Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hindustan Shipyard Ltd vs Eastern Power Distribution Company Of ...
2024 Latest Caselaw 4421 AP

Citation : 2024 Latest Caselaw 4421 AP
Judgement Date : 18 June, 2024

Andhra Pradesh High Court - Amravati

Hindustan Shipyard Ltd vs Eastern Power Distribution Company Of ... on 18 June, 2024

Author: Ninala Jayasurya

Bench: Ninala Jayasurya

                                         1
                                                                             NJS, J
                                                                    WP_20857_2023

APHC010405982023
                      IN THE HIGH COURT OF ANDHRA PRADESH
                                   AT AMARAVATI                            [3209]
                             (Special Original Jurisdiction)


                TUESDAY ,THE EIGHTEENTH DAY OF JUNE
                  TWO THOUSAND AND TWENTY FOUR

                                    PRESENT

          THE HONOURABLE SRI JUSTICE NINALA JAYASURYA

                      WRIT PETITION N
                                    No: 20857 of 2023

Between:

Hindustan Shipyard Ltd.,                                          ...PETITIONER
Rep.by its Senior Manager (Plant Maintenance)
                                   AND

Eastern Power Distribution Company of Andhra Pradesh
Ltd., and Others                                  .......RESPONDENT(S)

...RESPONDENT(S)

Counsel for the Petitioner(S):

1. Mr.K.Gopal K.Gopal Chowdary, Chowdary learned counsel for Mr.Challa Guna Ranjan, Advocate

Counsel for the Respondent(S):

1. Mr.Metta Chandra Sekhara Rao, Standing Counsel for APEPDCL

The Court made the following Order:

The Writ Petition is filed challenging the Provisional Assessment Order

dated 19.01.2023 of the 3rd respondent and Final Assessment Order of the 2nd

respondent dated 13.07.2023 on various grounds.

2. The relevant facts of the case as set out in the affidavit ffiled iled in support

of the writ petition may briefly be stated as follows:

NJS, J WP_20857_2023

The petitioner is a Government Company wholly owned by the

Government of India and under the control of the Ministry of Defence. It is

engaged in the construction and repairs of ships and sub-marines vital to the

National Security and Defence of India. It is availing electricity supply from the

1st respondent / Distribution Licensee vide Service Connection No.VSP012

with a Contracted Maximum Demand (CMD) of 3500 KVA.

3. The Government of India came out with the National Action Plan for

Climate change and the National Solar Mission was one of the flagship

programmes. A target of 100 Giga Watts (GW) was declared by the Ministry of

New & Renewable Energy, out of which 40 GW was to be achieved by various

small rooftop and distributed solar power plants. The Ministry of New &

Renewable Energy issued a communication dated 07.01.2015 conveying the

sanction of the President of India for setting up over 300 MW of grid-

connected and off-grid solar power projects by the Defence Establishments

under the Ministry of Defence and the Para-Military Forces under the Ministry

of Home Affairs providing for Viability Gap Funding. The petitioner was

among those mandated by the Government of India to set up rooftop solar

power projects and to use the energy generated therein for its own use.

4. The petitioner was allotted rooftop solar power plant with a capacity of 3

MW, to be installed on various vacant roofs of the buildings within the

premises of the Naval Shipyard at Visakhapatnam. The installation and

commissioning of 2 MWp ( 500 KWp x 4) was undertaken with the guidance,

NJS, J WP_20857_2023

approval and supervision of the Solar Energy Corporation of India Ltd.,

(SECI), a Government of India undertaking under the Ministry of New &

Renewable Energy (MNRE) and the same was commissioned in June, 2018.

Thereafter, the installation and commissioning of 1 MWp ( 500 KWp x 2) was

undertaken under the guidance, approval and supervision of the New &

Renewable Energy Development Corporation of Andhra Pradesh

(NREDCAP), which is the nodal agency set up by the State Government and

the same was commissioned in August, 2019. Both the rooftop solar power

plants were set up and operated as Off-Grid solar power plants under

Renewable Energy Service Company (RESCO) mode by M/s.Clean Max

Enviro Energy Solutions Pvt. Ltd., being the successful bidder identified by

'SECI' under competitive bidding and Power Purchase Agreements were

entered into for the energy generated and delivered by the said entity from the

rooftop solar power plants in the petitioner's premises for consumption by the

petitioner through the dedicated internal electrical lines within the petitioner's

premises. The energy generated from the rooftop solar power plants was

conveyed to various load centers within the petitioner's premises through

dedicated internal electrical lines in island mode. Statutory approvals by the

Chief Electrical Inspector to the Government of India under the Regional

Inspectorial Organization of the Central Electricity Authority in terms of Central

Electricity Authority (Measures relating to Safety and Electrical Supply)

Regulations 2010 for energizing the rooftop solar power plants were

sanctioned through Letters dated 16.11.2018 and 29.09.2020. Thereafter, the

NJS, J WP_20857_2023

energy generated from the rooftop solar plants in the petitioner's premises has

been continuously consumed by the petitioner's loads within the petitioner's

premises through the dedicated internal electrical lines.

5. On 28.06.2022, the 4 th respondent carried out a routine inspection of

the service connection of the petitioner bearing No.VSPO12 and prepared an

inspection report. On the basis of the said report, the 3rd respondent issued a

Provisional Assessment Order dated 19.01.2023 purportedly in terms of

Section 126 (2) of the Electricity Act, 2003(for short 'the Act') and based on

Assessment Rules contained in Appendix XII read with Clause 9.3 of the

General Terms and Conditions of the Supply (GTCS), wherein it is inter alia

alleged that the petitioner "is guilty of unauthorized use of Electricity under

Section 126 of the Act owing to usage of Electricity by a means not authorized

by the Company" and electricity charges allegedly due to the 1st respondent

were assessed at Rs.3,54,13,885/-. The petitioner submitted a representation

dated 03.02.2023 by way of objections to the said Provisional Assessment

setting out the relevant aspects. Thereafter, the 2nd respondent issued a

Notice dated 13.04.2023 to the petitioner and fixed a date i.e., 19.04.2023 for

personal hearing and passed the impugned Final Assessment Order dated

13.07.2023.

6. Heard Mr.K.Gopal Chowdary, learned counsel for the petitioner and

Mr.Metta Chandra Sekhar Rao, learned counsel appearing on behalf of the

respondents. Perused the material on record.

NJS, J WP_20857_2023

7. The learned counsel for the petitioner made elaborate submissions with

reference to the provisions of the Act. It is his foremost contention that the

impugned Assessment Order is without jurisdiction and contrary to the

provisions of the Act. He contends that invocation of Section 126 of the Act, in

the facts and circumstances of the case, is wholly misconceived and the

impugned order on the basis of the Inspection Report of the 4 th respondent is

liable to be set aside. Referring to the said report dated 28.06.2022, the

learned counsel submits that there is no allegation of tampering of seals,

much less theft of energy by the petitioner, that it is not even the case of the

respondents that there was any electricity supplied by the licensee that has

been used unauthorizedly or by means not authorized by it.

8. In elaboration, he submits that Section 126 of the Act applies only to the

electricity supplied or arranged to be supplied by the licensee and has no

application to the electricity generated from the rooftop solar power plants

installed in the petitioner's premises and consumed by it within its premises

through the internal lines and without use of licensee's transmission lines or

network.

9. Referring to Section 7 of the Act, he contends that a generating station

may be established, operated and maintained without obtaining a license. He

submits that as the electricity is generated from the rooftop solar power plants

installed in the petitioner's premises which is meant for it's consumption within

it's premises, the question of connectivity with the Grid of the 1st respondent

NJS, J WP_20857_2023

does not arise at all and therefore, the consumption of power injected to the

Grid through the transmission lines of the licensee / 1st respondent would not

arise at all. Further, that there is no provision of Law, Rule or Regulation which

contemplates permission / approval of the 1st respondent for installation of a

rooftop solar power plant, much less for consumption of energy generated

from the rooftop solar power plants for self utilization. He also submits that the

petitioner in terms of the scheme notified by the Ministry of New & Renewable

Energy is consuming the energy generated from the rooftop solar power plant

which has got the approval of the statutory authority i.e., Chief Electrical

Inspector and in such circumstances, the allegation that the petitioner is

unauthorizedly using the electricity without obtaining permission or approval of

the respondents is untenable and misconceived.

10. While stating that though no approval or permission is required, much

less from the 1st respondent for installation of rooftop solar power plant, the

learned counsel drawing the attention of this Court to the Letters of the

petitioner dated 04.12.2021, 08.02.2022 and 04.04.2022 submits that despite

the said communications, nothing was heard from the respondents. Therefore,

the petitioner's representatives / General Manager (Technical) and Director

(Corporate Planning) met the Chairman and Managing Director of the 1 st

respondent, but the same did not evoke any response. In those

circumstances, he submits that the action of the respondents and the

impugned order on the premise that the petitioner is indulging in unauthorized

use of electricity without approval of the 1st respondent is not tenable. He also

NJS, J WP_20857_2023

submits that the Order under challenge has been passed without considering

the several contentions with regard to scope and applicability of the Section

126 of the Act advanced on behalf of the petitioner during the personal

hearing.

11. The learned counsel further contends that the 2nd respondent while

passing the Final Assessment Order have taken irrelevant aspects into

consideration and therefore the impugned order is liable to be set aside on

that ground also. It is his contention that Regulation 3 of 2017 framed by the

Andhra Pradesh Electricity Regulatory Commission (A.P.E.R.C.), is not

applicable to the facts of the case, that Andhra Pradesh Solar Power Policy,

2018 referred to in the impugned order is in respect of solar power plants

connected with the Grid or open access is required. He submits that the

petitioner never availed the open access in terms of the Section 2 (47) of the

Act and further that in the impugned order, there is no reference as to the

provision / regulation which is infringed by the petitioner or that prohibit it from

injecting the power generated through the rooftop solar power plant for the

petitioner's own consumption through the internal supply system. Laying much

emphasis that the energy generated through rooftop solar power plant is not

the energy supplied by the licensee, he contends that the assessment made

purportedly on the basis of GTCS is wholly misconceived. He submits that in

terms of proviso to Section 42 (2) of the Act, open access is necessary for

levy of cross subsidy charges and when no open access is availed, imposition

of cross subsidy surcharge in the impugned order reflects non-application of

NJS, J WP_20857_2023

mind by the authorities. Insofar as the Circular Memo dated 02.08.2023

referred to in the counter-affidavit, the learned counsel submits that the

procedure and conditions mentioned in the said Circular are unreasonable

and without jurisdiction and at any rate, the same cannot be made applicable

to the inspection conducted on 28.06.2022, much prior to the issuance of the

said Memo. He submits that the impugned order is without jurisdiction and the

writ petition is maintainable. Making the said submissions, the learned counsel

seeks to allow the writ petition.

12. Mr.Metta Chandra Sekhara Rao, learned counsel for the respondents,

on the otherhand, contends that the writ petition is misconceived. He submits

that as the matter involves determination of questions of fact, the writ petition

under Article 226 of the Constitution of India is not maintainable. He submits

that Section 86 of the Act provides for adjudication of disputes and in view of

the availability of effective alternative remedies against the impugned order

including the provision for appeal, the writ petition is liable to be dismissed.

Without prejudice to the said contentions, he submits that the lines through

which the power generated from the rooftop solar power plants is drawn

belongs to DISCOM / 1 st respondent and as the petitioner had not obtained

the mandatory permission for rooftop solar power plant, the order passed by

the 2nd respondent pursuant to the inspection dated 28.06.2022 is legal, valid

and within the jurisdiction of the respondent-authorities. He submits that all the

solar power plants with capacity greater than the 1 MW require permission

from the 1st respondent before commissioning of the project and connecting to

NJS, J WP_20857_2023

the internal Grid of the consumer or to the Grid of the distribution company.

He submits that in the present case, the petitioner without obtaining any

permission from the 1st respondent, installed 3 MWP rooftop solar power

plant, which is not permissible. He also submits that the petitioner entered

into an agreement with M/s.Clean Max Enviro Solutions Private Limited to

purchase solar power generator by the said Company and therefore

Regulation No.3 of 2017 is applicable and the contentions contra are not

tenable. He submits that as the petitioner had indulged in unauthorized use of

electricity without obtaining approvals / permission from the 1st respondent as

required under Regulation 3 of 2017 as also in terms of the Memos issued by

the 1st respondent, the 2nd respondent is justified in passing the order under

challenge. It is also his contention that the General Terms and Conditions of

Supply (GTCS) are applicable as the petitioner is a consumer of 1st

respondent and the impugned Assessment Order is in accordance with the

relevant Terms and Conditions of Supply. He places reliance on the decisions

of the Hon'ble Supreme Court in Reliance Infrastructure Ltd., v. State of

Maharastra 1, PTC India Ltd., v. Central Electricity Regulatory Commission 2

and the decision of a Division Bench of the erstwhile High Court of Andhra

Pradesh at Hyderabad in CMD, SP DCL v. Sudalagunta Sugars Ltd., 3 and

urges for dismissal of the writ petition.

2019 (3) SCC 352

2010 (4) SCC 603

2013 (1) ALD 395

NJS, J WP_20857_2023

Consideration by the Court:

13. On an appreciation of the rival contentions, the points that falls for

adjudication by this Court are:

(i) Whether the Orders under challenge are valid, legal and within the jurisdiction of the respondent-authorities and sustainable in Law?

(ii) Whether the writ petition is maintainable?

14. At the outset, it may be appropriate to note that even as per the

admitted case of the respondents at the time of inspection of the petitioner's

premises / metering equipment, it was found that all the seals were in tact and

there is no suspected theft of energy (Ex.P5 dated 28.06.2022), but the

respondent authorities passed the orders under challenge inter alia, on the

premise that the solar generators are connected directly to the L.T.Network at

12 Numbers locations and the petitioner is utilizing solar power generated

without taking prior approvals from A.P.E.P.D.C.L. / A.P.TRANSCO and thus,

committed unauthorized use of electricity as per Section 126 (6)(b) (ii) of the

Act. Thus, no factual controversies are involved and the main issue which is

required to be adjudicated is whether Section 126 of the Act is applicable to

the facts of the case and the Orders under challenge are liable to be set aside

for the reason that the same are without jurisdiction.

15. Section 126 of the Act inter alia deals with Assessment, which is

extracted hereunder for ready reference:

NJS, J WP_20857_2023

Assessment :- (1) If on an inspection of any place or premises or after inspection of the equipments, gadgets, machines, devices found connected or used, or after inspection of records maintained by any person, the assessing officer comes to the conclusion that such person is indulging in unauthorized use of electricity, he shall provisionally assess to the best of his judgment the electricity charges payable by such person or by any other person benefited by such use.

(2)...........

(3)...........

(4)...........

(5)...........

(6)...........

16. As per the explanation (b) provided under Section 126 of the Act,

"unauthorized use of electricity" means the usage of electricity -

(i) by any artificial means; or

(ii) by a means not authorized by the concerned person or authority or licensee; or

(iii) through a tampered meter; or 2 [(iv) for the purpose other than for which the usage of electricity was authorized; or

(v) for the premises or areas other than those for which the supply of electricity was authorized."

17. In the present case, Section 126 (6) (b) (i), (iii), (iv) and (v) are not

attracted and even according to the respondents, the only allegation /

irregularity is that the petitioner had committed unauthorized use of electricity

which falls under Section 126 (6)(b)(ii) of the Act. According to them, as the

petitioner utilized the solar power generated without taking prior approvals

from the A.P.E.P.D.C.L / A.P. TRANSCO, the same amounts to unauthorized

NJS, J WP_20857_2023

use of electricity. It is not their case that the petitioner is unauthorizedly using

the electricity supplied by the 1st respondent nor is it their case that the

petitioner is availing solar power generated by an agency and injected to the

Grid maintained by the 1st respondent / Distribution company, without any

permission or approval as required under Law / Regulations. No provision

which require prior permission / approval for utilization of the solar power

generated through the rooftop solar power plant for consumption by the

petitioner within its premises has been pointed out by the respondents. Even

according to the respondents, the solar power generated is being utilized

within the premises of the petitioner and the only feature according to them is

the solar generators are connected directly to the L.T.Network at 12 Number

locations. However, they failed to explain / establish in what manner, the same

amounts to unauthorized use of electricity, which is undisputedly not being

supplied by the 1st respondent, much less through the transmission lines laid

by it or that by virtue of the same, the 1st respondent had sustained any loss.

In view of the same, this Court finds merit in the contentions of the learned

counsel for the petitioner that the provisions of the Act are not attracted and

invocation of Section 126 of the Act is without jurisdiction.

18. Further, as seen from the impugned order, no reference is made to any

provision requiring the permission for setting up of rooftop solar power plant

and non compliance of the same by the petitioner. In fact as seen from the

material on record, the petitioner had addressed as many as three letters to

the respondent authorities (Ex.P4) informing them about the installation and

NJS, J WP_20857_2023

commissioning of rooftop solar power plants as part of clean and green

initiative and also obtained necessary approvals from the Central Electricity

Authority / Chief Electricity Inspector to Government. To none of the

communications addressed by the petitioner, was there any reply and in the

said circumstances, the assessment on the premise that the petitioner

committed unauthorized use of electricity is not just or tenable. The Circular

Memo dated 02.08.2023 referred to in the counter affidavit requiring

permission from the 1st respondent before commissioning of the power plants

with capacity of more than 1 MW and the procedure to be followed for

synchronization of solar power plants in house for captive use, irrespective of

the validity or otherwise of the same, cannot have any retrospective effect.

The respondents have not placed any material on record to establish that as

on the date of inspection, the petitioner is required to obtain permission /

approvals for installation and synchronization of the solar power generated for

its captive use, in the absence of which, no conclusions can be arrived at by

this Court that the solar power utilized for the petitioner's captive use is

without any authorization / approval of the respondent authorities.

19. Insofar as the A.P.Solar Power Policy, 2018 referred to in the impugned

order is concerned, the same cannot be made applicable to the petitioner's

case. The policy of the Government as setout in G.O.Ms.No.1 dated

03.01.2019 (Ex.P15) is in respect of the solar power plants / project

synchronized with the Grid and as noted above, there is no Grid connectivity

much less, evacuation of power through the Grid. Therefore, reliance on the

NJS, J WP_20857_2023

said policy is misconceived and the said view of this Court is equally

applicable to the contentions advanced with reference to the Regulation No.3

of 2017 concerning the Power Evacuation from Captive Generation,

Cogeneration and Renewable Energy Power Plants. As per Para No.4 (16) of

the said Regulation, power evacuation means "the facility that allows

generated power to be immediately transferred from a generating plant to the

Grid for further transmission / distribution to load centers." In the present

case, there is no evacuation of power generated through the rooftop solar

power plant set up on the petitioner's premises to the Grid and therefore

application of the said Regulation would not arise at all.

20. This Court on a thorough consideration of the matter has no hesitation

to hold that the provisions of the Act are not applicable to the case on hand

and as such, the General Terms and Conditions of Supply are also not

applicable. Be that as it may.

21. The learned counsel for the petitioner also raised contentions with

reference to the levy of cross subsidy surcharge in the impugned order by

drawing the attention of this Court to Section 2 (47) of the Act. As rightly

contended, in the absence of use of any Transmission / distribution network of

the 1st respondent / licensee, the question of open access would not arise at

all. The levy of cross subsidy surcharge would arise, in the event of the

petitioner availing the open access only and in fact, as per provisos to Section

42 (2) of the Act, such open access shall be allowed on payment of surcharge

NJS, J WP_20857_2023

in addition to the charges for wheeling as may be determined by the State

Commission and the surcharge shall not be leviable in case, open access is

provided to a person who has established a captive generating plant for

carrying electricity to the destination of his own use.

22. In the present case, as seen from the impugned orders, there is no

reference to wheeling charges which clearly establishes that no power is

being wheeled through the distribution system of the 1st respondent under

open access and therefore the levy / imposition of cross subsidy surcharge is

unjust, without application of mind and jurisdiction. The impugned order is

therefore is not sustainable on that ground also.

23. Though the contentions advanced by the learned counsel for the

respondents that the petitioner can seek adjudication of the dispute under

Section 86 of the Act or by filing an appeal against the order of the 2nd

respondent may merit appreciation in a given case, but the facts and

circumstances of the present case do not warrant acceptance of the same, the

writ petition is maintainable and invocation of Section 126 of the Act is not

tenable.

24. So far as the decisions relied on by the learned counsel for the

respondents i.e., Chairman and Managing Director, Southern Power

Distribution Company Limited of A.P., v. Sudalagunta Sugars Ltd., is with

reference to a dispute between the parties concerning bills issued to the

NJS, J WP_20857_2023

respondent-Company and the said decision is not applicable to the facts of the

present case.

25. Reliance Infrastructure Limited v. State of Maharashtra, is a case

where there is a challenge to the tariff regulation framed by the Maharashtra

Electricity Regulatory Commission and the said decision is of no aid to the

respondents.

26. In PTC India Limited case, the Hon'ble Supreme Court inter alia, was

dealing with the powers of the Appellate Tribunal under the Electricity Act to

examine the validity of the CERC (Fixation of Trading Margin) Regulations,

2006 and the said case is based on a different fact situation.

27. Considering the matter in its entirety and in view of the conclusions

arrived at supra, the orders under challenge are not sustainable as the same

suffers from non-application of mind and without jurisdiction.

Point Nos.1 and 2 are answered accordingly.

28. In the result, the writ petition is allowed and the impugned orders are set

aside. There shall be no order as to costs. As a sequel, all pending

applications shall stand closed.

__________________________ JUSTICE NINALA JAYASURYA Dated 18.06.2024 BLV

NJS, J WP_20857_2023

THE HON'BLE SRI JUSTICE NINALA JAYASURYA

WRIT PETITION No.20857 of 2023

Date: 18.06.2024

BLV

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter