Citation : 2023 Latest Caselaw 1137 AP
Judgement Date : 24 February, 2023
THE HON'BLE SRI JUSTICE CHEEKATI MANAVENDRANATH ROY
WRIT PETITION No.4596 of 2023
ORDER:-
This Writ Petition for a mandamus is filed to declare the
action of respondent Nos.2 and 3 in issuing the impugned Stop
Work Order, dated 15.02.2023, under Section 450 of the HMC
Act, 1955, (for short "the Act") as illegal and arbitrary and
consequently prayed to set aside the Stop Work Order.
2. Heard learned counsel for the petitioner, learned
Assistant Government Pleader for Municipal Administration &
Urban Development appearing for respondent No.1 and Sri K.
Madhava Reddy, learned Standing Counsel for GVMC appearing
for respondent Nos.2 and 3.
3. The petitioner is a partnership firm in the name and style
"M/s Hayagreeva Farms & Developers" which is a registered
firm under the Partnership Act. Earlier the State has conveyed
the land in an extent of Ac.12.51 cents in Endada Village,
Visakhapatnam Rural, under a registered deed of conveyance,
dated 04.10.2010 to the petitioner. Possession of the land was
also delivered to the petitioner under the aforesaid deed.
Thereafter, it appears that the petitioner has obtained a building
permission from respondent No.2 and has been constructing
villas and apartments in a gated community. Subsequently, the
State has initiated proceedings to resume the land in question.
The petitioner has challenged the same before the Common
High Court for the State of Telangana and Andhra Pradesh in
W.P.Nos.36413 of 2014 and W.P.No.26653 of 2015. Both the
Writ Petitions were allowed as per order, dated 19.12.2017,
setting aside the proceedings of the District Collector resuming
the said land and directed the respondents therein to restore
the possession of the land to the petitioner and also further
directed the District Collector to issue NOC to the petitioner.
The State has challenged the said order of the learned Single
Judge before a Division Bench. The said Writ Appeal in
W.A.Nos.363 and 370 of 2018 came to be dismissed confirming
the order of the learned Single Judge and also confirming the
direction to issue NOC. The Division Bench incidentally held
that mere grant of NOC by the District Collector does not
obligate the GVMC to grant permission for construction, as any
application, seeking permission for construction, is required to
be examined by the municipal authorities in accordance with
the provisions of GHMC Act.
4. After the said litigation came to an end, pursuant to the
above direction, it appears that NOC was issued to the
petitioner and building permission was also granted by the 2nd
respondent for construction of the said villas and apartments.
While the said construction is in process, earlier notice under
Section 450 of the Act was issued to the petitioner to stop work
by pointing out certain shortfalls. That was again questioned by
the petitioner before this Court in W.P.No.194 of 2022.
Considering the earlier judgment of High Court of Telangana
rendered in Kommareddy Sravan Kumar v. State of
Telangana1 wherein it is held that as per settled law that as
long as permission granted in favour of a party intact, there
cannot be any direction, pending enquiry under Section 450 of
the Act to stop construction, this Court has disposed of the said
Writ Petition with a direction to respondent No.2 therein to
consider the explanation submitted by the petitioner to the
show cause notice issued by the municipal authorities and pass
appropriate orders according to law within two weeks and till
the said explanation is considered and final orders are passed,
the Court ordered for suspension of the Stop Work Order.
Further, the Court held that if the petitioner proceeds with any
further construction, it will be at his own peril and ultimately, if
the permission is rejected by the Municipal Corporation, that
the Municipal Corporation is at liberty to demolish the
construction of the building by following due process of law.
5. It appears that pursuant to the said direction of this
Court, the explanation of the petitioner was considered and final
order was passed, which is now placed at page No.212 of the
material papers of the Writ Petition. According to learned
counsel for the petitioner, the final order is vague and it does
not specifically hold that there was any shortfall in the
construction by deviating from the building permission.
2020 SCC OnLine TS 2907
6. While so, again the impugned notice under Section 450 of
the Act to stop work came to be passed by respondent No.2 on
two grounds. i) that NOC from the District Collector is not
placed on record and ii) that the petitioner has to provide 60 ft.
road as per the master plan, dated 08.11.2021.
7. As regards the first ground of producing NOC is
concerned, it is stated that the petitioner has already produced
NOC that was issued by District Collector on 08.06.2018 itself.
Further the Division Bench of this Court while disposing of the
Writ Appeal, clearly held that mere issuance of NOC does not
obligate the Corporation from considering the application of the
building permission. Therefore, prima facie the said ground is
not a valid ground for issuance of Stop Work Order. It does not
amount to violation of building permission. As regards the
second ground is concerned, the very issuance of notice under
Section 450 of the Act to stop work suffers from the same
infirmity as pointed by this Court in W.P.No.194 of 2022. This
Court already held as discussed supra on the basis of the law
laid down in Kommareddy Sravan Kumar v. State of
Telangana2 that as per settled law that as long as permission
granted in favour of the party is intact that there cannot be any
direction pending inquiry under Section 450 of the Act to stop
the construction. Therefore, the impugned notice suffers from
2020 SCC OnLine TS 2907
the said infirmity as pointed out earlier in the previous order
passed in the Writ Petition.
8. In the said facts and circumstances of the case, this Writ
Petition is disposed of with a direction to the petitioner to
submit his explanation to the impugned notice within two weeks
from the date of this order. After the said explanation is
submitted, respondent No.2 is directed to consider the
explanation and pass a final order on it within three weeks from
the date of submitting the said explanation. Till the said
exercise is completed as directed supra, the impugned notice
under Section 450 of the Act to stop work, is suspended. But it
is made clear that any further construction by the petitioner
would be subject to the final order that may be passed by
respondent No.2 and it would be at the own peril of the
petitioner. No costs.
Miscellaneous petitions, if any pending, in the Writ
Petition, shall stand closed.
______________________________________________ JUSTICE CHEEKATI MANAVENDRANATH ROY
Date: 24.02.2023
Note: Issue CC by 27.02.2023 B/o AKN
THE HON'BLE SRI JUSTICE CHEEKATI MANAVENDRANATH ROY
WRIT PETITION No. 4596 of 2023
Date: 24-02-2023
AKN
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!