Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M.S.E.B., Bhusawal vs The Union Of India
2009 Latest Caselaw 41 Bom

Citation : 2009 Latest Caselaw 41 Bom
Judgement Date : 8 December, 2009

Bombay High Court
M.S.E.B., Bhusawal vs The Union Of India on 8 December, 2009
Bench: A.B. Chaudhari
    fa400.91.odt                                                                                 1/7




                                                                                             
                IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                          NAGPUR BENCH, NAGPUR




                                                                     
                                FIRST APPEAL NO.400/1991

    APPELLANT:-                The Maharashtra State Electricity Board,
                               through the Executive Engineer (Stores)




                                                                    
                               Major Stores 'A', M.S.E.B. Deepnagar,
                               Bhusawal, Distt. Jalgaon.

                                             ...V E R S U S...




                                                      
    RESPONDENT:-               The Union of India,
                                     
                               Owning and Representing
                               the Central Railway, through the
                               General Manager, Central Railway,
                                    
                               V.T. Bombay.
    ----------------------------------------------------------------------------------------------
                        [Shri D.K. Dubey, Adv. for appellant]
                        [Shri P.S. Lambat, Adv. for respondent]
    ----------------------------------------------------------------------------------------------
            

                                            CORAM:- A.B. CHAUDHARI, J.

DATED :- 08.12.2009

ORAL JUDGMENT

1. Being aggrieved by the judgment and order dated

23.8.1990 passed by the Railway Claims Tribunal, Nagpur Bench in

Claim Case No.56/OA-I/RCT/NGP/90, rejecting the claim application

on the ground that delay in filing the same was not satisfactorily

explained and consequently, the claim application was dismissed,

the present appeal was filed by the appellant in this Court.

fa400.91.odt 2/7

2. Following are the facts which are not in dispute.

The goods were booked by the appellant on 11.3.1986

and the claim under Section 78-B of the Indian Railways Act, 1890

was lodged by the appellant on 21.6.1986 in response to which

the respondent - Railways issued letter dated 26.3.1987 indicating

to the appellant that the claim was settled at Rs.70,000/- but the

said amount was not being disbursed to the appellant because

there was debit in its account. On 20.2.1990 the appellant issued

notice under Section 80 of the Code of Civil Procedure which was

received by Railways on 26.2.1990. The claim came to be filed on

23.4.1990 i.e. almost one month after expiry of the statutory

period of two months. The Railway Claims Tribunal was

constituted by the Government of India on 8.11.1989 about which

gazette notification was made on 5.10.1989 and the Tribunal

started functioning at Nagpur from 8.11.1989.

3. Learned Counsel for the appellant argued that letter

dated 26.3.1987 that was issued by the Railways in response to

the claim application under Section 78-B of the Indian Railways Act

will have to be treated as acknowledgment under Section 18 of

fa400.91.odt 3/7

the Limitation Act, 1963 and therefore, the limitation stopped

running from that day. He then argued that under Section 15 (2)

of the Limitation Act there is provision to exclude statutory period

of two months in case where notice under Section 80 of the Code

of Civil Procedure is given and therefore, the limitation stood

extended up to 23.3.1990. According to him even though the

claim was filed on 23.4.1990 i.e. almost a month after total period

of three months unlike Civil Court, the Tribunal has been given

power under Section 17 (2) of the Railways Act, 1989 and

therefore, the Tribunal has a power to condone delay even beyond

period of three years if there is sufficient cause. According to

learned Counsel for the appellant sufficient cause was clearly set

out in various paragraphs of the application for condonation of

delay that was made by the appellant along with claim application

and these averments were not at all denied by filing any reply and

therefore, the said averments will have to be taken as true. The

Tribunal erred in not considering this aspect in correct

prospective.

fa400.91.odt 4/7

4. Per contra, learned Counsel for the respondent -

Railways vehemently opposed the appeal and argued that as a

matter of fact limitation started running from 11.3.1986 and the

period of three years expired on 10.3.1989 the letter regarding

settlement of claim dated 26.3.1987 would not stop running of

limitation as the appellant which is the public body ought to have

taken steps to file the proceedings during the period of limitation

rather than making correspondence here and there as stated in

paragraph Nos.3 and 4 of the application for condonation of delay.

According to him, the Tribunal was right in holding that the

appellant was required to be vigilant in pressing its claim in the

absence of which no sufficient cause could be said to have been

made out by the appellant. He then argued that assuming that

letter dated 26.3.1987 is in the nature of acknowledgment under

Section 18 of the Limitation Act; even then the claim was filed on

23.4.1990 and that is also beyond period of three years and the

explanation beyond three years is not satisfactory and therefore,

the Tribunal was right in dismissing the application for

condonation of delay. He then argued that the Tribunal having

fa400.91.odt 5/7

started functioning at Nagpur since 8.11.1989 it cannot be said

that the appellant did not know about constitution of Railway

Claims Tribunal at Nagpur since according to him ignorance of law

is no excuse.

5. I have gone through the impugned judgment and award

and the findings recorded by the Tribunal in the matter. At the

outset, it will have to be noted that the application for condonation

of delay is in several paragraphs and all relevant details for

claiming condonation of delay have been mentioned in that

application which is duly signed and verified by the concerned

organization of the appellant. Surprisingly enough respondent -

Railways did not bother to file any reply and deny the averments

or rebut the averments made in the said application. This clearly

means that the Tribunal was required to take those averments as

true at their face value in the absence of any denial or rebuttal but

reading of the order of the Tribunal shows nothing of this sort.

There is, therefore, failure on the part of the Tribunal in dealing

with the case on facts as stated by me. Now the averments in

paragraph Nos.3 and 4 of this application clearly show what steps

fa400.91.odt 6/7

were taken by appellant - organization. It is not necessary for me

to repeat those averments here. The appellant being a public

sector undertaking, it is required to consult its standing Counsel so

also the higher officials. It does not act or is not expected to act

like a private person who himself alone decides. The averments

made in the application in paragraph Nos.3 and 4 clearly show

that appellant having come to know about constitution of Tribunal

at Nagpur it was decided to refer the matter to Bombay office and

consequently, the legal department thereof, which opined that

claim should not be filed before the Civil Court but it will have to

be filed before the Tribunal. I fail to understand how the Tribunal

calls this particular action on the part of appellant - M.S.E.B. as not

satisfactory or sufficient cause for condoning the delay of about

one month. The delay of one month is not so much that the

Tribunal should have punished the appellant by throwing out the

claim application in the manner done particularly because these

averments in paragraph Nos.3 and 4 of the application were not

even denied. In my opinion, therefore, this period of one month

after three years was required to be condoned by exercising

fa400.91.odt 7/7

power under Section 17 (2) of the Railways Act, 1989 as sufficient

cause was made out. There is no need to deal with the

submissions made by learned Counsel for the respondent on the

point of Section 18 of the Limitation Act and so on and so forth as

that will burden this judgment. For the above reasons, therefore, I

make the following order.




                                               
                                  ORDER
                                  
                   (i)        First Appeal is allowed.
                                 
                   (ii)       The impugned judgment and order dated

23.8.1990 made by the Railway Claims Tribunal, Nagpur Bench in

Claim Case NO.56/OA-I/RCT/NGP/90 is set aside.

(iii) The proceedings are remitted to the Railways

Claims Tribunal, Nagpur Bench for deciding the claim made by the

appellant afresh without being influenced by any of the

observations made by the Railway Claims Tribunal or by this Court

on its own merits. The claim application be decided within a

period of four months from the date of receipt of writ of this Court.

No order as to costs.

JUDGE ssw

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter