Citation : 2023 Latest Caselaw 5156 AP
Judgement Date : 20 October, 2023
IN THE HIGH COURT OF ANDHRA PRADESH: AMARAVATI
HONOURABLE SRI JUSTICE SUBBA REDDY SATTI
WRIT PETITION No.10953 of 2021
Palem Ram Suresh, S/o late P.Ramalingaiah
Naidu, aged 45 years, Occ: Agriculture, R/o
Kuchivaripali, Rajampet Revenue Village,
Rajampet Mandal, Kadapa District and
another.
... Petitioners.
Versus
The State of Andhra Pradesh, Rep. by its
Principal Secretary, Energy Department,
Secretariat, Velagapudi, Guntur District and
six others.
... Respondents.
Counsel for the petitioners : Ms.P.Lakshmi Priya
Counsel for respondents 1 to 4 : Sri Anup Koushik Karavadi
ORDER
Challenging the notice dated 22.05.2021 issued by 4th
respondent under Section 68 and 164 of Electricity Act, 2003
r/w Telegraph Act,1885 and CEA (Safety and Electricity
Supply) Guidelines, 2010, the above writ petition was filed.
2. a) Averments in the affidavit, in brief, are that the
petitioners owned land in S.No.393 apart from other
properties of Rajampet village. Banana, Mango, Lemon etc.
SRSJ WP No.10953 of 2021
crops are being cultivated. Abutting the petitioners' land, 132
KV sub-station was constructed in the year 1990. The land of
the petitioners is fit for house sites. The 4th respondent issued
notices impugned in the writ petition. A perusal of the notice
would disclose that A.P TRANSCO is executing 132 KV
D.C/S.C. line from 200 KV sub-station, Rajampet to 132 KV
sub-station C.Orampadu under a system improvement
scheme for improving the reliability of power supply; that the
transmission lines are passing through the lands of the
petitioners; that compensation for the land in which the
tower laid will be arranged, for tower base area as a part of
land diminution and as per the land rates fixed by the
District Collector etc.,
b) Petitioners came to know that the respondents 2 to 4
got the administrative approval on 03.04.2013 for
construction of 132/22 KV sub-station at C.Orampadu and
the A.P. TRANSCO published notification in newspapers on
29.10.2014. The notifications were issued for the statewide
projects without particulars. As per the land identified by the
revenue authorities S.Nos.392 or 393 belonged to the
petitioners was not included. Thus, the petitioners did not
SRSJ WP No.10953 of 2021
submit any objections. If the respondents lay lines directly
from the sub-station, Rajampet, it will reduce one or two
poles and shorten the line. The Tower/Lines in between 6-4
shown by the respondents are not in straight. Respondents
changed the Detail Project Report (DPR) to benefit some
persons only after 18.03.2020 and after filing of counter
affidavit dated 06.11.2020 in W.P.No.18511 of 2020. The
respondent authorities have to erect 99 Towers as per DPR,
but now it has been changed to 96 with deviations and
hence, they issued notices to the petitioners. The Right to
Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (for short "the
Act") is not applicable to the Acts specified in Schedule-IV,
wherein the Indian Electricity Act, 2003 is at Serial No.12.
Section 105 (3) of the Act contemplates that the payment of
compensation is as per Schedule-I and rehabilitation and
resettlement specified in Schedules II and III of the Act.
Notification was issued in S.O.No.2368 (E) dated 28.08.2015.
Petitioners are entitled to compensation as per Schedule-I of
the Act and as per G.O.Rt.No.83 dated 20.06.2017. With
these averments, the above writ petition is filed.
SRSJ WP No.10953 of 2021
3. a) Counter affidavit was filed on behalf of 4th
respondent. It was contended, inter alia, that the A.P.
TRANSCO in exercise of powers conferred under
G.O.Ms.No.115 Energy Department dated 07.10.2003 gave
administrative approval vide TOO (CE-Construction-1)
Ms.No.3 dated 03.04.2013 for construction of 132/33 KV
sub-station at Chinna Orampadu and 132 KV DC/SC Line
from 220/132 KV SS Rajampet to proposed 132/22 KV SS
Chinna Orampadu. After the scheme was approved, the A.P.
TRANSCO published notification in Telugu and English
dailies on 29.10.2014 and objections are called for. However,
the petitioners did not raise objections at any point in time.
Notices were issued to all the concerned landowners. Notices
dated 22.05.2021 were issued to the petitioner by registered
post.
b) As per Section 164 of Electricity Act, 2003 r/w
Section 10 of Indian Telegraph Act, 1885, the A.P. TRANSCO
got absolute authority to proceed with laying of electricity
supply lines or electric poles for the transmission of electricity
on or over the private lands subject to right of the
owner/occupier to claim compensation, if any damage is
SRSJ WP No.10953 of 2021
sustained by reason of placing of such electric supply lines.
The acquisition of land is not necessary. The approved tower
profile and tower schedule were prepared by conducting
detailed survey in March, 2016. As per the approved tower
schedule, A.P. TRANSCO has in fact completed the work in
respect of 91 towers, out of the original proposed 99 towers
including line work and sub-station works.
c) The Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013
(for short "the Act") is not applicable to the electricity
erection towers as per Section 164 of Electricity Act. A.P.
TRANSCO is paying compensation amounts to the farmers as
per slab rate fixed by the District Collector vide proceedings
Ref.E6/1976/2018, dated 07.06.2019 duly considering the
G.O.Rt.No.83 dated 20.06.2017. The information furnished
under RTI dated 18.03.2020 is for the towers which were
already executed. There is no procedure for collecting land
survey numbers while doing the line survey. While taking up
the actual line execution, it will address the revenue
authorities to identify the actual land holder and survey
SRSJ WP No.10953 of 2021
number of the land where the tower is proposed to be laid for
paying land diminution/crop compensation.
d) A detailed survey was conducted, and the tower
schedule was approved on 19.03.2016. During that time,
there is no 132/33 KV features 220 KV sub-station,
Rajampet. The work for erection of 132/33 KV features in
220 KV sub-station, Rajampet was awarded on 30.05.2017.
During the execution of that work, the orientation of
proposed 132 KV C.Orampadu feeder bay at 220 KV SS
Rajampet and the revised tower schedule was approved on
08.03.2019. The revision of the tower schedule is completely
based on technical aspects but not to benefit some other
people. The contention of the petitioners to lay towers just
adjacent to the compound wall of 220 KV sub-station
Rajampet is not technically feasible and such changes in
alignment of line would impact other landowners and further
lead to multiple litigation. There is no provision under the
Electricity Act, 2003 to obtain prior consent from the owners
of private property for laying electrical lines.
SRSJ WP No.10953 of 2021
e) A.P. TRANSCO conducted a check survey with
revenue authorities and obtained the details of survey
numbers and landowners for location No.04 & 05.
Accordingly, notices were issued to the petitioners for laying
of towers. An amount of Rs.65,21,538/- was deposited by
A.P. TRANSCO to the Sub Collector, Rajampet vide cheque
No.0755234 dated 17.03.2021 towards compensation for
land acquisition of 220 KV SS Rajampet. The 132 KV sub-
station at Chinna Orampadu is almost completed in all
respects and the A.P. TRANSCO spent approximately 20
crores. The work envisaged on public interest and the same
is meant for agriculture supply and eventually prayed to
dismiss the writ petition.
4. The Tahsildar filed a separate counter affidavit on its
behalf and on behalf of 5th respondent, almost reiterating the
averments in the counter filed by 4th respondent.
5. Reply affidavit was filed by the petitioners contending
that respondents issued notices without considering
G.O.Rt.No.83 dated 20.06.2017. Guidelines were framed
under G.O.Rt.No.83 for payment of compensation towards
SRSJ WP No.10953 of 2021
damages with regard to right to way for transmission lines.
The respondents have not conducted any survey for laying
towers and thus, prayed to set aside the impugned notices.
6. Heard Sri P.Sreeramulu Naidu, learned senior counsel
representing Ms.P.Lakshmi Priya, learned counsel for the
petitioners, learned Government Pleader for Revenue for
respondents 5 & 6, Sri Anup Koushik Karavadi, learned
Standing Counsel for 2nd respondent.
7. Learned senior counsel representing the petitioners
would submit that original DPR is changed and the change in
DPR is not on straight line. He would submit that while fixing
compensation, notice under Section 67 of Electricity Act,
2003 has to be issued and the respondents failed to take into
consideration S.O.No.2368 (E) dated 28.08.2015, while fixing
the compensation. He would also submit that LOC 4& 5 were
not shown earlier and from LOC 6 to sub-station, if a line is
drawn, lying of tower in the petitioners' land can be avoided.
He also would contend that prior consent of the petitioners
was not taken.
SRSJ WP No.10953 of 2021
8. Per contra, learned standing counsel for 2nd respondent
would submit that no DPR is required, and the compensation
is being determined by the District Collector as per the
guidelines. He would also submit that Exhibit P3 filed along
with writ petition is not speaking about final plan and in fact,
original plan was slightly changed to benefit the petitioners.
As per the original plan, towers are to be laid in the centre of
petitioners' land and to avoid loss to the petitioners, the
authorities considered feasibility and are now laying towers
slightly moving to an end. He would submit that in fact
efforts were taken by the respondents to mitigate the loss
caused to the petitioners to the extent possible. He would
also submit that the guidelines relied upon by the petitioners
for fixing compensation under G.O.Rt.No.83 dated
20.06.2017 do not apply to the facts of the case.
9. The points for consideration are:
1) Whether the notices impugned are liable to be set aside?
2) Whether the respondent authorities are following the procedures while fixing the damages?
3) Whether the consent of land owner is necessary for laying electricity lines or towers?
SRSJ WP No.10953 of 2021
10. The main contention of learned senior counsel for the
petitioner is that without consent of the petitioners
respondent authorities are erecting towers in their land.
Regarding obtaining permission qua erecting towers or
transmission line, no permission of landlord is necessary.
11. In K.Subrahmanyam and Ors. Vs. The State of
Andhra Pradesh and Ors1, learned single Judge of this court
observed as follows:
6. The Indian Electricity Act was repealed and in its place, new statute i.e.. The Electricity Act, 2003 was enacted and there is no provision to obtain prior consent even from the owners of the private property for laying electricity lines. In fact, this Hon'ble Court in a decision reported in 2013(4) ALD-88, held that the APTRANSCO would not be required to either initiate proceedings for acquisition of land or to obtain consent from the owner for erecting tower or laying the lines and the entitlement of Land Owners to compensation would arise only at a later date and it cannot be a ground to hinder the implementation of the scheme. The Apex Court in a decision reported in 2007(6) SCC 792 and 2008(11) SCC 476 held that both telegraphic lines and electric lines are required to be drawn over the agriculture lands or other property belonging to the private parties and in drawing such lines the entire land cannot be acquired, but the effect thereof could be diminution of value of the property, over which, such lines are drawn and the Telegraphic Act, 1885 provides for the manner in which the amount of compensation is to be computed. The latest Judgment of the Apex Court in 2017(5) SCC 143
MANU/AP/0565/2021
SRSJ WP No.10953 of 2021
also supports the power of the electricity companies to erect towers and lines without prior consent of the owners. The law in this regard is already settled by this Court in several cases in favour of the power utilities and the issue is no longer 'res integra'. In fact, the petitioners have no manner of right to oppose the laying of lines and erection of towers in Government land. Based on the law laid down by the Apex Court, the Writ Petition is liable to be dismissed.
Against the order of the learned single Judge, intra
Court appeal was filed W.A.No.303 of 2021. Writ appeal
was dismissed by the Division Bench on 17.09.2021.
12. The similar issue came up before the Apex Court in the
case of Kerala State Electricity Board Vs. Chinamma
Antony2, wherein it was made it clear that the owner of the
land would be entitled to claim compensation on the basis of
various factors. In this regard, the Supreme Court observed
as under:
"9. Both Telegraph lines and electrical lines are required to be drawn over the agricultural lands and/ or other properties belonging to third parties. In drawing such lines, the entire land cannot be acquired but the effect thereof would be diminution of value of the property over which such line is drawn. The Telegraph Act, 1885 provides for the manner in which the amount of compensation is to be computed therefor.
2008 (11) SCC 476
SRSJ WP No.10953 of 2021
10. The situs of the land, the distance between the high voltage electricity line laid there over, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
13. The Hon'ble Apex Court in Power Grid Corporation of
India Limited Vs. Century Textiles and Industries Limited
and others [(2017) 5 SCC 143], considered the aspect of
lying of lines and the permission from the land owner and
also Sec 164 of the Electricity Act 2003 and Rule 3 of Works
of Licensees Rules 2006. Eventually, concluded that no prior
permission is required. Thus, in view of the expressions
referred to supra, the contention of the learned counsel for
the petitioner that without getting permission the authorities
are proceeding with work falls to ground.
14. The other contention of the learned senior counsel is
that compensation is not fixing properly and in fact
compensation has to pay as per provisions of Act 30 of 2013.
Learned senior counsel relied upon the report of committee
for payment of compensation in regard to Right of Way for
SRSJ WP No.10953 of 2021
transmission lines. Government of Andhra Pradesh issued
G.O.Rt.No.83 dated 20.06.2017. The said G.O. deals with
guidelines for payment of compensation towards damages in
regard to Right of Way for transmission lines. District
Collector, in fact, keeping in view the G.O., fixed the
damages. The damage for Right of Way is 10% of value as per
the rate fixed by Sub-Registrar. In view of the same, the
contention of the learned senior counsel for the petitioner
that damages need to fixed as per the provisions of Act 30 of
2013 falls to ground.
15. Learned senior counsel for the petitioner would contend
that DPR was changed. In fact, in the counter affidavit it was
specifically contended that detailed survey was conducted
and the tower schedule was approved on 19.03.2016. Initially
there are no 132/33 KV features in 220 KV substation
Rajampet. The work for erection of 132/33 KV features in
220 KV substation, Rajampet was awarded on 30.05.2017.
Revised detailed survey was carried out and tower schedule
was approved on 08.03.2019. Copy of the revised tower
schedule is also filed along with counter affidavit.
SRSJ WP No.10953 of 2021
16. The alignment, normally finalized taking into
consideration various technical aspects. Thus, change of
alignment, may not technically feasible. As seen from the
record the authorities had taken maximum precaution,
technically, to mitigate the damage to the land of petitioner.
APTRANSCO spent nearly 20 crores on the project and the
project is envisaged in the interest of public meant for
agriculture supply.
17. In view of the discussion supra, this court does not find
any merit in the writ petition and the writ petition is liable to
be dismissed.
18. Accordingly, the Writ Petition is dismissed. No costs.
As a sequel, all the pending miscellaneous applications
shall stand closed.
_________________________ SUBBA REDDY SATTI, J 20th October, 2023
PVD
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!