitled to the award of the contract. Indeed, if as the Court is
inclined to hold, the correct course of action for the Government
was to invite tenders, it may well be that the Petitioner would not
be entitled to relief in terms of the award of the contract in these
proceedings. The fundamental point, however, is that there is
absolutely no justification offered on the part of the State
Government, in the reply, for deviating from the normal rule of
inviting tenders for awarding a contract. A cursory reference has
been made to the fact that the Government had received the
concept of providing training from the First Respondent. The State
Government has stated in its affidavit that it had also received a
proposal from NIIT on 30 June 2010. But in the course of
VBC 13 wp8548.10-13,12
arguments, the learned Government Pleader fairly stated that the
proposal was received from NIIT in October 2009. There is nothing
novel about a proposal to set up computer infrastructure and
impart training to students in the Government Hostels. The
Government has stated that it was intending to impart training to
students of hostels on an experimental basis and it was only after
the receipt of the proposal from the First Respondent that the
process of providing such training was started. Even assuming that
the idea of imparting training to students of the Government Hostels
was mooted by the First Respondent, there was no reason or
justification for the Government not to invite tenders and to allow
all bidders an equal opportunity to submit bids for the award of the
contract. The Government has failed to do so. There is merit in
the submission that the entire decision making process has been
flawed and has been violative of Article 14 of the Constitution.
9. On behalf of the First Respondent, it has been submitted
that the Petition should be dismissed on the ground that there has
been an unexplained delay in moving the Court. The work order to
the First Respondent was awarded on 31 August 2010. A
VBC 14 wp8548.10-13,12
Memorandum of Understanding was entered into between the
State Government and the First Respondent on 24 September
2010. The Petition was lodged before this Court on 21 October
2010. By an interim order dated 25 October 2010, which was
passed by a Division Bench, after hearing Counsel appearing on
behalf of the First Respondent and the Learned Government
Pleader, the Division Bench clarified that any preliminary steps
being taken such as laying down electrical cables may continue, but
installation of computers shall not be allowed till 28 October 2010.
The interim order was thereafter continued. The Petitioner has, in
an affidavit filed in rejoinder in these proceedings, stated that after
the submission of his proposal on 23 July 2010 to the Secretary in
the Social Welfare Department, he has continuously followed up
the matter between July and September 2010. In September 2010,
the Petitioner met the Secretary in the Social Welfare Department.
On the proposal submitted by the Petitioner, the Secretary in the
Social Welfare Department made an endorsement on 9 September
2010 to the effect that the proposal should be put up along with
the main file. On this basis, it is urged on behalf of the Petitioner
that right until then, the Petitioner was led to believe that his
VBC 15 wp8548.10-13,12
proposal was under consideration. The work order that has been
issued to the First Respondent also states in condition 15 that in
the event that any dispute arises in relation to the contract
awarded to the First Respondent, the First Respondent would have
no claim as against the State Government. There is no delay on the
part of the Petitioner. Be that as it may, we are of the view that in
the present case, where the award of the contract has been effected
without complying with basic procedures consistent with the
requirement of Article 14, the intervention of the Court is
warranted. There is, in our view, no delay much less an
unexplained delay, on the part of the Petitioner in moving the
Court. The action of the Government is clearly arbitrary and
discriminatory as held by the Supreme Court in Monarch
Infrastructure (P) Ltd. vs. Commissioner, Ulhasnagar Municipal
Corporation,4 warranting the grant of relief.
10. For the reasons aforesaid, the Petition is allowed in terms
of prayer clause (a) by quashing the Government Resolution dated
18 August 2010 and the consequential work order dated 31 August
4 (2000) 5 SCC 287
VBC 16 wp8548.10-13,12
2010. In the event that the Government proposes to award a
contract for the installation of the computer infrastructure in the
271 Government Hostels and to impart training to students of the
hostels, the Government shall proceed in accordance with law, in
terms of the observations contained in this judgment.
11. While allowing the petition, we are of the view that the
equities that have intervened in the present case, prior to the date
of the interim order of this Court dated 25 October 2010 would
have to be balanced. It has been urged on behalf of the First
Respondent that even prior to the date of the interim order dated
25 October 2010, the First Respondent had supplied computer
infrastructure and paraphernalia to the Government Hostels after
the date of the work order. We are of the view that it would be
appropriate in the facts and circumstances of the case, to direct
that Government shall constitute a Committee consisting of the
Secretaries incharge of the (i) Social Justice and Special Assistance
Department; (ii) Finance Department; (iii) Information Technology
Department; and (iv) Law and Judiciary Department. The
Committee shall take a decision on whether (i) The computers and
VBC 17 wp8548.10-13,12
peripherals, if any, which have been supplied by the First
Respondent prior to the interim order dated 25 October 2010 meet
the requirements of the Government with reference to the
proposed setting up of infrastructure and imparting of training to
students of Government Hostels in the State; (ii) In the event that
the Committee comes to the conclusion that Computers and
peripherals were supplied by the First Respondent prior to the
interim order dated 25 October 2010 and are acceptable and meet
the requirements of the programme, the Committee shall proceed
to make a valuation of the equipment supplied by the First
Respondent at the rate applicable to the rate contracts of the State
Government. In that event, it would be open to the State
Government to offer to disburse to the First Respondent the
amount that is determined by the Committee subject to this being
acceptable to the First Respondent. In the event that the proposal
of the Committee is not acceptable to the First Respondent, it
would be open to the First Respondent to apply to the Committee
for removing the computers and peripherals which have been
supplied. This process shall be completed preferably within a
period of six weeks from today. The Director of Social Welfare
VBC 18 wp8548.10-13,12
shall assist the Committee in the completion of the aforesaid
exercise. The Petition shall stand disposed of with these directions.
There shall be no order as to costs.
( Dr.D.Y.Chandrachud, J.)
( Anoop V. Mohta, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!