Citation : 2023 Latest Caselaw 139 AP
Judgement Date : 6 January, 2023
THE HON'BLE SRI JUSTICE RAVI NATH TILHARI
WRIT PETITION Nos.598 & 599 OF 2023
COMMON JUDGMENT:-
Heard Sri Ghanta Rama Rao, learned senior advocate
assisted by Sri G. Manikhanta, learned counsel for the
petitioner and Sri S. Lakshminarayana Reddy, learned standing
counsel for the respondents 2 and 3.
2. Notice has been accepted by the learned Government
Pleader for Municipal Administration and Urban Development
Authority for the 1st respondent.
3. W.P.No.598 of 2023 has been filed by the petitioner High
Yield Estates Private Limited, represented by its Managing
Director under Article 226 of the Constitution of India,
challenging the notice dated 24.12.2022, issued by the 2nd
respondent under Section 461(1) of the A.P. Municipal
Corporation Act, 1955. Similar notices have been issued to the
petitioner with respect to the different buildings being
constructed by the petitioner, subject matter of the writ petition.
4. W.P.No.599 of 2023 has been filed by the same petitioner
as petitioner No.12 along with 11 other petitioners, to whom the
petitioner No.12 has allotted one flat each, in total 11 flats, out
of 34 flats of Ac.1.60 cents, in Sy.No.195/2A2. The challenge in
this petition is also to the same notices dated 24.12.2022 on the
same subject but given separately to all the petitioners.
5. The subject matter of both the writ petitions being the
same with the consent of the parties counsels both the writ
petitions are being decided by the common judgment.
6. By the impugned notices, the petitioners have been
granted time to show sufficient cause within the specified time
as to why the action of removal, alteration or pulling down of
the building in question be not taken with further direction to
the petitioners to stop construction work forthwith.
7. The petitioners have filed reply to the notices on
02.01.2023, inter alia submitting that the petitioners are not
making unauthorized constructions but have obtained the
building permission on different dates for each building. Along
with the reply the petitioners are said to have filed the copy of
the building permissions as well.
8. Sri Ghanta Rama Rao, learned senior counsel submits
that the notices proceed on the assumption that the petitioners
constructions are unauthorized constructions. He submits that
with respect to each building, on the petitioners applications,
the building permissions having been granted on different dates
in the month of December, 2022. The said building permissions
are still intact and not having been revoked or cancelled under
the statutory provisions of the A.P. Municipal Corporation Act,
1955 (in short, "the Act, 1955") and also there being no
proceedings with respect to any alleged deviations either under
Section 452, or Section 450 of the Act, 1955, the constructions
being raised by the petitioners cannot be said to be
unauthorized. Consequently, the notices issued are without
jurisdiction and the respondent authorities cannot in law direct
the petitioners to stop the construction work.
9. Sri S. Lakshminarayana Reddy, learned standing counsel,
based on the written instructions submits that though the
building permission was granted online but such grant is
subject to the terms and conditions specified in the building
permit itself. One of those conditions is in para No.16 which
inter alia provides that the permission was given based on the
inputs of pages, documents and drawings provided by the
applicant for such building permission. The final approval of
proceedings was subject to verification of the report and
documents of concerned officials including the site visit report
and any deviation identified was to lead modification/rejection
of the proceedings for building permission.
10. Sri S. Lakshminarayana Reddy further submits that the
A.P. Building Rules, 2017 (in short, "the Rules, 2017") under
Rule 3(22)(c) specifically provides for post verification of building
permissions. Shortfall notices were given on 29.12.2022
indicating the shortfall being inter alia (1) that there is no
approach road left and (2) layout open space charges were not
paid. But, the shortfall was not removed and any reply was also
not filed.
11. Sri Ghanta Rama Rao, learned senior advocate submits
that the shortfall notices have not been served to the petitioners
to which learned standing counsel for the Corporation submits
that the shortfall notices were sent to the login of the Licensed
Technical Persons (in short LTP) through which the building
permission was applied online. Consequently, he submits that
there is no illegality in issuing the impugned notices which
cannot be said to be without jurisdiction.
12. On a specific query as to whether in the shortfall notices
some time has been provided to remove the shortfall or/and to
file replies, learned standing counsel submits that it has not
been so specified but if the reply is filed to those notices within
a reasonable time, the same shall also be considered by the
competent authority, along with the petitioners' reply already
submitted to the impugned notices.
13. I have considered the submissions advanced by the
learned counsels for the parties and perused the material on
record.
14. The submission of the learned senior advocate is that the
construction is being raised after obtaining the building
permission which is not yet revoked or cancelled and the
deviations, if any, have also not been specified in the impugned
notices, and further as any notice under Section 450 or Section
452 of the Act, 1955, has not been given, the constructions
cannot be termed to be unauthorized. Consequently the notice
is without jurisdiction.
15. Rule 3 of the Rules, 2017, which provides for a stream
line of building plan approvals, lays down the procedural
requirements for obtaining building permission. Rule 3, Sub
Rule 10, Clause (i) inter alia provides that every person who
intends to erect, re-erect or make alteration in any place in a
building or demolition of any building shall submit an
application for building permission in writing and/or through
online as prescribed, to the concerned authority, of his intention
in the prescribed proforma. Clause (a) of sub Rule (22) of Rule,
3, defines Online Building Permission Management System
which means the Implementation of Information and
Communication Technology (ICT) enabled Integrated Online
Building Permission Management System where permission for
any category of buildings will be issued. Clause (b) provides
that the sanction of building permission of all categories of the
building including high raise building which are permissible in
normal course as per the zoning regulations and as per the
rules and with all prescribed documents and plans shall be
done and through the Online Building permission Management
System, by the respective sanctioning authority, except in case
of Gram Panchayat falling in the areas specified under Clause
(b) itself.
16. Rule 3 sub Rule (22) (c) provides for post verification of
building permissions, according to this provision, after sanction
of the building permissions through the Online Building
Permission Management System, the respective local
authorities, competent authority and sanctioning authority,
shall examine and scrutinize the building permission as per the
categories given, in detail and verify the compliance of the legal
provisions, the land uses as per the Master Plan/General Town
Planning, Schemes, layouts, relevant rules and regulations as
applicable and wherever there has been any false submission,
misrepresentation of material facts in the application on which
the building permission was sanctioned etc., it shall be invalid
and shall be deemed to be cancelled. It further provides that
the concerned authorities shall be entitled to take appropriate
action against such Licensed Technical Personnel and any
person whoever is responsible as also against the construction.
17. From the aforesaid, it is evident that the application for
building permission is to be submitted through online and the
permission shall be issued through the Online Building
Permission Management System. After sanctioning of the
building permission, the post verification of the building
permission is legally permissible under the Building Rules,
2017.
18. So, the building permission is subject to the post
verification and in case of violation of the relevant rules, the
regulations or non compliance with the provisions of land uses
or false submission, misrepresentation of material facts etc., the
building permission shall be invalid and shall be deemed to be
cancelled.
19. The building permission itself contained the condition in
para No.16 that the same was subject to verification.
20. In view of the above legal provisions the submission of the
learned senior advocate that once the Building Permission has
been granted and so long as the building permission is not
cancelled, the construction cannot be directed to be stopped by
saying it to be unauthorized is not acceptable. Rule 3(22)(c) of
the Rules, 2017 specifically provides that on post verification, in
view of the shortcomings etc., or non compliance with the
provisions as mentioned in such rule, the building permission
shall be invalid and deemed to be cancelled.
21. In the present case, the petitioners have been issued the
impugned notices to which they have already filed their reply.
22. The shortfall notices have also been uploaded/sent to the
login of the licensed Technical Persons.
23. It is open to the petitioners or/and the person competent
under law under liability to remove the shortcoming or/and to
submit their reply raising such objections as may be prescribed
before the competent authority.
24. This court is of the considered view that in the facts and
circumstances of the case as discussed above and in the light of
the legal provisions, it cannot be said that the show cause
notice is without jurisdiction.
25. There is no challenge to the impugned notices on the
ground of patent lack of jurisdiction in the authority issuing the
notices.
26. The Court does not find any legal ground to interfere with
the show cause notices in the exercise of writ jurisdiction.
27. In the result, the writ petition is being disposed of finally
in the following terms:
i) No case for interference with the impugned notices, is made out.
ii) The 2nd respondent- Zonal Commissioner, Zone-
VIII, Greater Visakhapatnam Municipal
Corporation, Visakhapatnam/the competent
authority, shall consider the petitioners reply to the impugned show cause notices and pass appropriate orders in accordance with law.
iii) The petitioners are granted liberty to file reply to the shortfall notices already uploaded on the Login of L.T.P, within a period of two weeks from the date of receipt of copy of this order.
iv) The competent authority shall consider the reply to the shortfall notices, if so filed by the petitioners, in accordance with law
v) Let the entire exercise be completed expeditiously and preferably within a period of six weeks.
28. No order as to costs.
As a sequel thereto, miscellaneous petitions, if any
pending, shall also stand closed.
__________________________ RAVI NATH TILHARI,J Date:06.01.2023.
Note:
Issue CC by tomorrow:
B/o Gk
THE HON'BLE SRI JUSTICE RAVI NATH TILHARI
WRIT PETITION Nos.598 & 599 OF 2023
Date:06.01.2023 Gk.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!