Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Shiva Chemicals vs The Government Of India
2022 Latest Caselaw 7225 AP

Citation : 2022 Latest Caselaw 7225 AP
Judgement Date : 20 September, 2022

Andhra Pradesh High Court - Amravati
M/S. Shiva Chemicals vs The Government Of India on 20 September, 2022
           HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO

                        W.P.No.11616 of 2021

ORDER:

The petitioner is in the business of manufacturing of paints, and

supply of painting services. He was registered as a vendor with the 2 nd

respondent-Corporation with vendor Code No.200372 for the past 10

years.

2. The case of the petitioner is as follows: the petitioner had

been awarded a contract bearing No.4410003330, on 24.07.2019 by the

2nd respondent-Corporation. This contract was for carrying out repairs of

various structures in SMS-1 area for a value of Rs.70,00,000/-. This work

was to be started from 01.09.2019 and to be completed by 01.08.2020.

The petitioner had taken immediate steps for commencement of execution

of work. However, the work could not be started because the Engineer in

Chief had not processed the application of the petitioner for issuance of

gate passes to the persons, who would have to carry out the work. The

the Engineer in Chief had, in fact, directed the petitioner to give the

names of the workers who were already working on other contracts, given

to the petitioner by the respondent-corporation. Thereafter, the petitioner

submitted a fresh application with names of 9 existing workers. Due to the

said delay, work could be commenced only from November, 2019. During

the course of the work, the petitioner was called upon to complete other

works on priority basis, and therefore, the execution of the work covered 2 RRR,J W.P.No.11616 of 2021

by the above contract got delayed. While the matters stood thus, the work

had to stop on account of the Covid-19 pandemic from March, 2020.

3. The petitioner sought extension of the contract and the said

extension was granted, from 01.08.2020 to 13.09.2020 to 14.09.2020 to

31.01.2021 and thereafter, till 30.04.2021. However, only 50% of the

work had been completed by the extended deadline and the petitioner

sought further extension of three more months along with late fee to

complete the contract. Respondents 2 to 4 had not shown any inclination

to give further extension and on the contrary issued show cause notice on

05.04.2021 to which the petitioner replied on 19.04.2021. Thereafter, the

impugned final order bearing reference No.VSP/WC/Sted.2021/

4410003330/edak-331 dated 25.05.2021 has been passed debarring the

petitioner from entering into the future business with the respondent-

corporation, and canceling the registration of the vendor code of the

petitioner and completion of the balance quantities in the above contract

at the risk and cost of the petitioner.

4. The petitioner has approached this Court impugning the

above order on the ground that the petitioner was unable to complete the

contract on account of the non-cooperation of the Engineer in Chief of the

respondent-corporation and the subsequent Covid-19 pandemic and the

restrictions imposed by the authorities due to this pandemic. The

petitioner submits that the entire business of the petitioner is executing

contracts with the respondent-corporation and cancellation of the vendor 3 RRR,J W.P.No.11616 of 2021

code of the petitioner as well as barring the petitioner from conducting

business with the respondent-corporation for a period of two years would

effectively take away the livelihood of the petitioner and as such would be

an illegal and arbitrary order.

5. The respondent-corporation had filed a counter affidavit

stating that the value of the contract is not Rs.70,00,000/- but

Rs.70,49,973/-. The respondent-corporation denies the allegation that the

Engineer in Chief had not granted temporary gate passes expeditiously. It

is stated that an application for gate passes was filed on 05.09.2019 and

the same was issued on 17.09.2019 for nine workers. However, these

workers attended the training programme for executing this work only on

30.10.2019 and actual work was commenced by only 8 workers from

22.11.2019. It is further stated that apart from this application, the

petitioner has applied for 4 additional passes only on 11.07.2020 and the

same was approved on the very same day. But the petitioner did not

collect the passes till 30.07.2020. However, no workers were engaged

after these gate passes had been issued and the petitioner himself had

sought cancellation of these passes on 29.09.2020. Thereafter, the

petitioner again applied for additional gate passes for 9 workers on

01.10.2020, which was approved on the same day. In the circumstances,

the contention that the petitioner was not able to take up the work on

account of the non-availability of gate passes for the workers is incorrect.

                                     4                                RRR,J
                                                    W.P.No.11616 of 2021


6. The contention of the petitioner that the workers engaged

for this contract had to be redeployed at the direction of the Engineer in

Chief is answered by the respondent-corporation by stating that Clause

2.3 of the contract itself provided a right to the Engineer to direct the

petitioner to redeploy the workers depending on the priority of the work.

The counter states that the painting of slag yard was critical for the unit

and therefore the said direction to redeploy does not in any manner

violate the terms of the contract. It is further stated that the contract

period was extended for a period of nine months, on the application of the

petitioner after the Covid-19 lockdown period despite which the petitioner

could only complete only about 49% of the work as of 30.04.2021.

7. It is submitted that in the circumstances, impugned order of

the respondent-corporation is in accordance with Clause 12.0(b) of the

tender document and Clause 14.1(c) and (d) of the General Conditions of

Contract, which permits such termination.

8. Smt. S.A.V. Ratnam, learned counsel for the petitioner,

would submit that the petitioner has four running contracts, including the

cancelled contract and the impugned order affects the execution of the

workers of the other three contracts and the same is impermissible and

arbitrary. She further submits that the respondent-corporation after taking

into account the past performance of the petitioner should have taken a

lenient view in the matter keeping in view the fact of the Covid-19

pandemic. She submits that termination of contract and other penalties 5 RRR,J W.P.No.11616 of 2021

imposed in the impugned order, are clearly disproportionate to the alleged

breach of contract and requires to be set aside.

9. Sri V. Subrahmanyam, learned Standing Counsel appearing

for the respondents 2 to 4 would point out that the petitioner was unable

to complete the contract despite extension of about nine months after the

Covid-19 lockdown period and there is no reason why the terms of the

tender document and general conditions of contract cannot be enforced.

He relies upon the judgments of this Court dated 01.09.2021 in

W.P.No.15385 of 2021; judgment dated 07.10.2020 in W.P.No.10241 of

2020; and judgment dated 19.04.2022 in W.P.No.16594 of 2020 to

contend that the writ petitions raising similar challenges had been rejected

by this Court.

10. The challenge raised in the present writ petition, relates to a

contractual matter. The scope of judicial review in such matters is

restricted to the extent of ascertaining whether the action of the

respondent(s) has been unfair, arbitrary and violative of the fundamental

rights of the petitioner. In the present case, no such situation has been

made out by the writ petitioner.

11. Shorn of the details, the essential fact is that the petitioner

was granted one year's time to complete the contract by 01.08.2020. The

petitioner was granted an extension of nine months up to 31.04.2021 to

complete the contract. Though the petitioner raises some complaints of

delay on account of the non-issuance of gate passes, the said delay, even 6 RRR,J W.P.No.11616 of 2021

if it were to be put on the respondents, is more than adequately

compensated by the extension of nine months given by the respondent-

corporation. In such a situation, the action of the respondent-corporation

in invoking the terms of the contract, as contained in the tender and

general conditions of contract, cannot be faulted.

12. Sri V. Subrahmanyam, learned Standing Counsel reiterates

the pleadings in the counter that the impugned order does not in any

manner affect the remaining three contracts in the hands of the petitioner

and the same are being continued.

13. In the circumstances, no case has been made out for this

Court to interfere with the writ petition. Accordingly this writ petition is

dismissed. There shall be no order as to costs. As a sequel, pending

miscellaneous petitions, if any, shall stand closed.

_________________________ R. RAGHUNANDAN RAO, J.

20th September, 2022 Js.

                          7                            RRR,J
                                       W.P.No.11616 of 2021


      HON'BLE SRI JUSTICE R. RAGHUNANDAN RAO




               W.P.No.11616 of 2021




                20th September, 2022
Js.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter