Citation : 2022 Latest Caselaw 8014 AP
Judgement Date : 21 October, 2022
HON'BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION Nos. 29574, 29575, 29587, 29591, 29603, 29608,
29615, 29689, 29699, 30882, 30958, 33833, 33838, 33860, 33861,
33865 and 33839 of 2015
COMMON ORDER:
Since all these writ petitions are identical in nature and as the
issues involved in these cases are also similar, this Court deems it
appropriate to dispose of all these writ petitions by way of this
common order.
2. Heard learned counsel for the petitioners and learned
Government Pleader for Irrigation appearing for the respondents.
3. For the sake of convenience and to avoid ambiguity in the
discussion, the facts in W.P.No.29574 of 2015 are taken into
consideration as under:
i) This writ petition is filed to declare the action of respondent
Nos.2 and 3 in not considering the representation of the petitioner
dated 14.08.2015 for payment of withhold amount in respect of the
work done by the petitioner i.e., temporary protection to close the
breach on Appanna Tank, near Vedurupaka village, Gokavaram
Mandal, East Godavari District, as illegal and arbitrary.
NV,J W.P.No.29574 of 2015 & batch
ii) It is the case of the petitioner that several tanks in
Korukonda and Gokavaram Mandals of East Godavari District
were breached due to Neelam Cyclone during the year 2012. All
the minor and major irrigation tanks and canal bunds were
damaged/breached and the storage water was flowing from all the
breached/damaged tanks. Then, the respondent authorities have
identified 243 works in respect of all the tanks and canals in these
two Mandals which are to be arrested on war footing. The 2nd
respondent due to urgency and to protect the storage of water in all
the tanks entrusted works on nomination basis to close the breaches
on emergency basis. The petitioner was allotted some of the
works, one of the works is to provide temporary protection to close
the breaches to the Appanna Tank, Vedurupaka Village,
Gokavaram Mandal, East Godavari District vide agreement
No.389/2012-13 dated 22.02.2013 with an estimated cost of the
work is Rs.1,50,000/-. The petitioner had completed the work
within the stipulated time and the same was recorded in the
measurements book maintained by the Assistant Engineer,
Godavari Central Division, Dowlaiswaram. Though respondent
NV,J W.P.No.29574 of 2015 & batch
Nos.2 and 3 were satisfied with the work executed by the
petitioner, the 2nd respondent withhold an amount of Rs.43,606/- on
the ground that an enquiry by the Vigilance Department is pending.
Then, the petitioner submitted a representation dated 14.08.2015 to
respondent Nos.2 and 3 seeking payment of the withhold amount
along with EMD. As there was no positive response from the
respondents, the petitioner filed the present writ petition.
iii) The 2nd respondent filed a counter affidavit admitting the
entrustment of 243 works to various contractors to close the
breaches of tanks within 45 days and the works were completed in
the year 2012 itself. It is stated that on a complaint put forth by
one Madineedi Bala Gangadhara Chowdary and others, the
Vigilance & Enforcement Department conducted a discreet enquiry
regarding 75 works out of 243 works and submitted a report stating
that some fraud was taken place and a proposal was made to
recover the amounts from the contractors. The 2nd respondent was
instructed to conduct an enquiry on the remaining 168 works for
finalising the payment of bills to the contractors. Basing on the
report of the Vigilance & Enforcement Department, the
NV,J W.P.No.29574 of 2015 & batch
Government issued a Memo dated 16.07.2014 instructing the
concerned authority to recover the amounts from the contractors.
The balance 168 works cannot be inspected at this stage and it is
highly impossible to establish whether the works were executed or
not and about the quality of works, because all the works are urgent
in nature and time bounded and subsequent to Neelam Cyclone in
the year 2012, many cyclones caused much loss to the same
irrigation sources and repairs were also carried out. In view of the
above ground position, a report was submitted to the higher
officials for further instructions/permission with regard to the
release of withhold amounts to the contractors. The orders are
awaited and soon after receipt of further instructions, action will be
taken.
4. The facts in all the writ petitions are similar and the 2 nd
respondent filed counter affidavits in all the writ petitions on
similar lines. Hence, it is not necessary to discuss again the
averments in the other writ affidavits as well as in the other counter
affidavits.
NV,J W.P.No.29574 of 2015 & batch
5. Learned counsel for the petitioners would contend that the
entire works were completed by the petitioners as per the terms of
the agreement and it was admitted by the respondent authorities.
However, the respondent authorities withhold the amounts due to
the petitioners only on the ground that an enquiry by the Vigilance
Department in respect of other works is pending. The learned
counsel would also contend that without conducting any enquiry or
inspection, the amounts payable to the petitioners cannot be
withheld for a longer period. The learned counsel would further
contend that non-payment of the withhold amounts by the
respondents even after lapse of nearly a decade after completion of
the works, is nothing but depriving the petitioners legitimate
entitlement of the balance amounts and it reveals the dereliction of
duties and negligence on the part of the respondents. The learned
counsel would also contend that such non-payment of money is
clearly arbitrary and high-handed requiring the interference of this
Court. The learned counsel relied on the judgment of a learned
Single Judge of this Court in Rayapureddy Srinivasa Rao and
others vs. Government of Andhra Pradesh, rep. by its Principal
NV,J W.P.No.29574 of 2015 & batch
Secretary to Government and others and batch1 wherein it is held
that non-payment of dues is arbitrary and that such dues need to be
cleared by the respondents at the earliest. He, therefore, prays to
allow the writ petitions by awarding interest for the fault of the
respondents.
6. Learned Government Pleader for Irrigation appearing for the
respondents would submit that the respondent authorities received
complaints against the works allotted to the contractors alleging
that some works were not at all grounded and some works were
stopped in the middle. In view of the same, the 1 st respondent took
a decision to conduct an enquiry by the Vigilance and Enforcement
Department. Pursuant thereto, the Vigilance and Enforcement
Department conducted an enquiry in respect of 75 works out of 243
works. As per the enquiry report dated 30.10.2013, in respect of
some of the works, excess amounts were paid and charges were
recorded more than the actual charges and it was suggested to
recover an amount of Rs.68,68,492/- towards excess quantities of
sand bags, casuarinas poles and casuarinas beams and
2021 SCC Online AP 3084
NV,J W.P.No.29574 of 2015 & batch
Rs.12,58,810/- towards usage of earth filled bags instead of sand
filled bags from the contractors concerned. In the said report, it is
also recommended to conduct an enquiry in respect of the
remaining 168 works. Finally, the 2nd respondent addressed a letter
dated 10.11.2015 to the 3rd respondent stating that the balance 168
works cannot be inspected at this stage and it is highly impossible
to establish whether the works were executed or not and about the
quality of works, because all the works are urgent in nature and
time bounded and subsequent to Neelam Cyclone in the year 2012,
many cyclones caused much loss to the same irrigation sources and
repairs were also carried out. It is also stated that all the bills were
paid to an extent of 70% and the balance amounts of the bills were
withheld by the then Executive Engineer, Godavari Central
Division, Dowlaiswaram. Accordingly, the 2nd respondent
requested the 3rd respondent to obtain instructions from the higher
authorities and take further action to release the withheld amounts
to the respective contractors.
7. The admitted facts are that the works were entrusted by the
2nd respondent to the petitioners and to that effect, they entered into
NV,J W.P.No.29574 of 2015 & batch
agreements and the works were completed within the stipulated
period of 45 days. All the bills were paid only to an extent of 70%
and the balance amounts of the bills were withheld by the 2nd
respondent due to pendency of vigilance enquiry. Out of 243
works, in respect of 75 works, enquiry was conducted and as per
the enquiry report of the Vigilance and Enforcement Department
dated 30.10.2013, in respect of the remaining 168 works, a
recommendation was made for enquiry.
8. Further, in his letter dated 10.11.2015 addressed to the 3rd
respondent, the 2nd respondent stated that the balance 168 works
cannot be inspected and it is highly impossible to establish whether
the works were executed or not at this stage, because all the works
are urgent in nature and time bounded and subsequent to Neelam
Cyclone in the year 2012, many cyclones caused much loss to the
irrigation sources and repairs were also carried out.
9. In Rayapureddy Srinivasa Rao (1 supra), a learned Single
Judge of this Court held as under:
NV,J W.P.No.29574 of 2015 & batch
"13) The Hon‟ble Apex Court in ABL International Limited v. Export Credit Guarantee Corpn. of India Ltd ((2004) 3 SCC 553) has observed thus:
"19. Therefore, it is clear from the above enunciation of law that merely because one of the parties to the litigation raises a dispute in regard to the facts of the case, the court entertaining such petition under Article 226 of the Constitution is not always bound to relegate the parties to a suit. In the above case of Gunwant Kaur [(1969) 3 SCC 769], this Court even went to the extent of holding that in a writ petition, if the facts require, even oral evidence can be taken. This clearly shows that in an appropriate case, the writ court has the jurisdiction to entertain a writ petition involving disputed questions of fact and there is no absolute bar for entertaining a writ petition even if the same arises out of a contractual obligation and/or involves some disputed questions of fact".
While summing up the conclusions in the aforesaid case, the Apex Court concluded thus:
"27. From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.
NV,J W.P.No.29574 of 2015 & batch
(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable.
14) A Division Bench of the High Court of Telangana at Hyderabad, by following the law declared by the Apex Court in ABL International Limited and Popatrao Vyankatrao Patil (2020 SCC Online SC 291), rejected the contention of the respondents that the Writ Petition was not maintainable in contractual matters.
15) The High Court of Andhra Pradesh in Mutyala Veera Venkata Satyanarayana vs. State of Andhra Pradesh (2021 SCC Online AP 1410) at Amaravati while dealing with the batch of writ petitions filed for claiming payments for supplying materials to the Panchayat under the Mahatma Gandhi National Rural Employment Guarantee Act, 2005, this Court held as under:
"Therefore, in view of the settled law and keeping in mind the purpose for which the legislation is enacted, this Court has to hold that there is a public element involved in this and that it is not a pure case of the State entering into a commercial contract.
This Court further held that apart from this when State or State instrumentalities act in an arbitrary manner or failed to
NV,J W.P.No.29574 of 2015 & batch
act within time the Writ Court does have jurisdiction to entertain the matter."
52) In Madras Port Trust v. Hymanshu International ((1979) 4 SCC 176) , the Apex Court held:
"2. ... It is high time that Governments and public authorities adopt the practice of not relying upon technical pleas for the purpose of defeating legitimate claims of citizens and do what is fair and just to the citizens. Of course, if a Government or a 5 [(1979) 4 SCC 176] 41 public authority takes up a technical plea, the Court has to decide it and if the plea is well founded, it has to be upheld by the court, but what we feel is that such a plea should not ordinarily be taken up by a Government or a public authority, unless of course the claim is not well founded and by reason of delay in filing it, the evidence for the purpose of resisting such a claim has become unavailable."
55) In Dilbagh Rai Jarry v. Union of India ((1974) 3 SCC 554: 1974 SCC (L&S) 89) , the Apex Court extracted with approval the following statement [from an earlier decision of the Kerala High Court (P.P. Abubacker case [Ed.: P.P. Abubacker v. Union of India, AIR 1972 Ker 103 : ILR (1971) 2 Ker 490 : 1971 Ker LJ 723], AIR pp. 107-08, para 5)]: (SCC p. 562, para 25)
"25. ... „5. ... The State, under our Constitution, undertakes economic activities in a vast and widening public sector and
NV,J W.P.No.29574 of 2015 & batch
inevitably gets involved in disputes with private individuals. But it must be remembered that the State is no ordinary party trying to win a case against one of its own citizens by hook or by crook; for the State's interest is to meet honest claims, vindicate a substantial defence and never to score a technical point or overreach a weaker party to avoid a just liability or secure an unfair advantage, simply because legal devices provide such an opportunity. The State is a virtuous litigant and looks with unconcern on immoral forensic successes so that if on the merits the case is weak, Government shows a willingness to settle the dispute regardless of prestige and other lesser motivations which move private parties to fight in court. The layout on litigation costs and executive time by the State and its agencies is so staggering these days because of the large amount of litigation in which it is involved that a positive and wholesome policy of cutting back on the volume of law suits by the twin methods of not being tempted into forensic showdowns where a reasonable adjustment is feasible and ever offering to extinguish a pending proceeding on just terms, giving the legal mentors of Government some initiative and authority in this behalf. I am not indulging in any judicial homily but only echoing the dynamic national policy on State litigation evolved at a Conference of Law Ministers of India way back in 1957."
56) As per the contention of the State Government, payments are not made due to pendency of vigilance enquiry against the works executed between 01.10.2018 to 31.05.2019. Though
NV,J W.P.No.29574 of 2015 & batch
the State Government Officers failed to place correct information for all these days about the status of the alleged vigilance enquiry, now it is clear by the affidavit filed by the 10th respondent (Central Government) and the statement made by the Chief Secretary, Government of Andhra Pradesh, before the Court that the said vigilance enquiry is concluded on 26.10.2020. The State Government at-least after completion of the vigilance enquiry ought to have made payments to the petitioners by clearing their bills. But, without making payments, even after filing of the writ petitions before the Court, the State Government contended that payments could not be made due to pendency of the enquiry against the petitioners."
10. In view of the above factual background and the citation
relied on by the learned counsel for the petitioners, this Court is of
the opinion that withholding of the balance amounts by the
respondents after execution of the works and after lapse of a
decade without there being any valid reasons, is illegal and
arbitrary and the remaining amounts as admitted by the
respondents shall be paid along with interest and EMD to the
petitioners and all the writ petitions are liable to be allowed.
NV,J W.P.No.29574 of 2015 & batch
11. Accordingly, all the writ petitions are allowed and the
respondents are directed to release the withhold amounts to the
petitioners along with EMD and interest @ 9% p.a. from the date
of report of the Vigilance & Enforcement Department dated
30.10.2013, within a period of six months from the date of receipt
of a copy of this order. No order as to costs.
Consequently, miscellaneous applications, if any, pending
shall stand closed.
____________________________________ VENKATESWARLU NIMMAGADDA, J 21st October, 2022 cbs
NV,J W.P.No.29574 of 2015 & batch
HON'BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
Writ Petition Nos. 29574, 29575, 29587, 29591, 29603, 29608, 29615, 29689, 29699, 30882, 30958, 33833, 33838, 33860, 33861, 33865 and 33839 of 2015
21st October, 2022 cbs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!