Citation : 2010 Latest Caselaw 248 Bom
Judgement Date : 3 December, 2010
vbc 1 arbp65.08-8.12
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
O. O.C. J.
ARBITRATION PETITION NO.65 OF 2008
Municipal Corporation of Greater Mumbai. ...Petitioner.
Versus
Hindustan Construciton Company Ltd. ...Respondent.
.......
Mr.R.D.Dhanuka with Mr.H.C.Pimple and Mr.R.Y.Sirsekar i/b.
S.H.Ujjainwala & Co. for the Petitioner.
Mr.Aspi Chinoy, Sr.Advocate with Mr.Kevic Setalwad i/b. M/s.Harish
Joshi & Co. for the Respondent.
......
CORAM : DR. D.Y. CHANDRACHUD, J.
December 3, 2010.
ORAL JUDGMENT :
The challenge in these proceedings under Section 34 of the
Arbitration and Conciliation Act, 1996, is to an arbitral award of 24
September 2007 of an arbitral Tribunal consisting of three Arbitrators.
2. In April 1995, the Petitioner invited tenders for the
vbc 2 arbp65.08-8.12
construction and completion of civil work of aerated lagoons at
Bhandup and Ghatkopar on Contracts 10AA and 11AA. The contract
was awarded to the Respondent on 5 January 1996 and a formal
agreement was entered into between the parties on 30 April 1996.
After the work was completed, the Respondent issued a taking over
certificate on 14 March 2001 for the civil work of the aerated lagoons
at Bhandup and for the work at Ghatkopar. The certificate recorded
that the Respondent had substantially completed the entirety of the
work in accordance with specifications and drawings and had agreed
to complete the pending items of work within two months; during the
defects liability period. The defects liability period commenced from
4 March 2001 and ended on 3 March 2002. On 14 March 2002, there
was a general inspection of the work executed by the Respondent and
the Respondent was called upon to rectify certain defects in terms of
clause 49.2 of the Conditions of Contract. On 16 April 2002, the
Chief Engineer (MSDP) of the Petitioner addressed a letter to the
Respondent recording that the balance of the work had been carried
out and that the defects had been rectified. Accordingly, defects
vbc 3 arbp65.08-8.12
liability certificates for the work under the contract came to be issued
by the Petitioner to the Respondent under Clause 62.1 of the
Conditions of Contract. These certificates were forwarded by the
Petitioner to the Respondent on 16 April 2002.
3. After the defects liability period had ended, some defects
were noted in June/July 2003 nearly two years after the work was
taken over by the Petitioner. On 15 September 2004, a meeting took
place between the parties. What transpired at the meeting is a matter
of dispute. During the course of the arbitral proceedings, the
Petitioner relied on Minutes of the Meeting. These were disputed by
the Respondent. What was produced before the arbitral Tribunal, was
a photocopy of Minutes which were not signed by the Respondent.
The original document was not produced. The Petitioner retained an
amount of Rs.66,51,987.69 which was otherwise due and payable to
the Respondent on the ground that the work which had been
rendered was defective. The arbitration agreement contained in the
contract was invoked and a three member Arbitral Tribunal presided
vbc 4 arbp65.08-8.12
over by a former Judge of this Court, and consisting of a retired Chief
Engineer of the Mumbai Port Trust and a former Chief Secretary of
the State Government was constituted.
4. The arbitral Tribunal found in its award that the
Respondent had duly carried out work under the contract and that the
Petitioner had issued a taking over certificate on 14 March 2001 both
for the work at Bhandup as well as that at Ghatkopar. The balance of
the work which remained as provided in the list annexed to the taking
over certificate was found to have been executed. The defects liability
period ended on 3 March 2002. Defects liability certificates were
issued by the Petitioner to the Respondent. A joint inspection had
taken place on 14 March 2002. The Petitioner was found to have
satisfactorily attended to the minor defects noticed in the work and it
was only thereafter that the defects liability certificates were issued by
the Petitioner to the Respondent. The Tribunal noted that the defects
liability certificates were unconditional. If the Respondent as a
contractor had failed to carry out remedial work within reasonable
vbc 5 arbp65.08-8.12
time, the Petitioner as an employer would have, in the normal course,
taken on an alternative agency to execute the work for remedying the
alleged defects. The Tribunal noted that no record was produced by
the Petitioner to show that it engaged any agency to remedy any
alleged defect even during the period of liability or even thereafter. In
these circumstances, the Tribunal held that the documents on record
would show that there was no defect in the work executed by the
Contractor. The alleged leakage was noted in June/July 2003 much
after a lapse of two years of the taking over of the work by the
Petitioner. On these grounds, the Tribunal allowed the claim of the
Respondent for the balance due of Rs. 66.51 lakhs. Interest was
allowed on the aforesaid amount and on a payment which had been
delayed at the rate of 10% per annum; compounded monthly in terms
of clause 60.8 of the applicable General Conditions of Contract.
5. The Petitioner had made a counter claim which was
dismissed. The Tribunal noted that the work executed by the
Respondent was not defective and in any event, the Petitioner had not
vbc 6 arbp65.08-8.12
carried out any work of rectification at the risk and cost of the
Respondent in respect of any alleged defective work. The counter
claim was not based on any loss, or damage actually caused to or
suffered by the Petitioner and was in these circumstances rejected.
6. The award of the Tribunal has been assailed on two
grounds at the hearing of the Petition. Counsel appearing on behalf
of the Petitioner submitted that the Tribunal has relied on an
unproved document which was not taken on record by the Tribunal in
the course of the evidence. This document is a report of Dr.Katti. As
a matter of fact, there are two reports of Dr.Katti: an interim report
forwarded along with a letter dated 1 November 2004 and a final
report of 8 November 2004. The second submission is that the
Tribunal has without justification come to the conclusion that the
Minutes of the Meeting held on 15 September 2004 had not been
proved by the Petitioner. These Minutes, according to the Petitioner,
are relevant because the Respondent had agreed at that meeting to
rectify defects that had arisen at its cost. The Tribunal held that the
vbc 7 arbp65.08-8.12
original was not produced and, therefore, was not proved. The
submission is that the Petitioner led oral evidence in support of the
document and answers were elicited from the witness for the
Petitioner in the course of the cross-examination. For these reasons,
it is the submission that the minutes of the meeting held on 15
September 2004 were duly proved. The Tribunal has been
inconsistent, when it relied on one of the reports of Dr.Katti and on
the other hand refused to accept the minutes of the meeting of 15
September 2004. This, it is submitted, is in violation of the principles
of natural justice.
7. On the other hand, it has been urged on behalf of the
Respondent by Learned Senior Counsel that the Tribunal was entirely
justified in holding that the minutes of the meeting dated 15
September 2004 were not proved. The fact that the meeting was held
on 15 September 2004 is not in dispute. Almost contemporaneously
with the holding of the meeting the Respondent had addressed a
letter dated 1 November 2004 to the Petitioner placing on record its
vbc 8 arbp65.08-8.12
version of what transpired at the meeting. The Petitioner did not
produce the original signed minutes and had no explanation to offer
as to why the signed copy of the minutes was not available. In these
circumstances, the document was not proved and the reasoning of
the Tribunal does not suffer from any perversity or illegality. The
second submission which has been urged on behalf of the Respondent
is that the report of Dr.Katti finds mention in the award only with
reference to what transpired at the alleged meeting of 15 September
2004. At a meeting of the arbitral Tribunal on 6 March 2006, a
statement was made on behalf of the Petitioner that the Petitioner
admits documents, copies whereof were filed in the arbitral
proceedings and it was on that basis that the Respondent stated that it
was not leading any oral evidence. In any event, as a matter of fact,
the contents of the report of Dr.Katti are not the basis of the award.
The basis of the award of the Tribunal is that the Petitioner having
issued a taking over certificate and defects liability certificates and all
the work of rectification having been carried out by the Respondent,
the work was satisfactorily performed and no defect had remained.
vbc 9 arbp65.08-8.12
8. In assessing the merits of the rival submissions, it must be
noted at the outset, that the basis of the award of the arbitral Tribunal
is that the Petitioner had duly certified that the work which was
executed by the Respondent was in accordance with the specifications
of the contract. This, according to the Tribunal, was evidenced by the
taking over certificates issued by the Petitioner to the Respondent
both in respect of the work of the aerated lagoons at Bhandup and
Ghatkopar. The work which had remained to be carried out was duly
completed and such defects which were pointed out were found to
have been rectified. Thereupon, the Petitioner had issued defects
liability certificates. This is the foundation and basis of the award of
the arbitral Tribunal. The Petitioner sought to rely on minutes of the
meeting which was held on 15 September 2004 in support of its
submission that at that meeting the Respondent had agreed to rectify
certain defects upon the payment of an amount of Rs.62 lakhs. The
fact that the meeting was held is not in dispute. What transpired at
the meeting is the bone of contention. Now it is an admitted position
vbc 10 arbp65.08-8.12
before the Court that the Petitioner did not produce the original
signed minutes of the meeting. The Petitioner had no justification to
offer, when its witness deposed in evidence as to why a signed copy of
the minutes or for that matter, the original of the minutes was not
produced. Admittedly, what is produced in an evidence was a photo
copy of the alleged minutes which was only signed by the Deputy
Municipal Commissioner. The witness, who deposed on behalf of the
Municipal Corporation admitted, in response to Question 47, that a
copy of the minutes was required to be sent to the Respondent, the
contractor. The witness stated that he was unaware as to whether the
office of the Deputy Municipal Commissioner had issued a copy of the
minutes to the contractor. The witness was asked as to whether he
would produce the original of the minutes of the meeting of 15
September 2004 (R-20) to which he answered by stating that he
would try to trace out the original document and would produce it as
early as possible. Thereafter, neither was the original produced, nor
was any justification for leading secondary evidence given. In these
circumstances, on this state of the record, the Tribunal was entirely
vbc 11 arbp65.08-8.12
justified in coming to the conclusion that the alleged minutes upon
which reliance has been placed by the Petitioner were not duly
proved. Before concluding this aspect of the matter, it must be noted
that there was an exchange of correspondence between the parties
soon after the meeting of 15 September 2004. On 1 November 2004,
the Petitioner had addressed a letter to the Respondent stating that at
that meeting, the Deputy Municipal Commissioner had promised that
the payment would be effected by the Petitioner to the Respondent.
According to the Respondent, though it was not obliged to obtain a
technical report from Dr.Katti, it had agreed to obtain that report
provided the payment of the final bill was released immediately. By
its letter dated 1 November 2004, the Respondent forwarded a copy
of the interim report of Dr.Katti dated 26 October 2004. The
Respondent's version of what transpired is that it had never agreed to
undertake the work of repair. On this state of the record, and
particularly having regard to the contemporaneous material in the
form of correspondence between the parties exchanged soon after the
meeting, it was not possible for the Tribunal to come to the
vbc 12 arbp65.08-8.12
conclusion that the minutes on which reliance was placed by the
Petitioner constitute an authentic record of what transpired at the
meeting. For these reasons, the award of the Tribunal on this ground
cannot be held to be arbitrary, perverse or being illegal.
9. Now it is no doubt well settled that an arbitral Tribunal is
not bound by the strict rules of evidence which govern civil trial. But,
equally ever since the judgment of the Supreme Court in Bareilly
Electricity Supply Co.Ltd. Vs. The Workmen,1 it is well settled that
the principles of natural justice must be observed even if an
adjudicating body is not governed by the strict rules of evidence or
procedure. The Supreme Court observed that the application of the
principles of natural justice does not imply that what is not evidence
can be acted upon. The judgment of the Supreme Court would also
buttress the contention of the Respondent that the minutes of the
meeting of 15 September 2004 could not have been relied upon when
neither the original was produced nor was any justification put fourth
for the absence of the signed copy of the original.
1 AIR 1972 SC 330
vbc 13 arbp65.08-8.12
10. Now, in so far as the report of Dr.Katti is concerned,
Counsel appearing on behalf of the Respondent drew the attention of
the Court to the minutes of the meeting before the arbitral Tribunal
on 6 March 2006. During the course of the hearing before the
Tribunal, the representative of the Petitioner stated that the Petitioner
was admitting documents, copies of which were filed in the arbitral
proceedings. The minutes of the meeting also record that the
Respondent was not leading any oral evidence. The submission which
has been urged on behalf of the Petitioner is that when the
representative of the Petitioner stated that he was admitting the
documents, it only meant that the existence of the documents was
being admitted and not the contents for, if the contents were to be
admitted, there would be nothing that would remain to be tried in
the arbitral proceedings. Be that as it may, and even assuming that
the submission which has been urged on behalf of the Petitioner is
correct, on a reading of the award of the arbitral Tribunal it is clear
that the report of Dr.Katti is not the basis or the foundation of the
award. The report of Dr.Katti is initially referred to in the arbitral
vbc 14 arbp65.08-8.12
award while adverting to the case of the claimant. The reference to
the report in the course of the arbitral award is only to be found in the
context of the meeting which took place on 15 September 2004. It is
in the context of that meeting, that the arbitral Tribunal noted that
though there was no contractual obligation on the part of the
Respondent, the Respondent agreed to have a report of Dr.Katti in the
matter without any commitment on its part to bear the costs thereof.
The Tribunal has thereafter observed that even the minutes which
were relied upon by the Petitioner do not record that the Respondent
had agreed to carry out the work of repair as sought to be suggested
by the Petitioner and that no agreement to carry out repairs to the
alleged defective or damaged work on the part of the Respondent was
arrived at during the meeting of 15 September 2004. In these
circumstances, I am of the view that the question as to whether
Dr.Katti's report could have been relied upon as substantive evidence
is of no significance because the arbitral award as a matter of fact is
not based on the report of Dr.Katti.
vbc 15 arbp65.08-8.12
11. Besides this, it has been submitted on behalf of the
Respondent by the Learned Counsel that at no stage during the course
of the arbitral proceedings had the Petitioner ever contended that the
report of Dr.Katti was not proved or could not be referred to.
12. For all these reasons, I am of the view that the arbitral
award does not suffer from any illegality or perversity.
13. The Petition is accordingly dismissed. No costs.
( Dr.D.Y.Chandrachud )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!