ORDER:
The petitioner had executed the contract for
upgradation of road from Edulapalem to Konam upto BT
standards in Paderu Mandal of Visakhapatnam District, vide
Agreement No.189/2018-19 dated 12.11.2018. As the
petitioner was not paid his dues amounting to
Rs.40,78,389/-, he has approached this Court by way of the
present writ petition.
2. A learned Single Judge of this Court, in similar
Circumstances, after considering the earlier orders of this
Court, by an order dated 08.02.2022 in W.P.No.3074 of 2022,
had directed that the respondents should pay the principal
amount of the bill raised by the petitioner therein while
leaving it open to the petitioner to agitate his right for
interest.
3. In the said circumstances and following the said
judgment, this Writ Petition is disposed, with a direction to
the respondents to finalize the amounts payable to the
petitioner within a period of three weeks from today and in
any event to pay the amounts due to the petitioner within a
period of six weeks thereafter.
4. Needless to say, it would be open to the petitioner
to agitate his rights for payment of interest in an appropriate
forum. There shall be no order as to costs.
As a sequel, pending miscellaneous petitions, if any,
shall stand closed.
____________________________ R. RAGHUNANDAN RAO, J 23.02.2023 MJA
HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO
WRIT PETITION No.2434 of 2023
23.02.2023
MJA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!