Citation : 2023 Latest Caselaw 2663 AP
Judgement Date : 1 May, 2023
HIGH COURT OF ANDHRA PRADESH: AMARAVATI
HON'BLE MR. JUSTICE D.V.S.S. SOMAYAJULU
AND
HON'BLE MR.JUSTICE V.SRINIVAS
C.M.A.Nos.1022 & 1027 of 2012
COMMON JUDGMENT: (per D.V.S.S.Somayajulu, J)
Both of these appeals arise out of the order passed by the
Principal District Judge, Nellore in dismissing A.O.P.No.541 of
2007 and in allowing A.O.P.No.762 of 2007.
2. An award dated 30.04.2007 was passed, wherein Claims
Nos.1, 3 and 10 were allowed by the Arbitrator. Challenging the
same, A.O.P.No.762 of 2007 was filed by the State. A.O.P.No.541
of 2007 is filed by the contractor questioning that part of the
award which disallowed the claims. Learned Principal District
Judge, Nellore heard the matter at length and dismissed
A.O.P.No.541 of 2007 by which the disallowed claims were
challenged. The Principal District Judge allowed
A.O.P.No.762 of 2007 and set aside the award in so far as it
2
relates to three claims. Questioning the same, C.M.A.No.1022 of
2012 is filed.
3. Questioning the order in A.O.P.No.541 of 2007,
C.M.A.No.1027 of 2012 is filed.
4. This Court has heard Sri M.V.S.Suresh Kumar, learned
senior counsel for the appellant and learned Government Pleader
for Arbitration.
5. Sri Suresh Kumar argued the matter at length and
submitted that the award passed by the sole Arbitrator on
30.04.2007 is a reasoned award considering all the contentions
raised and also the legal and factual points that were raised. He
points out that only three claims were allowed. He contends that
clear reasons were also assigned for the three claims that were
passed. Therefore, he submits that the trial Court committed an
error in dismissing the A.O.P. Relying upon the leading
judgment in UHL Power Company Limited v. State of
Himachal Pradesh1, learned counsel argues that the scope for
interference in such cases is very limited and yet trial Court
ignored the same. He relies upon paras 16 to 22 of the judgment
1 (2022) 4 SCC 116
3
to argue that there is no perversity in the findings and that the
Arbitrator has taken a clear and plausible view. Therefore, he
submits that the award should not be set aside.
6. In reply to this, learned Government Pleader argues the
matter at length and points out that the learned Arbitrator
committed an error in ignoring the signed documents. It is his
contention that the forwarding slip enclosed to the agreement was
rightly relied upon by the learned trial Judge and that therefore,
the findings of the trial Court should not be upset. Coming to the
interest, he points out that learned Arbitrator overlooked the
specification 69 of the A.P.Detailed Standard Specifications and
awarded the amount towards interest. Therefore, he justifies the
impugned order.
7.COURT: The law on the subject is sufficiently well settled.
8. In a recent judgment reported in Haryana Tourism Ltd. v.
Kandhari Beverages Ltd.,2 the Hon'ble Supreme Court was
dealing with sections 34 and 37 of the Arbitration Act. It was
clearly held that the award can only be set aside if it is (a) contrary
2
(2022) 3 SCC 237
4
to the fundamental policy of Indian law; (b) interest of India; (c)
justice or morality; (d) if it is patently illegal.
9. In UHL Power Company Limited (1 supra) relied on by the
learned senior counsel also, the Hon'ble Supreme Court clearly
held in paras 16 and 17 as follows:
16. As it is, the jurisdiction conferred on courts
under Section 34 of the Arbitration Act is fairly narrow,
when it comes to the scope of an appeal under Section
37 of the Arbitration Act, the jurisdiction of an appellate
court in examining an order, setting aside or refusing to
set aside an award, is all the more circumscribed.
In MMTC Ltd. v. Vedanta Ltd. [MMTC Ltd. v. Vedanta
Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ) 293] , the
reasons for vesting such a limited jurisdiction on the
High Court in exercise of powers under Section 34 of the
Arbitration Act have been explained in the following
words : (SCC pp. 166-67, para 11)
"11. As far as Section 34 is concerned, the position is
well-settled by now that the Court does not sit in appeal
over the arbitral award and may interfere on merits on
the limited ground provided under Section 34(2)(b)(ii) i.e.
if the award is against the public policy of India. As per
the legal position clarified through decisions of this
Court prior to the amendments to the 1996 Act in 2015,
a violation of Indian public policy, in turn, includes a
violation of the fundamental policy of Indian law, a
violation of the interest of India, conflict with justice or
morality, and the existence of patent illegality in the
arbitral award. Additionally, the concept of the
"fundamental policy of Indian law" would cover
compliance with statutes and judicial precedents,
adopting a judicial approach, compliance with the
principles of natural justice,
and Wednesbury [Associated Provincial Picture Houses
Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 (CA)]
5
reasonableness. Furthermore, "patent illegality" itself
has been held to mean contravention of the substantive
law of India, contravention of the 1996 Act, and
contravention of the terms of the contract."
17. A similar view, as stated above, has been taken
by this Court in K. Sugumar v. Hindustan Petroleum
Corpn. Ltd. [K. Sugumar v. Hindustan Petroleum Corpn.
Ltd., (2020) 12 SCC 539] , wherein it has been observed
as follows : (SCC p. 540, para 2)
"2. The contours of the power of the Court under
Section 34 of the Act are too well established to require
any reiteration. Even a bare reading of Section 34 of the
Act indicates the highly constricted power of the civil
court to interfere with an arbitral award. The reason for
this is obvious. When parties have chosen to avail an
alternate mechanism for dispute resolution, they must
be left to reconcile themselves to the wisdom of the
decision of the arbitrator and the role of the court
should be restricted to the bare minimum. Interference
will be justified only in cases of commission of
misconduct by the arbitrator which can find
manifestation in different forms including exercise of
legal perversity by the arbitrator."
10. This Court is therefore analysing the award and the findings
of the Arbitrator vis-à-vis the settled case law.
11. Issue No.1/claim No.1 is the subject matter of dispute. This
dispute is stated as follows in the Award:
'The only dispute is whether the claimant is entitled to
payments for the deviated items at the rate of 19.71% less
than the estimated cost for all the deviated items at the rate of
17% over and above estimated cost on these items. It is an
admitted fact that the respondents have paid to the claimant
at the rate of 19.71% less than the 'estimated cost' whereas the claimant claims at the rate of 17% over and above the estimated cost.'
12. The controversy for the payment centers round the
estimated cost or the estimated value of the contract. According
to the claimant, the estimated value of the contract is Rs.292.88
lakhs and the quoted rate is Rs.426.71 lakhs. This is the issue
which had to be decided by the Arbitrator. After setting out the
pleadings and the controversies, he proceeded to decide the matter
and give his reasons and conclusions from para 36 to 57 of the
award. There is no dispute strictly about the quantum of the
claim or the quantum of the work. The applicable rate is the
issue.
13. The learned Arbitrator rightly noticed that in the tender
notice itself, the estimated cost of the work was indicated as
Rs.292.88 lakhs. This is a figure which was relied upon by all the
contractors. It is a fact that the contractors do not have absolute
access to the site, nor do they have complete access to the
drawings etc. Therefore, in filing their tender, they would rely
upon the estimate that is furnished by the department. These
estimates were also not prepared by anybody's whims and fancies.
They are the result of a study and evaluation by the departmental
Officers. Based on the departments estimates permission is taken
for the tender etc. Therefore, in the opinion of this Court, the
Arbitrator rightly noticed that a tender notice is issued after
working out the value based upon the standard schedule of rates.
14. He also noticed the fact that in the formal agreement,
executed between the parties, the estimate of the work is show as
Rs.292.88 lakhs. The Superintendent Engineer also addressed a
letter to the Executive Engineer stating that the contract has been
approved. The estimated value and contractual value is also
correlated to the learned Arbitrator to the EMD which is payable
at 1.5 %. The Arbitrator, therefore, came to the conclusion that
1.5% of the EMD claim to Rs.4.39 lakhs was paid by the
contractor. The details of the two pay orders are mentioned in the
document. 1.5 % of Rs.292.88 lakhs is Rs.4.39 lakhs. If the
estimated value of the contract was to be treated as
Rs.4,26,71,192.00/- as claimed by the respondent, the Contractor
should have deposited a sum of Rs.6 lakhs and odd and not
Rs.4.39 lakhs. This is the factor which has been relied upon by
the learned Arbitrator. He also noticed in para 45 that in the
revised tenders that were floated, the estimated value of the
contract remained at Rs.292.88 lakhs only. Only in the
forwarding slip, the estimated amount is mentioned as Rs.292.88
lakhs and the contract value is as mentioned as
Rs.4,26,71,192.00/-; that the tendered contract was 19.71 % less
than the estimated value. The contention of the learned counsel
for the respondent is that this forwarding slip is also signed by the
tender. However, the fact remains that the tender/contract has
given an explanation which is accepted by the Arbitrator in paras
27 to 49. In the opinion of this Court, the estimated value is also
typed in the agreement and it is shown as Rs.292.88 lakhs. The
view taken by the learned Arbitrator, in the opinion of this Court,
is neither perverse nor illogical nor does it shock the conscience of
this Court. The approximate value in the tender was clearly
mentioned as Rs.292.88 lakhs. In the letter from the Chief
Engineer to the Contractor, the price was accepted as
Rs.3,42,575/-. Performance security was also demanded along
with the balance EMD and this was also submitted. The
estimated cost is also mentioned in the articles of agreement.
Merely because in the forwarding slip a different figure is
mentioned, it does not lead to inescapable conclusion that this is
a figure agreed upon by the contractor. The learned Arbitrator
sifted through all the documents before coming to this conclusion.
15. In view of the case law cited above, this Court is of the
opinion that the trial Court committed an error in setting aside the
award in so far as it relates to this claim. The contractor relied
upon the representations of the department as contained in their
tender notification itself. On the basis of this estimated value of
the work only, any prudent or reasonable contractor would quote
his rates. The approximate value of the civil work was clearly
indicated as Rs.292.88 lakhs. It is not a case of tender being
floated by the State wherein the figure is mentioned as
approximately Rs.200 to Rs.300 lakhs. The fact that a figure of
Rs.292.88 lakhs was quoted, clearly indicates that some amount
of work has gone into the preparation of an estimate. It is this
figure which will form the basis of any contractor's
valuation/quotation. Thereafter, the said figure was also
mentioned in the typed agreement which is entered into between
the parties. Based on this figure, the contractor quoted price of
Rs.3,42,575/-.
16. In this view of the matter, this Court is of the clear opinion
that the Principal District Judge committed a clear error in
disallowing the claim. The learned Arbitrator, in the opinion of
this Court, considered all the documents in sequence and not
merely the forwarding slip in coming to a conclusion that he did.
The case law relied upon on Ramanath International
Constructions Pvt. Ltd., v. Union of India (2007 (2) ALT 59),
wherein a further judgment of Rajasthan State Mines was
considered, is not really applicable. In the opinion of this Court,
the core issue in this case was the estimated value of the contract
and the rate quoted by the contractor which led to the concluded
agreement. Once these two issues are decided, the rest of the
claim falls into the place.
17. In the opinion of this Court, the view taken by the learned
Arbitrator is a clear view and is more than a plausible view. It is
neither erroneous, perverse nor shocking.
18. As far as claim No.3 is concerned, it is a claim for storage
centage charges. It is no doubt true that the agreement states
that the contractor shall be bound to supply the materials and
also engage watch and ward. The learned Arbitrator did not in the
opinion of this Court award a fancy figure or a figure devoid of
merits. He relied upon the case schedule volume which is marked
as Ex.P.65. The findings based upon this are found in para 71 of
the award. Although a larger amount is claimed, still by relying
upon the cost schedule, the learned Arbitrator worked down the
claim and awarded a sum of Rs.10,24,000/- only. This action is
neither perverse nor arbitrary. It is a plausible view that can also
be taken.
19. Last claim is towards interest. Learned Government Pleader
relied upon preliminary specification 69 of APDSS. However, this
Court notices that the learned Arbitrator relied upon case law
including cases of considering P.S.69 to come to the conclusion
that the Arbitrator can award interest. In the opinion of this
Court, PS.No.69 does not apply to an Arbitrator. The clause is as
follows:
P.S.69: 'Interest on Money due to the Contractor'. (A) No omission by the Executive Engineer or the Sub-divisional Officer to pay the amount due upon certificates shall vitiate or make void the contract, nor shall the contractor be entitled to interest upon any guarantee fund or payments in arrear, nor upon any balance which may on the final settlement of his accounts, be found to be due to him.
20. It is the Arbitrator who is awarding the amounts basing on
the power conferred upon him by section 31 of the Arbitration Act,
96. There is no clause in the contract barring the award of
interest. Therefore, this Court is of the opinion that the Arbitrator
did not commit any error in awarding interest as he did at 10%
per annum; from 31.12.2001 when the defect liability claim come
to an end.
21. Therefore, after considering all the above aspects, this Court
is of the opinion that the lower Court committed an error in
allowing the A.O.P.No.762 of 2007.
22. Therefore, the order of the District Judge dated 23.02.2012
in so far as it relates to setting aside the award and allowing
A.O.P.No.762 of 2007 is set aside. The appellant is entitled to the
amount awarded along with the interest etc., as awarded by the
learned Arbitrator.
23. In so far as C.M.A.No.1027 of 2012 is concerned, after
hearing to the submissions of the learned counsel and the learned
Government Pleader is of the opinion that the Contractor failed to
justify his action. The Arbitrator rightly disallowed this claim.
This Court is of the opinion that the lower Court rightly dismissed
A.O.P.No.541 of 2007.
24. As a result of these findings, C.M.A.No.1022 is allowed and
C.M.A.No.1027 of 2012 is dismissed. No order as to costs.
As a sequel, the miscellaneous petitions if any shall stand
dismissed.
__________________________ D.V.S.S. SOMAYAJULU,J
_______________ V.SRINIVAS,J Date: 01.05.2023 KLP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!