Citation : 2023 Latest Caselaw 3298 AP
Judgement Date : 4 July, 2023
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
AND
HON'BLE SRI JUSTICE B.V.L.N.CHAKRAVARTHI
C.M.A.No.159 of 2023
JUDGMENT: (per Hon'ble D.V.S.S.Somayajulu)
This Civil Miscellaneous Appeal is filed questioning the order
dated 15.04.2023 in I.A.No.88 of 2023 in O.S.No.30 of 2023 passed by
the VI Additional District Judge, Visakhapatnam.
2. The appellants before this Court are the respondents 10 and 11
in the suit O.S.No.30 of 2023. They are questioning the order
mentioned above by which they were restrained under Order 39 Rules
1 and 2 from making any further constructions in the plaint schedule
property.
3. This Court has heard Sri B.Raj Kiran, learned counsel for the
appellants and Sri P.Naga Raju and SKSK.Sarma for the respondents.
4. Learned counsel for the appellants points out that the lower
Court committed a serious error in granting a temporary injunction
restraining the construction in the petition schedule property. It is his
contention that trial Court has not considered the documents or the
pleadings in its proper perspective. He states that the appellants are
constructing in the property which is far more than the petition
schedule property. He states that permission has been obtained for
construction in a total site measuring 7500 square yards. The
development agreement coupled with General Power of Attorney
executed in their favour is dated 18.02.2021 and it deals with the 478
square yards of land and the other extent of the property belongs to
third parties to the proceedings who have also permitted the
appellants for construction. Therefore, he submits that granting of a
blanket order of injunction against further construction is not correct
and contrary to law. He points out that after substantial
constructions were raised, a suit was filed and an injunction was
obtained. It is their contention that on this ground of delay also, the
lower Court committed an error. Relying upon the photographs filed,
learned counsel argues that in view of the substantial constructions
made, a blanket order of injunction should not have been granted. He
also points out that the respondents/plaintiffs also orally agreed for
partition of the property and received consideration. He also relies on
Kishorsinh Ratansinh Jadeja v. Maruti Corporation and others 1.
5. In reply to this, SKSK.Sarma, learned counsel argues that the
suit itself is filed for a partition and for allotment of a share of the
plaintiffs. He contends that under a registered sale deed dated
29.07.2015, the plaintiffs along with defendants 1 to 4 acquired an
extent of 635 square yards. Relying upon the sale deed, he points out
that the land is undivided. In the said undivided bit, defendant Nos.1
(2009 ) 11 SCC 229
and 2 have 158.75 square yards each. Defendant No.3 has 79.37
square yards and defendant No.4 has 79.37 square yards. The
plaintiffs 1 and 2 have 79.37 square yards each. No boundaries are
specified for these extents. The extents are specified but the division
by metes and bounds has not taken place. Contrary to this sale deed,
the development agreement dated 18.10.2021 has been entered into
by defendant Nos.1 to 4 with the developers/appellants. This was
done behind the back of the plaintiffs. Pursuant to the said
development agreement, construction of the building has started.
Learned counsel points out that unilaterally defendant Nos.1 to 4 have
executed the development agreement for what they claim is their share
at 476.24 square yards leaving a certain bit of land as the property
belonging to the plaintiffs. He points out that the division of the
property can only occur after all the parties agreed to a partition, or
pursuant to a decree passed by a Court for partition. In this case, as
there is no consent or a document of partition, a suit is filed for
partition. Learned counsel therefore submits that unilaterally, co-
sharers cannot determine their shares and permit construction
thereon. At best, they could have sold only their undivided share in
the property. The counsel contends that without the consent by the
plaintiffs construction cannot go on. He relies upon the following
cases to argue that the injunction granted is a reasoned order passed
after considering the merits of the matter.
(1) Jose Caetano Vaz v. Julia Leocadia Lucretia Fernandas2
(2) Sabitri Devi and others v. Sri Lakhan @ Ramjiwan Prasad
and others3
(3) Rukmani and others v. H.N.Thirumalai Chettiar 4
(4) Somepalli Govindu v. Madikiri Rajamani and others 5 and
(5) Gangubai Bablya Chaudhary v. Sitaram Bhalchandra
Sukhtankar6
6. COURT: After hearing the submissions, this Court notices that
O.S.No.30 of 2023 is filed for a partition and for allotment of share in
terms of the sale deed dated 29.07.2015. The plaintiffs are claiming
for a partition and delineation of their share pursuant to the
document dated 29.07.2015. Second prayer is for a permanent
injunction. A copy of the sale deed is on the file of this Court. The
contents of the sale deed clearly reveal that the purchasers (plaintiffs
1 and 2 along defendant Nos.1 to 4) purchased a total extent of 635
square yards in Sy.No.47. Boundaries are given in the entire extent
only and not for the individual extents. The extent which belongs to
each of the parties to this deed is described as follows: (1) Defendant
Nos.1 and 2-148.75 square yards each. (2) Defendant Nos.3 and 4
(plaintiffs 1 and 2) 79.37 square yards each.
1969 0 AIR (Goa) 90
2017 AIR (Pat) 85
1985 AIR (Mad) 283
AIR 2023 AP 54
AIR 1983 SC 742
7. It is a fact that the property is not physically divided and only
undivided extents are mentioned. Thereafter, on 18.02.2021 a sale
deed was executed by defendant Nos.1 to 4 alienating 476.24 square
yards of land by defendant Nos.1 to 4 in favour of defendant Nos. 5 to
9. This land is described with boundaries. Defendant Nos.5 to 9
entered into a development agreement on the very same day with
defendant Nos.10 and 11 for developing this bit. Interestingly, in
these documents, 476.24 square yards out of 635 square yards is the
subject matter. Both these documents do not refer to any partition.
They do not also state that the consent of the plaintiffs was given for
alienation of his property or for its development. Plaintiffs have also
not signed on either of these documents as consenting parties.
Unilaterally the defendants seem to have divided and appropriated the
land.
8. An argument was also advanced that the conduct of the
plaintiffs does not entitle them to seek an injunction. As it is argued
that they have allowed construction substantially before filing the suit
and interlocutory application. In the opinion of this Court and in the
circumstances of the present case, the same is not tenable. This
Court agrees with the conclusions and ratio of the judgments relied
upon by the plaintiffs including Jose Caetano Vaz's case and
Rukmani's case (2 and 4 supra). Unless and until the property is
partitioned and/or the share is delineated, construction cannot be
permitted to be made. This would definitely cause prejudice to the
plaintiffs. The case law relied upon by the learned counsel for the
appellant in Kishorsinh Ratansinh Jadeja (1 supra) was a case
where the conduct of a party in sleeping over the matter for
development for a period of 19 years was commented upon. This case
is not a case of inordinate delay. On 08.06.2022, the approved plan
was granted for construction. A lawyers notice was issued on
14.10.2022. This did not evoke a proper response. Thereafter, a suit
was filed on 03.03.2023. Therefore, the delay cannot be said to be
inordinate.
9. This Court also notices that the order impugned is a reasoned
order. The trial Court has considered all the issues that were raised in
proper perspective. It has also noted that in the sale deed dated
18.02.2021, boundaries are given for the property alienated by the
defendant Nos.1 to 4 in favour of defendant Nos.5 to 9 without it being
mentioned that the property has been partitioned either by the deed or
by an understanding. Even with regard to the so called oral partition
and/or agreement of sale also, the trial Court has rightly come to a
conclusion. An oral partition should always be supported by
contemporaneous evidence to show that there was in fact a partition
and it was acted upon. The fact that the said partition or agreement is
not mentioned in any for the documents executed by the defendant
Nos.1 to 4 is also an important factor in the plaintiffs favour.
10. Considering all of the above, this Court is of the opinion that the
impugned order does not suffer from any infirmities. It is a reasoned
order considering the important issues that are raised in their proper
perspective. If the building is allowed to be constructed without the
plaintiffs share being demarcated on the ground in accordance with
law, they will suffer serious loss. The defendants cannot be allowed to
raise constructions. The plaintiffs have more than a prima facie case
in their favour. Greater harm will be caused to them if the
construction is allowed to go on in a site which is not partitioned or
divided and in which plaintiffs may have a share on the ground. The
loss will also be irreparable.
11. This Court is of the opinion that there are no merits of the civil
miscellaneous appeal and the same is therefore dismissed. No order
as to costs. As a sequel, the miscellaneous petitions if any shall stand
dismissed.
__________________________ D.V.S.S. SOMAYAJULU,J
______________________________ B.V.L.N.CHAKRAVARTHI,J
Date: 04.07.2023 KLP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!