Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rastriya Ispat Nigam Limited vs Radha Madhav Engg Enterprises
2021 Latest Caselaw 3666 AP

Citation : 2021 Latest Caselaw 3666 AP
Judgement Date : 22 September, 2021

Andhra Pradesh High Court - Amravati
Rastriya Ispat Nigam Limited vs Radha Madhav Engg Enterprises on 22 September, 2021
          THE HON'BLE SRI JUSTICE A.V.SESHA SAI
                            AND
           THE HON'BLE MS JUSTICE J.UMADEVI

                       COM.CA No.11 OF 2019
JUDGMENT:

(per AVSS,J.)

Challenge in the present Commercial Court Appeal is to

the order and decree dated 16.08.2019 passed by the Court

of the Special Judge for trial and disposal of the Commercial

Disputes, Visakhapatnam, in CAOP No.38 of 2017 (Old AAP

No.306 of 2017). The petitioner in the said CAOP No.38 of

2017 is the appellant in the instant appeal. The appellant

herein filed the said CAOP No.38 of 2017 before the Special

Court under Section 34 of the Arbitration and Conciliation

Act, 1996, praying to set aside the Award dated 15.12.2016

passed by the Arbitral Tribunal (respondents 2 to 4 herein)

on the claims made by respondent No.1 herein and the

counter claims of the appellant herein.

2. Briefly stated, the facts and circumstances,

leading to filing of the present Commercial Court Appeal, are

as under:-

The appellant herein, i.e., Rashtriya Ispat Nigam

Limited, Visakhapatnam Steel Plant, floated a tender for

structural steel plant works for Sinter Plant No.3 and in the

said process, respondent No.1 herein emerged as the

successful tenderer and the appellant herein awarded the

contract in favour of respondent No.1 and issued letter of

acceptance on 05.04.2007. An agreement was also entered

into on 02.05.2007 and the contract value being

Rs.3,49,00,000/-, including all taxes and duties, but

excluding service tax. The initial period of contract was 13

months from the date of letter of acceptance and the said

period came to an end on 28.04.2008. The appellant herein

granted extension for six times up to 30.06.2010.

Subsequently, a portion of the work was withdrawn by

respondent No.1 and the same was awarded in favour of

M/s. Hindustan Steel Works Construction Limited on

05.08.2010 by undertaking tender process. For the balance

work of the 1st respondent herein, the appellant herein

extended the period up to 31.08.2010 and respondent No.1

herein requested further extension till 31.10.2010 by way of

a letter dated 07.09.2010, which was declined by the

appellant herein, vide letter dated 08.09.2010. Thereafter,

vide notice dated 14.12.2010, the appellant herein informed

respondent No.1 that the contract stood terminated by efflux

of time and instructed respondent No.1 to vacate the site.

On 15.06.2012, respondent No.1 herein did put forth claims

worth Rs.5.45 crores and the appellant herein gave a reply on

09.07.2012, turning down the same except the final bill

amount and certain extra items. Thereafter, the issues

landed before the Arbitral Tribunal and respondent No.1

herein laid claims for a total sum of Rs.5.45 crores.

3. Before the Arbitral Tribunal, respondent No.1

herein made 15 claims, whereas the appellant herein made

six counter claims. The Arbitral Tribunal, vide Award dated

15.12.2016, granted amount under 12 claims and disallowed

three claims laid by respondent No.1 and allowed one

counter claim and rejected five counter claims made by the

appellant herein out of six counter claims. Assailing the said

Award, to the extent the same went against the appellant, the

appellant herein, by invoking the provisions of Section 34 of

the Arbitration and Conciliation Act, 1996, filed CAOP No.38

of 2017 on the file of the Court of the Special Judge for trial

and disposal of the Commercial Disputes, Visakhapatnam.

Learned Special Judge, by way of an order and decree dated

16.08.2019, dismissed the CAOP No.38 of 2017, confirming

the Award dated 15.12.2016 rendered by the Arbitral

Tribunal.

4. In the above background, challenging the validity

and legal sustainability of the said order and decree dated

16.08.2019, the present Commercial Court Appeal came to

be preferred.

5. Heard Sri V.Ravinder Rao, learned Senior

Counsel, representing Sri W.B.Srinivas, learned counsel for

the appellant and S/Sri P.V.Krishnaiah and M.Ramdas,

learned counsel for respondent No.1, apart from perusing the

entire material available on record.

6. Submissions/Contentions of Sri V.Ravinder

Rao, learned Senior Counsel:

(1) The order passed by the learned Special Judge,

confirming the award of the Arbitral Tribunal is highly

erroneous, without jurisdiction, contrary to law, weight of

evidence and probabilities of the case and opposed to the

very spirit and object of the provisions of the Indian Contract

Act, 1872, the Arbitration and Conciliation Act, 1996 (for

short, 'the Act, 1996') and the Micro, Small and Medium

Enterprises Development Act, 2006 (for short, 'MSMED Act').

(2) The order impugned is full of assumptions and

presumptions and in total disregard of the documentary

evidence available on record and the basic principles of law.

(3) The claims made by respondent No.1 are beyond the

terms and conditions of the contract, more particularly,

Clauses 17.2 and 18 of the General Conditions of Contract.

(4) The Arbitral Tribunal has no jurisdiction to award

interest by invoking the provisions of the MSMED Act and

the claimant ought to have approached the appropriate

forum for the said relief, if so advised, by raising a dispute

before the Facilitation Council under Sections 15 to 18 of the

MSMED Act, 2006.

(5) The reasoning given by the Tribunal that the

appellant committed breach of contract is highly perverse as

the claimant himself breached the contract by not completing

the work within the extended period.

(6) The appellant herein did not commit any breach of

contract, as such, respondent No.1 herein would not be

entitled for any compensation.

(7) The appellant herein terminated the contract as per

the terms and conditions of the contract, as such, the

termination of the contract cannot be faulted, and the Award,

on the basis of the findings arrived at, contra is neither

sustainable nor tenable in the eye of law.

(8) The Tribunal granted claims 5 and 8 in violation of

the terms and conditions of the contract and substantive law

and the same are not permissible in view of Clauses 23.1 and

18.5.1 of the General Conditions of Contract read with

Clause-15 of the Special Conditions of Contract.

(9) As per Clause 15.3 of the Special Conditions of

Contract, if the delay is not attributable to the contractor, the

contractor is entitled for price variation only and not for

damages as per Clauses 23.1 and 18.5.1 of the General

Conditions of Contract read with Annexure-4.

(10) The Tribunal ought not to have awarded Claims 5

and 8 in view of Section 28(3) of the Act, 1996 and the

phrase compensation as stipulated in Section 28(3) of the

Act, 1996, is required to be treated as liquidated damages.

(11) The judgment of the Hon'ble Supreme Court in

Associate Builders Vs. Delhi Development Authority 1 cannot

be made applicable for claiming claims 5 and 8, since the

clauses akin to clause 18.5.1 of the General Conditions of

Contract was not there in the said reported case.

(12) All extensions were granted without liquidated

damages, which the contractor already claimed under Claim

No.1 in the form of release of due payment of final bill

(Rs.75,26,745-91 ps), labour escalation bill (Rs.9,16,194-15

ps), POL escalation bill (Rs.35,383-65 ps) and material

escalation bill (Rs.16,38,044-72 ps), as such, the contractor

is not entitled to claims 5 and 8 separately.

(13) Vide letters dated 20.04.2009 and 15.03.2010,

contractor sought the extension and asked for price

escalation but not damages, but, for the first time, before the

Arbitral Tribunal, the contractor asked for damages. Price

variation is in the form of liquidated damages, as such, grant

of claims 5 and 8 is nothing but duplication and the said

claims are in the nature of general damages and are not

(2015) 3 SCC 49

permissible in view of Clause 18.5.1 of the General

Conditions of Contract.

(14) According to Section 74 of the Indian Contract Act,

1872 contractor is only entitled for reasonable compensation,

i.e., price variation, already covered under claim No.1, as

such, the claimant is not entitled for amount covered by

claims 5 and 8 and the price variation needs to be treated as

liquidated damages.

In support of his submissions and contentions, as

regards claims 5 and 8, learned Senior Counsel takes the

support of the following judgments of the Hon'ble Supreme

Court:

(1) Mahanagar Telephone Nigam Limited Vs. Tata Communications Limited2;

(2) Kailash Nath Associates Vs. Delhi Development Authority and another3;

(3) Bharat Sanchar Nigam Limited Vs. Reliance Communication Limited4;

(4) Union of India Vs. Raman Iron Foundry5;

(5) Fateh Chand Vs. Balkishan Dass6;

(2019) 5 SCC 341

(2015) 4 SCC 136

(2011) 1 SCC 394

(1974) 2 SCC 231

AIR 1963 SC 1405

(15) According to the learned Senior Counsel, claims 4

and 7 are excepted matters in view of Clause 21.3 of the

General Conditions of Contract, as such, these claims are not

tenable.

(16) Proviso to Clause 21.3 of the General Conditions of

Contract mandates the contractor to make claim for extra

works within 30 days to the Engineer supported by

documents, but in the instant case, contractor made a claim

for extra works, i.e., under Claim No.4 on 05.01.2012,

though the contract was terminated on 31.08.2010, i.e., 1½

years after termination of the contract, i.e., during the

contractual period, the contractor did not raise the claim.

But however, the Executive Engineer allowed the claims 2, 4

to 10, but disallowed the claims 1, 3, 11 and 12, which are

set out under claim No.4. Since the claims 4 and 7 are the

accepted matters, they are not tenable and the Arbitral

Tribunal has no jurisdiction under Clause 28 of the General

Conditions of Contract.

In support of his contentions on claims 4 and 7, learned

Senior Counsel places reliance on the judgment of the

Hon'ble Supreme Court in M/s. Mitra Guha Builders (India)

Company Vs. Oil and Natural Gas Corporation Limited7 (Paras

16 to 29).

(2020) 3 SCC 222

(17) On Claim No.13, it is contended that as per Clause

9.3 of the General Conditions of Contract, the contractor is

not entitled for the said claim and it would not be open for

the contractor to claim anything under this head.

(18) On Claim No.14, it is contended by the learned

Senior Counsel that in view of Clause 28.4 of General

Conditions of Contract, the Arbitral Tribunal has no

jurisdiction to award interest.

(19) Arbitral Tribunal is the creature of the statute, and

while exercising jurisdiction under the Act, 1996, the Arbitral

Tribunal erred in awarding interest as per the MSMED Act,

2006.

In support of his contentions on claim No.14, learned

Senior Counsel places reliance on the following judgments:

(1) In Union of India v. Ambica Construction8 ;

(2) In Sri Chittaranjan Maity v. Union of India9 ;

(20) The Arbitral Tribunal is prohibited under Section

31(7) (a) of the Act, 1996 read with Clause 28.4 of the

General Conditions of Contract. Once the Arbitral Tribunal

is barred under Section 31(7) (a) of the Act, 1996, read with

Clause 28.4 of the General Conditions of Contract, the

Arbitral Tribunal cannot fall back on the provisions of the

(2016) 6 SCC 36

(2017) 9 SCC 611

MSMED Act, 2006 and the said provision of law will not

confer jurisdiction on the Arbitral Tribunal to award interest,

and Sections 18 and 24 of the MSMED Act, 2006, would not

come to the aid of the appellant herein.

(21) Alternatively, it is the submission of Sri V.Ravinder

Rao, learned Senior Counsel that the benefit of Section 15 of

the MSMED Act, 2006, is available only to the goods supplied

by the contractors and the services rendered to the buyer,

but not for contractual works.

(22) The violation of the orders of the Constitutional

Courts are required to be treated as the decisions taken

against the public policy (Referring Associate Builders Vs.

Delhi Development Authority's case reported in (2015) 3 SCC

49).

7. Submissions and contentions of S/Sri

P.V.Krishnaiah and M.Ramdas, learned counsel for

respondents:

(1) The Award passed by the learned Arbitral Tribunal

and the order passed by the learned Special Judge under

Section 34 of the Act, 1996, are strictly in accordance with

the provisions of the said legislation and that there are no

errors, nor there exists any infirmities, in the impugned order

of the learned Special Judge, as such, the same does not

warrant any interference of this Court under Section 37 of

the Arbitration and Conciliation Act, 1996.

(2) The jurisdiction of the Courts is limited only to the

extent of the grounds set out in sub-section (2) of Section 34

of the Act, 1996 and in the instant case, there are no such

grounds existing.

(3) Award of the Arbitral Tribunal cannot be impeached

unless the same is contrary to the provisions of the Act,

1996, and the terms of the contract and the said

contingencies are conspicuously absent in the case on hand.

(4) At no point of time, respondent No.1-contractor

failed in fulfilling the obligations and the delay in executing

the contractual work was due to the attitude of the appellant

and not due to the conduct of respondent No.1-contractor.

(5) The grounds now sought to be pressed into service

by the learned counsel for the appellant were neither raised

before the Arbitral Tribunal nor before the Special Court nor

before this Court in the Memorandum of Grounds of Appeal,

as such, the same do not warrant any consideration by this

Court.

(6) The findings of the team of Arbitrators, in the

absence of any person with judicial knowledge, are not fatal

to the Award in view of law laid down by the Hon'ble

Supreme Court and in the instant case, the First Arbitrator

was appointed by the contractor and second Arbitrator by the

appellant, who in turn jointly elected the third Arbitrator.

Learned counsel takes the support of the following

judgments in support of the submissions:

(1) Municipal Corporation of Delhi Vs. M/s. Jagan Nath

Ashok Kumar and another10

(2) P.R.Shah, Shares and Stock Brokers Private Limited

Vs. B.H.H.Securities Private Limited and others11

(7) In the absence of any fault on the part of any

contractor, the prohibition contained in Clause 19.1 cannot

be applied for denying the claims 5 and 8.

(8) The decision in Kailash Nath Associates Vs. Delhi

Development Authority and another (3 supra) is applicable

only in the cases where there is breach of contract and since

there is no breach of contract committed by the contractor,

the said decision cannot be made applicable.

(9) Learned counsel places reliance on a decision in

Associate Builders Vs. Delhi Development Authority case (1

supra), to sustain the Award on claims 5 and 8.

(10) The contention as regards the liquidated damages

was not raised before all the lower fora nor raised in the

Memorandum of Grounds of Appeal in the present appeal, as

(1987) 4 SCC 497

(2012) 1 SCC 594

such, the same cannot be raised now orally for the first time

during the course of arguments.

(11) As per the appellant, claims 5 and 8 are also

contrary to law, but the same cannot be sustained and when

there is a delay on the part of the appellant, clause 18.4 of

the General Conditions of Contract would not come to the

rescue of the appellant herein. Learned counsel places

reliance on the judgment in Central Bank of India Vs.

Virudhunagar Steel Rolling Mills Limited and others12.

(12) In view of Clause 17.1 of the Special Conditions of

Contract and Clause 26.3 of the General Conditions of

Contract, contentions of the learned counsel for the appellant

as regards claims 4 and 7 are not sustainable and he relies

on a decision of the Hon'ble Supreme Court in Kalpraj

Dharamshi and another Vs. Kotak Investment Advisors Ltd.,

and another13.

(13) The contention of the learned counsel for the

appellant as regards the claim-14 cannot be sustained in

view of the law laid down by the Bombay in M/s. Steel

Authority of India Ltd., and another Vs. Micro, Small

Enterprise Facilitation Council, through Joint Director of

Industries, Nagpur Region, Nagpur14.

(2015) 16 SCC 207

2021 SCC Online SC 204

AIR 2012 Bombay HC 178

Both the learned counsel have filed written arguments also.

8. In the above background, now, the issues which

this Court is called upon to answer in the present

Commercial Court Appeal are:-

(1) Whether the order of the learned Special Judge, confirming the award passed by the Arbitral Tribunal is in accordance with the provisions of the Arbitration and Conciliation Act, 1996, the Indian Contract, 1872 and the Micro, Small and Medium Enterprises Development Act, 2006 and whether the contentions of the learned counsel for the appellant as regards claims 5 and 8 are sustainable and tenable?

(2) Whether the findings of the learned Arbitral Tribunal, as confirmed by the learned Special Judge, on claims 4 and 7 warrant any interference of this Court under Section 37 of the Arbitration and Conciliation Act, 1996?

(3) Whether the Arbitral Tribunal is justified in granting relief covered by claim No.13 ?

(4) Whether the Arbitral Tribunal and the Special Judge are justified in granting interest to the respondent- contractor on claim No.14 in view of the conditions of contract and Whether the Tribunal and the Special Court are justified in invoking the provisions of the Micro, Small and Medium Enterprises Development Act, 2006?

9. Anterior to the process of examining, analyzing

and adjudicating various issues that have cropped up in the

present Commercial Court Appeal, it may be highly essential

and apposite to refer to the provisions of Section 34 of the

Arbitration and Conciliation Act, 1996, which read as follows:

" 34. Application for setting aside arbitral award.

1. Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and subsection (3).

2. An arbitral award may be set aside by the Court only if-

a. the party making the application furnishes proof that-

i. a party was under some incapacity, or

ii. the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or

iii. the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

iv. the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or

v. the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or

b. the Court finds that-

i. the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or

ii. the arbitral award is in conflict with the public policy of India.

[(2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award:

Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.]

(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.

(4) On receipt of an application under sub-section (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the arbitral tribunal an opportunity to resume the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award.

(5) An application under this section shall be filed by a party only after issuing a prior notice to the other party and such application shall be accompanied by an affidavit by the applicant endorsing compliance with the said requirement.

(6) An application under this section shall be disposed of expeditiously, and in any event, within a period of one year from the date on which the notice referred to in sub-section (5) is served upon the other party.]"

10. It is very much lucid and candid from a reading of

the above provisions of law that the application for setting

aside an arbitral award is maintainable only in the

contingencies stipulated under Section 34(2)(a) (i to v) and

Section 34(2)(b) and Section 34(2A) and Section 34(3) of the

Act, 1996. The issues in the instant Commercial Court

Appeal are required to be examined, analyzed and resolved

within the parameters of the above said provisions of law.

11. Respondent No.1 herein filed a claim statement,

claiming as many as 15 claims and the particulars of the

same including the amounts awarded by the Arbitral

Tribunal, vide Award dated 15.12.2016 are as follows:-

                                     Amount         Amount          Whether
Sl.No.          Claim                claimed        awarded         interest
                                   Rs.     Ps.     Rs.     Ps.      granted

1.       Release of final bill,
         Labour        wages,
                                  1,01,16,368-43   96,66,136-00     Granted
         PQL,        material
         escalation

2.       Refund of amount
         deducted towards
                                    2,17,653-00     2,17,018-00     Granted
         payment       of
         labourers

3.       Release          of
         Performance
         guarantee     bond
         submitted by the
                                   34,90,000-00    34,90,000-00    Not granted
         Claimant in lieu of
         security    deposit
         under provision of
         SSI

4.       Payment      towards
         expenditure       in
                                  1,19,30,185-73   79,27,943-00     Granted
         executing 12 Nos.
         of extra items

5.       Delay in issue of
         drawings, materials
                                   68,25,022-00    40,95,013-00     Granted
         and               non-
         availability of fronts

6.       Change             in                      Rejected the
                                   96,84,406-00                    Not granted
         specification                                     claim

7.       Fixing of higher
         BOQ rates for the         44,00,714-48    23,30,236-00     Granted
         additional scope of




      work for JH44A to
      JH49A

8.    Revision of bill of
      quantities     (BOQ)
      rates to increase all
      input costs for the         54,83,000-00     36,49,047-00 Granted
      period        beyond
      original    schedule
      date of completion.

9.    Semi Fabrication of
      steel     structures         8,93,279-00       6,14,457-00 Granted
      lying at the site

10.   Collection,
      transportation,
      stocking, etc., of          15,29,545-00     13,33,247-00 Granted
      steel drawn from
      VSP.

11.   Additional
      expenditure met by
      engaging      higher
      capacity traitors 30         5,08,000-00       4,16,000-00 Granted
      TON     instead    of
      originally engaged
      20 Ton

12.   Additional
                                                   Claim rejected
      expenditure         for
                                  25,62,500-00        by Arbitral Not granted
      engaging         heavy
                                                        Tribunal
      cranes

13.   Additional
      expenditure         for
                                   4,15,000-00       3,81,800-00 Granted
      development          of
      fabrication site

14.   Payment of interest                            @ 20.25% at
      as per Government                            monthly rates
      norms from time to                           i.e., 3 times of
      time SSI (MSME)                               Banks rate of
      units as all the                                   6.75% as
      claims from the                                published by
                                 As per MSMED
      date of eligibility till                              RBI on --
                                      Act, 2006
      the actual date of                              09.12.2016
      payment as per the                           vide Annexure
      MSMED Act, 2006.                              8 at Page 207
                                                       in line with
                                                     MSMED Act,
                                                             2006.

15.   Costs                                          Rejected by
                                  26,20,068-00                   --
                                                       Tribunal

      Total                       5,80,55,719-64   3,41,20,897-00





12. Appellant herein raised six counter claims and out

of which the Arbitral Tribunal allowed counter claim No.4

and disallowed counter claim Nos.1, 2, 3, 5 and 6 on the

ground of limitation and the particulars of the same are as

follows:

                                       Amount         Amount           Whether
Sl.No.             Claim               claimed        awarded          interest
                                     Rs.     Ps.     Rs.       Ps.     granted

1.         Rist and costs           1,97,65,552-30          Rejected      --

2.         Recovery of amount
           of failure of RMEE
                                     95,96,585-68           Rejected      --
           to account for the
           steel

3.         Cost incurred for
           returning       the
                                      5,75,335-00           Rejected      --
           surplus steel, cut
           pieces and scrap

4.         Crane            hire
                                        91,725-00          91,725-00      --
           purchases

5.         Charges for power
                                     15,28,340-00           Rejected      --
           consumption

6.         Recovery    of     il.
                                      2,19,361-00           Rejected      --
           building cess

7.         Total                    3,17,76,641-55    4,91,725-00



13. As against the Award passed by the learned

Arbitral Tribunal on 15.12.2016, the appellant herein

preferred CAOP No.38 of 2017 on the file of the Court of the

Special Judge, and the Special Judge, by way of the

questioned order and decree dated 16.08.2019, dismissed

CAOP No.38 of 2017, confirming the Award passed by the

Arbitral Tribunal.

14. Though the present appeal came to be preferred

against the entire Award, as confirmed by the learned Special

Judge, learned Senior Counsel, Sri V.Ravinder Rao, during

the course of arguments, mainly confined and advanced

arguments on claims 4, 5, 7, 8, 13 and 14 only and did not

press the appeal in respect of the other claims and the

counter claims. Therefore, this Court deems it appropriate to

deal with the said claims only.

15. Findings on Claims 5 and 8:

Claims 5 and 8 are as follows:

Claim No.5: Compensation for breach of contract such as non-issue of drawings, materials and non-availability of fronts, etc. by the respondent, resulting in the time of completion getting extended. The claim is on account of compensation of loss of profits and over-heads on the balance works as on 29.04.2008; claim amount: Rs.68,25,022/- + Service Tax + interest.

Claim No.8: Revision of rates of the BOQ (Bill of Quantities) due to increase in all input costs for the period beyond the original schedule date of completion till the claimant was allowed to execute the work (i.e. from 29.04.2008 to 31.08.2010). Claim amount Rs.54,83,040/- (+) service tax (+) interest as applicable to SSI Units.

Against the amounts so claimed, the Arbitral Tribunal,

vide Award dated 15.12.2016, granted Rs.40,95,013/- +

service tax of Rs.6,14,252/- and Rs.36,49,047/- + service tax

of Rs.5,47,357/- + interest, respectively, against the claim

Nos. 5 and 8.

16. While attacking the grant of claims 5 and 8,

learned Senior Counsel for the appellant, Sri V.Ravinder Rao,

maintains that having allowed claim No.1, which pertains to

release of final bill, labour wage escalation, POL escalation

and material escalation, the Arbitral Tribunal grossly erred in

granting claims 5 and 8 and the same tantamounts to

duplication in granting the reliefs. It is the further

submission of learned Senior Counsel that the Tribunal

totally ignored clauses 18.5.1, 21.1, 21.3 and 23.1 of the

General Conditions of Contract, while awarding the claims

and also condition No.15 of the Special Conditions of

Contract and Annexure-4 thereof. In this context, it may be

apt to extract the said conditions of contract.

17. Clause 18.5.1 of the General Conditions of

Contract reads thus:

Extension of time for Completion: Should the quantum of extra or additional work of any kind or other special circumstances of any kind whatsoever which may occur be such as fairly entitle the Contractor to an extension of time for the completion of the Work, the Engineer shall decide the amount of such extension. However the Engineer is not bound to take into account any extra or additional work or other special circumstances, unless the Contractor has within thirty (30) days after such work has been commenced or such circumstances have arisen or as soon thereafter as is practicable but not later than thirty (30) days delivered to the Engineer full

and detailed particulars of any claim for extension of time to which he may consider himself entitled in order that such claim may be investigated at that time. In my case, the Contractor shall not be entitled to Revision of Price, any compensation or damages on account of such extension of completion period."

18. Clause 21.0 deals with alterations, additions and

omissions and the same read as infra:

"Clause 21.1: Variations: The Engineer/Consultant shall have the right to make any variations of the form, quality or quantity of the Work or any part thereof that may in his opinion be necessary/required for the completeness of the Work and for any other reasons which in his opinion be desirable/required, he shall have right to order the Contractor to do any of this following:-

a) increase or decrease the quantity of any work/ works included in the Contract.

b) omit any such work/works.

c) change the character or quality or kind of any such work/works.

d) change the levels, lines, position and dimensions of any part the work/works.

e) execute additional work of any kind necessary for the completion of the work/works.

and no such variation shall in any way vitiate or invalidate the Contract but the value of all such variations shall be taken into account in ascertaining the amount of the Contract Price and adjustment of time for completion, if required.

Clause 21.2 : Orders for variations to be in writing: No such variation shall be made by the Contractor without an order in writing of the Engineer/Consultant. Provided that no order in writing shall be required for increase or decrease in the quantity of any work where such increase

or decrease is not the result of any order given order this Clause, but is the result of the quantities exceeding or being less than those stated in the Bill of Quantities.

Provided also that if for any reason, the Engineer/ Consultant shall consider it desirable to give any such order, verbally, the Contractor shall comply with such order and confirmation by the Contractor in writing of such verbal order given by Engineer / Consultant shall be deemed to be an order in writing subject to Clause No.5.3 hereof."

19. Clause 23.1 of the General Conditions of Contract

reads as follows:

"Clause 23.1: Prices or the Rates for the Work stipulated in the Contract, shall remain firm and binding during the Contract Period subject to the variations stipulated in the Special Conditions of the Contract."

20. Clause 15.0 of the General Conditions of Contract

reads as under:

"Clause 15.0: Price Variation:

Clause 15.1: The price variation on accepted rates of the Bill of Quantities will be permissible to the extent given in Annexure-4 enclosed. The rates quoted by the Tenderer shall be inclusive of all taxes, levies, duties, etc., but exclusive of Service tax and Education Cess thereon prevailing on the date of opening of Envelop-2.

Clause 15.2 : During tenure of the Contract, if any new taxes, duties/levies, etc., are imposed or tax rates undergo changes as notified by the Govt. and become applicable to the subject works, the same shall be reimbursed by the Employer on production of documentary evidence in respect of payment of the same. Benefits accruing to the Contractor on account of withdrawal/reduction in

any existing taxes and duties, the same shall be passed on to the Employer.

Clause 15.3 : The variations due to 15.1 and 15.2 above shall not be permissible during the extended period of contract, if the delay is attributable to the Contractor."

21. Annexure-4 of the Special Conditions of Contract

which deals with Price Variation Formula reads as follows:

"ANNEXURE-4 (As per Clause No.15.0 of Special Conditions of Contract)

PRICE VARIATION FORMULA

The following clause relating to variation in wages shall be applicable. No other claim on account of any other variation either statutory or otherwise shall be applicable.

(CLARIFICATION: In case of revision of rates of materials, wages & POL prices with effect from any date in a month say March, 2006. The work done with effect from subsequent month (i.e., April, 2006) only will qualify for price variation as per the above formula.)

1.0. PRICE VARIATION DUE TO LABOUR:

1.1 Price variation on account of wages for fabrication of steel structures/pipe work:

For every rupee per month of 208 hours by which the wage structure of minimum rates workers varied from the base month as a result of Government action (direct or indirect), adjudication (legislative or otherwise), the selling price, exclusive of escalation claims shall be adjusted by Rs.2.0 (Rupees two only) per tonne and such adjustment shall be applied to such selling prices in respect of structures inspected and accepted after the first day of the subsequent month of such wage revision.

i) For the purpose of this order, the base date shall be the date of opening of the Envelope-2.

For the purpose of this clause the wage structure of minimum rated workers shall be defined as comprising:

1) Average of minimum rates of monthly wages of skilled, semi-skilled & un-

skilled workers applicable for the area of work as notified by the Commissioner of Labour, Andhra Pradesh, Hyderabad published in the Andhra Pradesh Gazette.

2) Leave with pay.

3)Provident Fund

4) Employees State Insurance Contribution.

1.2 Escalation for erection in the composite rate of fabrication and erection:

For the purpose of calculating the price variation for erection work, the erection cost component in the awarded composite rates of fabrication and erection shall be taken as 30% of the relevant items. Against this 30% value, representing the erection cost, the labour component in the erection cost shall be taken as 40%. On this basis, the payable/deductible price variation towards erection shall be computed as per the following formula:

            V            = W x 0.40 x 0.3 (X-X0)
                               XO
      Where

V     =      Escalation or de-escalation payable or
deductable.
W     =      Value of the work done based on the

accepted composite rates of the Bill of Quantities for the period for which variation is applicable.

RASHTRIYA ISPAT NIGAM LIMITED

X = Average of revised minimum rates of wages of skilled, semi-skilled and un-skilled workers applicable for the area of site of work as per minimum rates of wages as notified by Commissioner of Labour, Andhra Pradesh, Hyderabad, published in

the Andhra Pradesh Gazette for the period under consideration.

ХО = Average of minimum rates of wages of skilled, semi-skilled and unskilled workers on the base date (.e., the date of opening of the Envelope-2) applicable for the area of site of work as per minimum rates of wages as notified by Commissioner of Labour, Andhra Pradesh, Hyderabad, published in the Andhra Pradesh Gazette.

1.3 Labour escalation on Erection/Installation (without cost of materials) (excluding pure painting works).

For calculating escalation for erection/installation rates excluding cost of materials and fabrication, the following formula shall be applicable:

                  V     =     0.40 x W x (X - XO)
                                      XO

The notations here will be same as given at Clause No. 1.2

1.4 Labour escalation for items of pure painting:

For calculating labour escalation for items of pure painting works, the following formula shall be applied:

            V     =     0.15 x W x (X - XO)
                               XO

The notations here will be same as given at Clause No. 1.2

2.0 PRICE VARIATION FOR ALL OTHER ITEMS OF THE WORK (excluding the items at Clause Nos. 1.1 to 1.4).

For calculating labour escalation for all other items (excluding the cost of materials), the following formula shall be applied.

      V     =    0.4xwx (X-XO)
                        XO

The notations here will be same as given at Clause No. 1.2

3.0 PRICE VARIATON DUE TO MATERIALS:

Formula as below shall be applicable during the contract period. The payment or deduction on account of variation shall be claimed in January and July of every year for the preceding periods of si: months and also on completion of contract along with necessary details/documents to the satisfaction of the Engineer. The contractor shall submit the detailed documents even if there is variation or not.

3.1 Amount payable/deductible due to variation (inclusive of pure painting

items) in the price of consumables like electrodes, industrial gases, paint etc. and also the cost of material to be supplied by the party shall be determined on the basis of the following formula:

             V      =      0.40 x W (X-XO)
                                 ХО
Where
       V       =      the amount payable/deductible due
to variation in the prices
       X       =      all commodity whole sale price index
for the month under reference.
       XO      =      all commodity whole sale price index

as on the date of opening of the Envelope-2.

W = gross value of the work done at contract rates for all items for the period for which the variation is applicable. The variation will be applicable for the quantities measured one (1) month after the date of effect of the revised rates and the above variation in prices shall be applicable only during the contract period.

NOTE: The wholesale price index for all commodities shall be based on average of month Bulletins published by RBI.

3.2 Price variation due to change in POL prices shall be applicable as per formula given below:

             V      =      0.04 x W (X-XO)
                                 XO




               V      =    Escalation of de-escalation (variation)
        payable or deductable.

               W      =       Gross value of the work done at

contract rates for all items for the period for which the variation is applicable.

X = Revised rate of Ordinary High Speed Diesel Oil per litre as fixed by Public Sector Oil Company applicable for the area of site of work for the period under considerations.

ХО = Rate of Ordinary High Speed Diesel Oil per litre as fixed by Public Sector Oil Company applicable for the area of site of work on the base date (i.e., the date of opening of Envelope-2).

               0.04 =        is assumed to be the POL content of
        contract rates.


        CLARIFICATION:

i) In case of revision of rates of Ordinary High Speed Diesel Oil with effect from anydate in a month, say March, 2006, the work done with effect from the first day ofsubsequent month (i.e., 15 April, 2006) only will qualify for price variation as per the above formula.

ii) In case of more than one revision in the rate of Ordinary High Speed Diesel Oil, in a month, the latest revision in the rates shall be considered for payment of escalation."

22. In this context, it may be apt to refer to the

observations of the Arbitral Tribunal while dealing with claim

No.5. The Tribunal, on the basis of the material available

came to a conclusion that the RINL/appellant herein did not

provide any fronts till 28.04.2008 for erection of fabricated

structures thereby committed breach of contract and the

Tribunal also took into consideration Section 73 of the Indian

Contract Act, 1872 which reads as follows:

"73. Compensation for loss or damage caused by breach of contract.--When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.

COMPENSATION FOR FAILURE TO DISCHARGE OBLIGATION RESEMBLING THOSE CREATED BY CONTRACT- When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it, is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract.

Explanation: In estimating the loss or damage, arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account."

It is very much manifest from a reading of the above

provision of law that when there is a breach of contract, the

party who commits such breach, shall compensate the

person who suffers by such breach by way of paying

compensation for any loss or damage caused.

23. The Tribunal also took into account the letters of

the claimant dated 16.04.2008 and 26.04.2008 and found

that the extension of time granted to the claimant was

without liquidated damages and with escalations. The

Tribunal also found that respondent No.1-contractor, at no

point of time, was responsible for the delays and all the

delays were attributable only to the appellant herein. The

Special Court also while placing reliance on the decision of

the Hon'ble Supreme Court in P.M.Paul Vs. Union of India15,

eventually held in respect of claim No.5 that there was

nothing to discredit the findings of the Arbitral Tribunal on

claim No.5. In view of the said cogent and convincing

reasons assigned by the learned Arbitral Tribunal, as

confirmed by the Special Judge, this Court does not find any

valid reasons to disturb the findings recorded on claim No.5

by the Special Judge. It is also significant to note, as

pointed out by the learned counsel for the 1st respondent

herein, that RINL/appellant herein did not plead specifically

either before the Arbitral Tribunal or before the Special Court

or before this Court in the Memorandum of Grounds of

Appeal in the present appeal, in the manner now sought to

be projected during the course of arguments.

24. Coming to Claim No.8 -- Which pertains to

revision of BOQ rates under the period beyond the original

schedule of compensation, the claimant laid a claim of

Rs.54,83,040/- on the ground that during the currency of

the contract, all input costs went up considerably including

costs of labour and overhead charges. The Tribunal recorded

a finding that had the Visakhapatnam Steel Plant come

forward in fulfilling their obligations, the project might have

been completed by the claimant in time and the present

(1989) 1 SCC 368

situation could have been averted. The appellant herein

contended before the Arbitral Tribunal that due to

inadequate mobilization of the resources by the claimant, the

contract could not be completed within the agreed period.

After taking into account all the contentions including

clauses 18.4 and 28.1 and contention that these claims are

excepted matters, the Tribunal turned down the contentions

of the appellant on the ground that the breach was solely

attributable to the appellant and eventually found that the

Visakhapatnam Steel Plant had to compensate when it

committed breach of contract. The learned Special Judge by

placing reliance on the judgments of the Hon'ble Supreme

Court in Associate Builders Vs. Delhi Development Authority

(1 supra), Oil and Natural Gas Corporation Limited Vs. Saw

Pipes Limited reported in AIR 2003 SC 2629 and J.K.Cold

Tyres Retreads Vs. Union of India and another reported in

2015(1) ALD 532, declined to interfere with the Award of the

Arbitral Tribunal. Therefore, this Court does not find any

valid reason to disturb the finding recorded by the Arbitral

Tribunal and the Special Judge on Claim No.8 also.

25. In this context, it may be appropriate to refer to

the judgments cited by the learned Advocates. In the case of

Mahanagar Telephone Nigam Limited Vs. Tata

Communications Limited (2 supra), the Hon'ble Apex Court, at

paragraphs 11 to 13, held in the following manner.

"11. In Kailash Nath Associates v. DDA, (2015) 4 SCC 136, after considering the case law on Section 74, this Court held:

"43. On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be stated to be as follows:

43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the court cannot grant reasonable compensation.

43.2. Reasonable compensation will be fixed on well- known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.

43.3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the section.

43.4. The section applies whether a person is a plaintiff or a defendant in a suit.

43.5. The sum spoken of may already be paid or be payable in future.

43.6. The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded."

12. In the present case, clauses 16.2 to 16.4 are relevant, and are set out as under:

"16.2 (a) FOR DELIVERY OF STORES:

Should the supplier fail to deliver the store/services or any consignment thereof within the period prescribed for delivery, the purchaser shall be entitled to recover 0.5% of the value of the delayed supply for each week of delay or part thereof for a period up to 10 (TEN) weeks and thereafter at the rate of 0.7% of the value of the delayed supply for each week of delay or part thereof for another TEN weeks of delay. In the case of package supply where the delayed portion of the supply materially hampers installation and commissioning of the systems, L/D charges shall be levied as above on the total value of the concerned package of the Purchase Order. However, when supply is made within 21 days of QA clearance in the extended delivery period, the consignee may accept the stores and in such cases the LD shall be levied upto the date of QA clearance.

16.2 (b) FOR INSTALLATION & COMMISSIONING Should the supplier fail to install and commission the project within the stipulated time the purchaser shall be entitled to recover 0.5% of the value of the purchase order for each week of delay or part thereof for a period upto 10 (TEN) weeks and thereafter @ 0.7% of the value of purchase order for each week of delay or part thereof for another 10 (TEN) weeks of delay. In cases, where the delay affects installation/commissioning of part of the project and part of the equipment is already in

commercial use, then in such cases, LD shall be levied on the affected part of the project.

16.2 (c). The Liquidated Damages, as per Clause 16.2

(a) and 16.2 (b) above shall be limited to a maximum of 12%, even in case the DP extension is given beyond 20 weeks.

16.3. Provisions contained in Clause 16.2(a) shall not be applicable for durations (periods) which attract L.D. against clause 16.2(b) above.

16.4. Quantum of liquidated damages assessed and levied by the purchaser shall be final and not challengeable by the supplier."

13. As has been correctly held by the impugned judgment, a maximum of 12% can be levied as liquidated damages under the contract, which sum would amount to a sum of INR 25 lakh. Since this clause governs the relations between the parties, obviously, a higher figure, contractually speaking, cannot be awarded as liquidated damages, which are to be considered as final and not challengeable by the supplier. This being the case, the appellant can claim only this sum. Anything claimed above this sum would have to be refunded to the respondent."

In case of Kailash Nath Associates Vs. Delhi

Development Authority and another (3 supra), the Hon'ble

Supreme Court ruled as follows : (paragraphs 31 to 43)

"31. Section 74 as it originally stood read thus:

"When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has

broken the contract reasonable compensation not exceeding the amount so named."

32. By an amendment made in 1899, the Section was amended to read: "74. Compensation for breach of contract where penalty stipulated for.- When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.

Explanation.-A stipulation for increased interest from the date of default may be a stipulation by way of penalty.

Exception.-When any person enters into any bail-bond, recognizance or other instrument of the same nature, or, under the provisions of any law, or under the orders of the Central Government or of any State Government, gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of any condition of any such instrument, to pay the whole sum mentioned therein.

Explanation.-A person who enters into a contract with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested."

33. Section 74 occurs in Chapter 6 of the Indian Contract Act, 1872 which reads "Of the consequences of breach of contract". It is in fact sandwiched between Sections 73 and 75 which deal with compensation for loss or damage caused by breach of contract and compensation for damage which a party may sustain through non-

fulfillment of a contract after such party rightfully rescinds such contract. It is important to note that like Sections 73 and 75, compensation is payable for breach of contract under Section 74 only where damage or loss is caused by such breach.

34. In Fateh Chand v. Balkishan Das, 1964 SCR (1) 515, this Court held: "The section is clearly an attempt to eliminate the somewhat elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages and stipulations in the nature of penalty. Under the common law a genuine pre-estimate of damages by mutual agreement is regarded as a stipulation naming liquidated damages and binding between the parties: a stipulation in a contract in terrorem is a penalty and the Court refuses to enforce it, awarding to the aggrieved party only reasonable compensation. The Indian Legislature has sought to cut across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty.

....

Section 74 of the Indian Contract Act deals with the measure of damages in two classes of cases (i) where the contract names a sum to be paid in case of breach and (ii) where the contract contains any other stipulation by way of penalty. We are in the present case not concerned to decide whether a covenant of forfeiture of deposit for due performance of a contract falls within the first class. The measure of damages in the case of breach of a stipulation by way of penalty is by Section 74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the Court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to all

the circumstances of the case. Jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; but compensation has to be reasonable, and that imposes upon the Court duty to award compensation according to settled principles. The section undoubtedly says that the aggrieved party is entitled to receive compensation from the party who has broken the contract, whether or not actual damage or loss is proved to have been caused by the breach. Thereby it merely dispenses with proof of "actual loss or damages"; it does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of contract can be awarded to make good loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach."(At page 526, 527) Section 74 declares the law as to liability upon breach of contract where compensation is by agreement of the parties pre-determined, or where there is a stipulation by way of penalty. But the application of the enactment is not restricted to cases where the aggrieved party claims relief as a plaintiff. The section does not confer a special benefit upon any party; it merely declares the law that notwithstanding any term in the contract predetermining damages or providing for forfeiture of any property by way of penalty, the court will award to the party aggrieved only reasonable compensation not exceeding the amount named or penalty stipulated. The jurisdiction of the court is not determined by the accidental circumstance of the party in default being a plaintiff or a defendant in a suit. Use of the expression "to receive from the party who has broken the contract" does not predicate that the jurisdiction of the court to adjust amounts which have been paid by the party in default cannot be exercised in dealing with the claim of the party complaining of breach of contract. The court has to adjudge in every case reasonable compensation to which the plaintiff is entitled

from the defendant on breach of the contract. Such compensation has to be ascertained having regard to the conditions existing on the date of the breach."(At page

530)

35. Similarly, in Maula Bux v. Union of India (UOI), 1970 (1) SCR 928, it was held:

"Forfeiture of earnest money under a contract for sale of property- movable or immovable-if the amount is reasonable, does not fall within Section 74. That has been decided in several cases :Kunwar Chiranjit Singh v. Har Swarup, A.I.R.1926 P.C.1; Roshan Lal v. The Delhi Cloth and General Mills Company Ltd., Delhi, I.L.R. All.166; Muhammad Habibullah v. Muhammad Shafi, I.L.R. All. 324; Bishan Chand v. Radha Kishan Das, I.D. 19 All. 49. These cases are easily explained, for forfeiture of a reasonable amount paid as earnest money does not amount to imposing a penalty. But if forfeiture is of the nature of penalty, Section 74 applies. Where under the terms of the contract the party in breach has undertaken to pay a sum of money or to forfeit a sum of money which he has already paid to the party complaining of a breach of contract, the undertaking is of the nature of a penalty.

Counsel for the Union, however, urged that in the present case Rs. 10,000/- in respect of the potato contract and Rs. 8,500 in respect of the poultry contract were genuine pre-estimates of damages which the Union was likely to suffer as a result of breach of contract, and the plaintiff was not entitled to any relief against forfeiture. Reliance in support of this contention was placed upon the expression (used in Section 74 of the Contract Act), "the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation". It is true that in every case of breach of contract the person aggrieved by the breach is not required to prove actual loss or damage

suffered by him before he can claim a decree, and the Court is competent to award reasonable compensation in case of breach even if no actual damage is proved to have been suffered in consequence of the breach of contract. But the expression "whether or not actual damage or loss is proved to have been caused thereby" is intended to cover different classes of contracts which come before the Courts. In case of breach of some contracts it may be impossible for the Court to assess compensation arising from breach, while in other cases compensation can be calculated in accordance with established rules. Where the Court is unable to assess the compensation, the sum named by the parties if it be regarded as a genuine pre- estimate may be taken into consideration as the measure of reasonable compensation, but not if the sum named is in the nature of a penalty. Where loss in terms of money can be determined, the party claiming compensation must prove the loss suffered by him.

In the present case, it was possible for the Government of India to lead evidence to prove the rates at which potatoes, poultry, eggs and fish were purchased by them when the plaintiff failed to deliver "regularly and fully" the quantities stipulated under the terms of the contracts and after the contracts were terminated. They could have proved the rates at which they had to be purchased and also the other incidental charges incurred by them in procuring the goods contracted for. But no such attempt was made."(At page 933,934)

36. In Shree Hanuman Cotton Mills and Anr. v. Tata Aircraft Limited, 1970 (3) SCR 127 it was held:

"From a review of the decisions cited above, the following principles emerge regarding "earnest":

(1) It must be given at the moment at which the contract is concluded.

(2) It represents a guarantee that the contract will be fulfilled or, in other words, 'earnest' is given to bind the contract.

(3) It is part of the purchase price when the transaction is carried out.

(4) It is forfeited when the transaction falls through by reason of the default or failure of the purchaser.

(5) Unless there is anything to the contrary in the terms of the contract, on default committed by the buyer, the seller is entitled to forfeit the earnest" (At page 139) "The learned Attorney General very strongly urged that the pleas covered by the second contention of the appellant had never been raised in the pleadings nor in the contentions urged before the High Court. The question of the quantum of earnest deposit which was forfeited being unreasonable or the forfeiture being by way of penalty, were never raised by the appellants. The Attorney General also pointed out that as noted by the High Court the appellants led no evidence at all and, after abandoning the various pleas taken in the plaint, the only question pressed before the High Court was that the deposit was not by way of earnest and hence the amount could not be forfeited. Unless the appellants had pleaded and established that there was unreasonableness attached to the amount required to be deposited under the contract or that the clause regarding forfeiture amounted to a stipulation by way of a penalty, the respondents had no opportunity to satisfy the Court that no question of unreasonableness or the stipulation being by way of penalty arises. He further urged that the question of unreasonableness or otherwise regarding earnest money does not at all arise when it is forfeited according to the terms of the contract.

In our opinion the learned Attorney General is well founded in his contention that the appellants raised no

such contentions covered by the second point, noted above. It is therefore unnecessary for us to go into the question as to whether the amount deposited by the appellants, in this case, by way of earnest and forfeited as such, can be considered to be reasonable or not. We express no opinion on the question as to whether the element of unreasonableness can ever be considered regarding the forfeiture of an amount deposited by way of earnest and if so what are the necessary factors to be taken into account in considering the reasonableness or otherwise of the amount deposited by way of earnest. If the appellants were contesting the claim on any such grounds, they should have laid the foundation for the same by raising appropriate pleas and also led proper evidence regarding the same, so that the respondents would have had an opportunity of meeting such a claim."(At page 142)

37. And finally in ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, it was held:

"64. It is apparent from the aforesaid reasoning recorded by the Arbitral Tribunal that it failed to consider Sections 73 and 74 of the Indian Contract Act and the ratio laid down in Fateh Chand case [AIR 1963 SC 140: (1964) 1 SCR 515 at p. 526] wherein it is specifically held that jurisdiction of the court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; and compensation has to be reasonable. Under Section 73, when a contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew when they made the contract to be likely to result from the breach of it. This section is to be read with Section 74, which deals with penalty stipulated in the contract, inter alia (relevant for the present case) provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case

of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused, thereby to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named. Section 74 emphasizes that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by him.

67........In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach thereof. In such a situation, if the parties have pre-estimated such loss after clear understanding, it would be totally unjustified to arrive at the conclusion that the party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of Sections 73 and 74 of the Indian Contract Act. There was nothing on record that compensation contemplated by the parties was in any way unreasonable. It has been specifically mentioned that it was an agreed genuine pre- estimate of damages duly agreed by the parties. It was also mentioned that the liquidated damages are not by way of penalty. It was also provided in the contract that such damages are to be recovered by the purchaser from the bills for payment of the cost of material submitted by the contractor. No evidence is led by the claimant to establish that the

stipulated condition was by way of penalty or the compensation contemplated was, in any way, unreasonable. There was no reason for the Tribunal not to rely upon the clear and unambiguous terms of agreement stipulating pre-estimate damages because of delay in supply of goods. Further, while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages.

68. From the aforesaid discussions, it can be held that:

(1) Terms of the contract are required to be taken into consideration before arriving at the conclusion whether the party claiming damages is entitled to the same.

(2) If the terms are clear and unambiguous stipulating the liquidated damages in case of the breach of the contract unless it is held that such estimate of damages/compensation is unreasonable or is by way of penalty, party who has committed the breach is required to pay such compensation and that is what is provided in Section 73 of the Contract Act.

(3) Section 74 is to be read along with Section 73 and, therefore, in every case of breach of contract, the person aggrieved by the breach is not required to prove actual loss or damage suffered by him before he can claim a decree. The court is competent to award reasonable compensation in case of breach even if no actual damage is proved to have been suffered in consequence of the breach of a contract.

(4) In some contracts, it would be impossible for the court to assess the compensation arising from breach and if the compensation contemplated is not by way of penalty or unreasonable, the court can award the same if it is genuine pre-estimate by the parties as the measure of reasonable compensation."

38. It will be seen that when it comes to forfeiture of earnest money, in Fateh Chand's case, counsel for the appellant conceded on facts that Rs.1,000/- deposited as earnest money could be forfeited. (See: 1964 (1) SCR Page 515 at 525 and 531).

39. Shree Hanuman Cotton Mills & Another which was so heavily relied by the Division Bench again was a case where the appellants conceded that they committed breach of contract. Further, the respondents also pleaded that the appellants had to pay them a sum of Rs.42,499/- for loss and damage sustained by them. (See: 1970 (3) SCR 127 at Page 132). This being the fact situation, only two questions were argued before the Supreme Court: (1) that the amount paid by the plaintiff is not earnest money and (2) that forfeiture of earnest money can be legal only if the amount is considered reasonable. (at page 133). Both questions were answered against the appellant. In deciding question two against the appellant, this Court held:-

"But, as we have already mentioned, we do not propose to go into those aspects in the case on hand. As mentioned earlier, the appellants never raised any contention that the forfeiture of the amount amounted to a penalty or that the amount forfeited is so large that the forfeiture is bad in law. Nor have they raised any contention that the amount of deposit is so unreasonable and therefore forfeiture of the entire amount is not justified. The decision in Maula Bux's [1970]1SCR928 had no occasion to consider the question of reasonableness or otherwise of the earnest deposit being forfeited. Because, from the said judgment it is clear that this Court did not agree with the view of the High Court that the deposits made, and which were under consideration, were paid as earnest money. It is under those circumstances that this Court proceeded to consider the applicability of Section 74 of the Contract Act. (At page 143)"

40. From the above, it is clear that this Court held that Maula Bux's case was not, on facts, a case that related to earnest money. Consequently, the observation in Maula Bux that forfeiture of earnest money under a contract if reasonable does not fall within Section 74, and would fall within Section 74 only if earnest money is considered a penalty is not on a matter that directly arose for decision in that case. The law laid down by a Bench of 5 Judges in Fateh Chand's case is that all stipulations naming amounts to be paid in case of breach would be covered by Section 74. This is because Section 74 cuts across the rules of the English Common Law by enacting a uniform principle that would apply to all amounts to be paid in case of breach, whether they are in the nature of penalty or otherwise. It must not be forgotten that as has been stated above, forfeiture of earnest money on the facts in Fateh Chand's case was conceded. In the circumstances, it would therefore be correct to say that as earnest money is an amount to be paid in case of breach of contract and named in the contract as such, it would necessarily be covered by Section 74.

41. It must, however, be pointed out that in cases where a public auction is held, forfeiture of earnest money may take place even before an agreement is reached, as DDA is to accept the bid only after the earnest money is paid. In the present case, under the terms and conditions of auction, the highest bid (along with which earnest money has to be paid) may well have been rejected. In such cases, Section 74 may not be attracted on its plain language because it applies only "when a contract has been broken".

42. In the present case, forfeiture of earnest money took place long after an agreement had been reached. It is obvious that the amount sought to be forfeited on the facts of the present case is sought to be forfeited without any loss being shown. In fact it has been shown that far

from suffering any loss, DDA has received a much higher amount on re-auction of the same plot of land.

43. On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be stated to be as follows:- Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the Court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the Court cannot grant reasonable compensation.

Reasonable compensation will be fixed on well known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.

Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the Section.

The Section applies whether a person is a plaintiff or a defendant in a suit.

The sum spoken of may already be paid or be payable in future.

The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is

not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded.

Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application."

In case of Bharat Sanchar Nigam Limited Vs. Reliance

Communication Limited (4 supra), the Hon'ble Supreme Court

held as under: (paragraph 53)

"53. Lastly, it may be noted that liquidated damages serve the useful purpose of avoiding litigation and promoting commercial certainty and, therefore, the court should not be astute to categorize as penalties the clauses described as liquidated damages. This principle is relevant to regulatory regimes. It is important to bear in mind that while categorizing damages as "penal" or "liquidated damages", one must keep in mind the concept of pricing of these contracts and the level playing field provided to the operators because it is on costing and pricing that the loss to BSNL is measured and, therefore, all calls during the relevant period have to be seen. [See Communications Law in India by Vikram Raghavan at page 639]. Since clause 6.4.6 represents pre-estimate of reasonable compensation, Section 74 of the Contract Act is not violated. Thus, it is not necessary to discuss various judgments of this Court under Section 74 of the Contract Act."

In the case of Union of India Vs. Raman Iron Foundry

(5 supra), the Hon'ble Supreme Court held as under:

(Para 11).

"11. The language used in the body of cl. 18 also supports the view that it is with recovery of sums presently due and payable by the ,contractor to the purchaser that this clause deals. It may be noted that cl. 18 does not lay down the substantive rights and obligations of the parties under the contract. It is merely intended to provide a mode of recovery of ' a claim for payment of a sum of money arising out of or under the contract". It, therefore, postulates a claim for a sum which is due and payable, that is. presently recoverable and may be recovered by the mode therein provided. it is difficult to believe that the contracting parties could have intended that even though a sum is not due and payable by the contractor to the purchaser under the contract, the purchaser should be entitled to recover it. It is important to note that cl. 18 does not -create a lien on other sums due to the contractor or give to the purchaser a right to retain such sums until his claim against the contractor is satisfied.If merely a right of lien or retention were given to secure payment of a claim, then even if the claim were for a sum not presently due and payable, the provision perhaps would not have been so startling ,or unusual. But here the right given to the purchaser under. cl. 18 is a right to recover the amount of his claim by appropriating other sums due to the contractor and, on the, interpretation of the appellant, this can be done even if the claim is for a sum which is not due or payable in praesenti and the purchaser is otherwise not entitled to recover it. That would indeed be a highly extra-ordinary result which we would be loathe to reach in the absence of clear and compelling language. This interpretation, if accepted, would mean that as soon as a claim is made by

the purchaser, it would immediately become recoverable and the purchaser would be entitled to sell off the securities of the contractor and appropriate the sale proceeds in or towards satisfaction of such claim and in case that is insufficient, recover the balance by appropriating other sums due to the contractor and if there is even then a shortfall, recover it personally from the contractor, for the last words of cl. 18 provide that "the contractor shall on demand pay to the purchaser the balance remaining due". And this consequence would ensue even if the claim is for a sum which the -contractor is under no existing obligation to pay or which is not presently payable or is disputed as regards the existence of liability or its quantum. A mere making of a claim by the purchaser would impose a liability on the contractor to pay it. That surely could -not have been the intention of the contracting parties. It would be more consonant with reason and good sense to take the view, which, as pointed out above, is plainly and indubitably supported by the language used by the contracting parties, that cl. Is does no more than merely provide an additional mode of recovery to the purchaser, and the purchaser is entitled to exercise the right conferred, under that clause only where there is a claim for a sum which is presently due and payable by the contractor."

In Fateh Chand Vs. Balkishan Dass (6 supra), the

Hon'ble Supreme Court held as under: (Paras 10 and 15).

"10. Section 74 of the Indian Contract Act deals with the measure of damages in two classes of cases

(i) where the contract names a sum to be paid in case of breach and `ii) where the contract contains any other stipulation by way of penalty. We are in the present case not concerned to decide whether a covenant of forfeiture of deposit for due performance of a contract falls within the first class. The measure of damages in the case of

breach of a stipulation by way of penalty is by s.

74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the Court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to all the circumstances of tile case. jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; but compensation has to be reasonable, and that imposes upon the Court duty to award compensation according, to settled principles. The section undoubtedly says that the aggrieved party is entitled to receive compensation from the party who has broken the contract, whether or not actual damage or loss is proved to have been caused by the breach. Thereby it merely dispenses with proof of "actual loss or damages"; t does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of contract can be awarded to make good loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach.

...

15. Section 74 declares the law as to liability upon breach of contract where compensation is by agreement of the parties predetermined, or where there is a stipulation by way of penalty. But the application of the enactment is not restricted to cases where the aggrieved party claims relief' as a plaintiff. The section does not confer a special benefit upon any party; it merely declares the law that notwithstanding any term in the contract predetermining damages or providing for forfeiture of any property by way of penalty, the court will award to the party aggrieved only reasonable compensation not exceeding the amount named or penalty stipulated. The jurisdiction of the court,

is not determined by the accidental circumstance of the party in default being a plaintiff or a defendant in a suit. Use of the expression "to receive from the party who has broken the contract" does not predicate that the jurisdiction of the court to adjust amounts which have been paid by the party in default cannot be exercised in dealing with the claim of the party complaining of breach of contract. The court has to adjudge in every case reasonable compensation to which the plaintiff is entitled from the defendant on breach of the contract. Such compensation has to be ascertained having regard to the conditions existing on the date of the breach."

26. In the considered opinion of this Court, the

amounts awarded under claims 5 and 8, having regard to the

reasons assigned by the learned Arbitral Tribunal and the

Special Judge, by any stretch of imagination, cannot be

termed to be unreasonable. The contention advanced by

the learned counsel for the appellant that since the Arbitral

Tribunal awarded amounts under claim No.1 in the form of

price variation, the Tribunal ought not to have granted the

reliefs under claims 5 and 8, cannot be sustained in the eye

of law, having regard to the language of the provisions of

Sections 73 and 74 of the Indian Contract Act, 1872.

Therefore, the judgments sought to be pressed into service by

the leaned counsel for the appellant would not render any

assistance to the appellant herein in view of the facts and

circumstances of the case.

27. Coming to the judgments cited by the learned

counsel for the 1st respondent-Contractor, in the case of

Associate Builders Vs. Delhi Development Authority (1 supra),

the Hon'ble Apex Court at paragraphs 2, 7 to 10, 12, 57 to

62, held as follows:

"2. The appellant herein was awarded a certain construction work contract by the DDA vide a letter of award dated 14th May, 1992. DDA was building a colony consisting of 7,000 houses in Trilok Puri in the trans-Yamuna area. 168 Middle Income Group houses and 56 Lower Income Group houses, Grade-A Pocket- B (balance work) was awarded for the tendered amount of Rs.87,66,678/-. The contract was to be completed in 9 months. Admittedly, it was ultimately completed only in 34 months, the contractor completing 166 Middle Income Group houses and 36 Lower Income Group houses. The total value of work that was done amounted to Rs.62,84,845/-. As many as 15 claims were made by the contractor and the High Court of Delhi appointed one Shri K.D. Bali to arbitrate the present dispute.

...

7. The Arbitrator by a reasoned award dated 23rd May, 2005 held that the entire delay of 25 months in the execution of the project was thanks to the DDA, none of this delay being attributable to the contractor. The learned Arbitrator found:

"That all the above four claims are inter linked being related to the overhead expenses and therefore dealt together.

That the date of commencement of work was 24.5.92 and the period for completion was 9 months and therefore, the disputed date of completion was 23.2.93 but the work could be actually completed on 28.3.95.

That there was delay of 25 months in completion of the work beyond the stipulated date of completion.

That the Claimants urged that there had been various delays in the execution of work due to the lapses and defaults of the Respondents from the very commencement of work. The progress was held up time and again and the claimants therefore, as back as 17.2.93 advised the Respondents (C-9 page 167) that the Claimants are not interested to execute the work beyond the stipulated date of completion and therefore, their contract be finalized on the stipulated date of completion as the Claimants shall be exposed to incur heavy expenditure in overheads for maintaining establishment watch and ward and tools and

plants and other shuttering material but the Respondents did not refute. The chief reasons for delay are highlighted below:-

I) Delay in supply of structural and architectural drawings.

II) That out of 9 Blocks 2 blocks are abnormally delayed as the site of the said 21 blocks was made available in piecemeal which stretched till 26.2.94 whereas the stipulated completion was 23.2.93.

III) Delay in laying the conduit by the electrical agency resulting in delay in casting of RCC slab and plastering work besides development work. The said hindrance was removed lastly on 28.3.95.

IV) Abnormal delay in making availability of the alignment sketch for electrical cables.

V) Inordinate delay in supply of stipulated material such as cement, steel and pipes.

VI) Delay in decision of finishing work in kitchen and bath rooms.

VII) There was inordinate delay in making availability of colour scheme.

VIII) That the Respondents also abnormally delayed the supply of door shutters which were to be supplied by the Respondents. The same were supplied as late as 8.11.94.

IX) Inordinate delay in writing in the electrical conduits resulting in delay in completion of finishing work.

X) Suspension of work by the Respondents for the period 17.1.94 to 25.2.94 and from 7.8.94 to 22.3.95 because of non-removal of hindrances.

XI) Delayed payment due to non-sanction of Administrative Approval and Expenditure Sanction.

That all the delays as set out had been duly recorded 733 to 739 and M.A.S. register pages from 747 to 768 as highlighted by the Claimants. The Claimants also relied upon certain documents of MAS Register supplied by the Respondents.

That the Claimants further stated that the Claimants had also filed reasons for delay and hold up of the work various defaults of the Respondents in Annexure pages 740 to 746. The Claimants also highlighted the correspondence made by the Claimants with Respondents.

That the Claimants further stated that the said hindrances were avoidable but the Respondents did not take timely steps.

That the Claimants also referred the contents of the letter dated 10.7.95 (page 885) wherein it was observed that the Superintending Engineer appreciated the working of the Claimants and also observed that there was no fault of the contractor and they have successfully completed the work. The Claimants further stated that, they had incurred heavy expenditure on overheads of the lapses and default of the Respondents.

As against this the Respondents stated that there was poor planning of the claimants and also contended that since the compensation has been levied under Clause 2 of the agreement therefore, claim of the claimants deserves to be rejected.

That on record it is conclusively proved that the Respondents committed breach of contract as they failed to discharge their obligations in time resulting in prolongations did not deny the deployment of the tools and plants and machinery at site besides watch and ward during the prolongation."

8. It is important to note that before the Division Bench, the learned counsel for the DDA conceded that this being a pure finding of fact, he would not be challenging it before the Division Bench.

9. Of the total claim of Rs.37.28 lakhs, the learned Arbitrator awarded an amount of Rs.23.39 lakhs. Further, the learned Arbitrator has laboriously gone through all the evidence and answered each claim giving reasons for the same.

10. By a judgment dated 3rd April, 2006, the learned Single Judge of the High Court of Delhi dismissed the objections of the DDA and upheld the award. In an appeal filed under Section 37 of the Arbitration Act, vide the impugned judgment dated 8th February, 2012, a Division Bench of the High Court of Delhi set aside the judgment of the Single Judge on claims 9, 10, 11 and 15, and negatived these claims in toto. Further, claims 12 and 13 were scaled down doing "rough and ready justice". Resultantly, the awarded amount of Rs.7,20,000/- was scaled down to Rs. 5,57,137.50/-.

...

12. Mr. Amarendra Sharan, learned Senior Advocate appearing on behalf of the DDA has relied strongly on clause 10C and clause 22 to support the judgment of the Division bench and has further argued that there has been duplication so far as certain claims are concerned. He argued that an award in the teeth of clause 10C and clause

22 would be a jurisdictional error which would vitiate the award.

...

57. We come now to the arguments of Mr. Sharan in support of the Division Bench judgment. The learned counsel strongly relied on clause 10C and clause 22. These two clauses are set out as below:

Clause 10C of the agreement reads as follows:

"If during the progress of the works, the price of any material incorporated in the works, (not being a material supplied from the Engineer- in-Charge's stores in accordance with Clause 10 hereof and/or wages of labour increases as direct result of the coming into force of any fresh law, or statutory rule or order (but not due to any changes in sales tax) and such increase exceed ten per cent of the price and/or wages prevailing at the time of receipt of the tender for the work, and contractor thereupon necessarily and properly pays in respect of the material (incorporated in the work) such increased price and/or in respect of labour engaged on the execution of the work such increased wages, then the amount of the contract shall accordingly be varied provided always that any increase so payable is not, in the opinion of the Superintending Engineer (whose decision shall be final and binding) attributable to delay in execution of the contract within the control of the contractor. Provided, however, no reimbursements shall be made if the increase is not more than 10% of the said prices/wages and if so the reimbursements shall be made only on the excess over 10% and provided further that any such increase shall not be payable if such increase has become operative after the contract or extended date of completion of the work in question.

If during the progress of the works, the price of any material incorporated in the works (not being a material supplied from the Engineer- in-Charge's stores in accordance with Clause 10 hereof) and/or wages of labour is decreased as a direct result of the coming into force of any fresh law or statutory rule or order (but not due to any changes in sales tax) and such decrease exceeds ten per cent of the prices and/or wages prevailing at the time of receipt of the tender for the work, Delhi Development Authority shall in respect of materials incorporated in the work (not being materials supplied from the Engineer-in-Charge's stores in accordance with Clause 10 hereof) and/or labour engaged on the execution of the work after the date of coming into force of such law, statutory rule or order be entitled to deduct from the dues of the contractor such amount as shall be equivalent of difference between the prices of materials and/ or wages as they prevailed at the time of receipt of tender for the work minus ten per cent thereof and the prices of

materials and/ or wages of labour on the coming into force of such law, statutory rule or order.

The contractor shall for the purpose of this condition keep such books of account and other documents as are necessary to show the amount of any increase claimed or reduction available and shall allow inspection of the same by a duly authorised representative of Delhi Development Authority and further shall, at the request of the Engineer- in-Charge furnish, verified in such a manner as the Engineer-in-Charge may require. Any document, so kept and such other information as the Engineer-in-Charge may require.

The contractor shall, within a reasonable time of his becoming aware of any alteration in the prices of any such materials and/ or wages of labour give notice thereof to the Engineer-in- Charge stating that the same is given in pursuance to the condition together with all information relating thereto which he may be in a position to supply."

Clause 22 reads as follows:

"All sums payable by way of compensations under any of these conditions shall be, considered as reasonable compensation to be applied to this use of Delhi Development Authority without reference to the actual loss or damage sustained, and whether or not any damage shall have been sustained.

Specifications and Conditions:

1. The contractor must get acquainted with the proposed site for the works and study specifications and conditions carefully before tendering. The work shall be executed as per programme approved by the Engineer-in-Charge. If part of site is not available for any reasons or there is some unavoidable delay in supply of materials stipulated by the Departments, the programme of construction shall be modified accordingly and the contractor shall have no claim for any extras or compensation on this account."

58. Clause 10C concerns itself with the price of material incorporated in the works or wage or labour increases. It has been seen that claims 9, 10 and 11 have nothing to do with either of the aforesaid subjects. In seeking to apply this clause to claim 15, the simple answer is that this clause will not apply when a claim for damages is made. Further, the Arbitrator considered this clause in detail and only awarded amounts under this clause in excess of 10 percent as required by the clause when it came to awarding amounts under claims 2, 3 and 4, which fell within the ambit of clause 10C. The DDA in the appeal before the Division Bench correctly gave up any challenge to these claims as has been recorded in paragraph 4 of the order under appeal.

59. The Arbitrator has dealt with this clause in detail and has construed and applied the same correctly while dealing with claims 2, 3 and 4 and has obviously not applied the said clause to claims 9, 10, 11 and 15 as no occasion for applying the same arose. The award cannot be faulted on this ground.

60. Also, so far as clause 22 is concerned, the DDA did not raise any argument based on this clause before the learned Arbitrator. However, it must in fairness be stated that it was argued before the learned Single Judge. In para 15 of his judgment, the learned Judge sets the clause out and then follows a judgment of the High Court of Delhi in Kochhar Construction Works v. DDA & Anr., (1998) 2 Arb. LR 209. Apart from the fact that a learned Single Judge of the same court is bound by a previous judgment of a Single Judge, the conclusion of the learned Single Judge that if the appellant is at fault and the contract is prolonged for an inordinate period of time, it cannot be said that the respondents cannot be compensated for the same is correct. Besides, this point was not urged before the Division Bench and must be taken to be given up. Mr. Sharan cited Harsha Constructions v. Union of India & Ors., (2014) 9 SCC 246 to say that in respect of excepted matters, no arbitration is possible, and that this being a jurisdictional point, he should be allowed to raise it before us. Unfortunately for Mr. Sharan, the clause does not operate automatically. It only operates if an objection is taken stating that part of the site is not available for any reason. Nowhere has the DDA stated which part of the site is not available for any reason. Further, the learned Single Judge's reason for rejecting an argument based on this clause also commends itself to us as the object of this clause is that no claim for extras should be granted only if there is an unavoidable delay. We have seen that the delay was entirely avoidable and caused solely by the DDA itself.

61. One more point needs to be noted. An argument was made before the learned Single Judge that there has been a duplication of claims awarded. The learned Judge dealt with this argument as follows:

"18. Learned counsel for the petitioner in respect of ground P, once again makes a reference to the issue that there is overlapping of the claim. I am unable to accept the submission made by the learned counsel. The consequence of delay may have more than one ramifications including the cost of material the supervision required at the site, the inability of the contractor to utilise the manpower at some other place, the inability of the contractor to make, profits from some other contract by utilisation of the same resources. All these aspects are liable to be considered. The Arbitrator has considered the claims separately and has dealt with, claims 9, 10, 11 & 15 together. Claims 12 & 13 have been thereafter dealt with on the same principles since it was found that it was not the respondent, who was

responsible for the delay for a period of 25 months beyond the stipulated condition of 9 months.

There is thus no question of overlapping in different heads and the grievance of the petitioner is rejected."

62. The Single Judge is clearly right. We have gone through all the 15 claims supplied to us and we find that none of these claims are in fact overlapping. They are all contained under separate heads. This argument, therefore, must also fail.

The law laid down in Central Bank of India Vs.

Virudhunagar Steel Rolling Mills Limited and others (10

supra), in the considered opinion of this Court, is squarely

applicable to the case on hand.

28. Findings on Claims 4 and 7: Respondent No.1

claimed under claim No.4, a sum of Rs.1,19,30,185-75 ps

plus service tax and interest and respondent No.1 claimed

the said amount towards expenditure met by him in

executing 12 number of extra items. Under claim No.7 i.e.

fixation of higher BOQ rates for the additional scope of work

entrusted to the claimant for JH 44A to JH 49A and making

payment thereof, respondent No.1 herein claimed a sum of

Rs.44,00,714.48 ps. Against claim No.4, the Arbitral

Tribunal granted Rs.79,27,943/- + service tax and interest,

and against claim No.7, the Arbitral Tribunal granted

Rs.23,33,236/- + service tax and interest.

29. The principal contention advanced by the learned

counsel for the appellant as regards these claims is, in view

of clause 21.3 of the General Conditions of Contract, these

claims are excepted matters, as such, the contractor is not

entitled for the said claims and the Arbitral Tribunal has no

jurisdiction to entertain these claims for arbitration under

Clause 28 of the General Conditions of Contract. In this

context, it may be appropriate to refer to clause 21.0 of the

Special Conditions of Contract, which reads as under:

"EXCEPTED MATTERS :

In the above clauses, wherever it is mentioned that the decision/instructions/opinions of the Engineer/Employer will be final/binding and are conclusive, these will also be treated as excepted matters as defined in General Conditions of Contract."

The Tribunal, while dealing with these claims,

categorically found that having breached the contract, it

would not be open for the appellant herein to take the plea of

the excepted matters. Learned Special Judge, by placing

reliance on the judgment of the Hon'ble Supreme Court in Mc

Dermott International INC Vs. Burn Standard Co. Ltd., and

others reported in (2006) 11 SCC 181 and Hind Construction

Contractors by its Sole Proprietor Bhikamchand Mulchand Jain

(Dead) by LRs. Vs. State of Maharashtra reported in AIR 1979

Supreme Court 720, also turned down the plea of the

appellant Company, as regards the plea of the excepted

matters. Clause 26.3 of the General Conditions of Contract

reads as follows:

"Clause 26.3 : Valuation at the date of termination of Contract: The Engineer shall as soon as may be practicable after any such entry and expulsion by the Employer fix and determine ex-party or by or after reference to the parties or after such investigation or enquiries as he may think fit to make or institute and shall certify what amount (if any) had at the time of such entry and expulsion been reasonably earned by or would reasonably accrue to the Contractor in respect of work then actually done by him under the Contract and what was the value of any unused or partially used materials, any Constructional plant and Temporary works which have been deemed to become the property of the Employer Under Clause No.9.29 herein above upon the Site."

30. In support of his contentions and submissions,

learned Senior Counsel appearing for the appellant seeks to

place reliance on the judgment of the Hon'ble Apex Court in

the case of M/s. Mitra Guha Builders (India) Company Vs. Oil

and Natural Gas Corporation Limited (7 supra). In the said

judgment, paragraphs 16 to 29 read as under:

"16. In order to appreciate the claim of ONGC in levying the damages in terms of Clause 2, it is necessary to refer to Clause 2 of the agreement which reads as under:-

"Clause 2: Compensation for Delay The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be deemed to

be the essence of the contract on the part of the contractor and shall be reckoned from the 15th day after the date on which the order to commence the work is issued to the contractor. The work shall throughout the stipulated period of the contract be proceeded with all due diligence and the contractor shall pay compensation on amount equal to ½ % per week as the Superintending Engineer (whose decision in writing shall be final) may decide on the amount of the contract, value of the whole work as shown in the agreement, for every week that the work remains uncommenced, or unfinished, after the proper dates. After further to ensure good progress during the execution of the work, the contractor shall be bound in all cases in which the time allowed for any work exceeds, one month (save the special jobs) to complete one-eighth of the work, before one-fourth of the whole time allowed under the contract has elapsed and three- eights of the work, before one-half of such time has elapsed, and three-fourth of such time has elapsed. However, for special jobs if a time schedule has been submitted by the contractor and the same has been accepted by the Engineer-in-Charge, the Contractor shall comply with the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay as compensation an amount equal to ½ % per week as the Superintending Engineer (whose decision in writing shall be final) may decide on the said contract value if the whole work for every week that the due quantity of works remains incomplete provided always that the entire amount of compensation to be paid under the provisions of the clause shall not exceed ten per cent (10%) of the tendered cost of the work as shown in the tender." [Emphasis added]

17. A reading of Clause 2 makes it clear that the Superintending Engineer has been conferred with not only a right to levy compensation; but it also provides a mechanism for determination of the liability/quantum of

compensation. The very Clause 2 itself would show that such a decision taken by the Superintending Engineer shall be final. The finality clause in the contract in terms of Clause 2 makes the intention of the parties very clear that there cannot be any further dispute on the said issue between the parties; much less before the arbitrator.

18. Clause 25 of the agreement - Settlement of disputes by Arbitration, reads as under:-

"Clause 25 - Settlement of disputes by Arbitration If any dispute, difference, question or disagreement shall, at any time, hereafter arises between the parties hereto or the respective representatives or assigns in connection with or arising out of the contract, or in respect of meaning of specifications, design, drawings, estimates, scheduled, annexures, orders, instructions, the construction, interpretation of this agreement, application of provisions thereof or anything hereunder containing or arising hereunder or as to rights, liabilities or duties of the said parties hereunder or arising hereunder any matter whatsoever incidental to this contract or otherwise concerning the works of execution or failure to execute the same whether during the progress of work or stipulated/extended period or before or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by a Director of ONGC Ltd. at the time of dispute. There will be no objection to any such appointment that the arbitrator so appointed is an employee of ONGC Ltd. or that he had to deal with the matters to which the contract relates and that in the course of this duties as ONGC Ltd. employees, lie had expressed views on all or any of the matters in dispute or difference. If the arbitrator to whom the matter is originally referred dies or refuses to act or resigns for any reason from the position of arbitrator, it shall be lawful for the Director of ONGC Ltd. to appoint another person to act as arbitrator in the manner aforesaid. Such

person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor if both the parties consent to this effect, failing which the arbitrator will be entitled to proceed de-novo. ...........

It is also a term of the contract that if the contractor(s) do/does not make any demand for arbitration in respect of any claim(s) in writing within 90 days of receiving the intimation from the corporation that the bill is ready for payment, the claim of the contractor(s) will be deemed to have been waived and absolutely barred and the Corporation shall be discharged and released of all liabilities under the contract in respect of these claims.

The decision of the Superintending Engineer regarding the quantum of reduction as well as his justification in respect of reduced rates for sub-standard work, which may be decided to be accepted, will be final and would not be open to arbitration. ...........". [Emphasis added]

19. The intention of the parties to exclude some of the decisions of the Superintending Engineer from the purview of arbitration is clearly seen from the abovesaid clause. Claim No.6 made by the appellant is to declare that the penalty imposed by ONGC under Clause 2 was illegal and unwarranted and the amount withheld by ONGC was payable to the appellant. The very prayer to declare the amount levied by the Superintending Engineer as illegal is against the tenor of the terms of the contract (Clause 2) between the parties. By virtue of the finality clause in the contract, any decision taken by the Superintending Engineer in levying compensation cannot be referred to an arbitrator. The parties have consciously agreed to have finality to the decision of the Superintending Engineer and the same cannot be frustrated by challenging the same as illegal. Any other meaning to the finality clause in the contract and allowing further adjudication by another authority would make the

agreed Clause 2 and Clause 25 of the agreement meaningless and redundant.

20. As held by the Division Bench of the High Court, whether there was delay in completion of work and the levy of liquated damages, could not have been determined by the arbitrator. Vide letters dated 08.12.1999, 09.12.1999, 17.12.1999, 11.02.2000 and 17.04.2000, ONGC called upon the respondent/contractor to remove the defects failing which it would get the defects remedied at his cost. According to ONGC, the completion time was extended without prejudice to the right of ONGC to recover compensation in accordance with Clause 2 of the agreement. The contention of ONGC is that by the letter dated 15.05.2001, the contractor was put on notice that in exercise of the power conferred on the Superintending Engineer under Clause 2, the contractor is liable to pay 10% of the contract value by way of compensation. The contractor was informed by the said letter dated 15.05.2001 that the compensation is levied on him for the period of 39 weeks at half per cent per week subject to maximum of 10% of the contract value and that the actual amount of compensation shall be worked out on checking the final bill and the same shall be recovered by ONGC from the final bill. By the subsequent letter dated 25.05.2001, the claimant was informed that the final bill is ready and the claimant was required to reconcile the final bill after adjusting the compensation.

21. A reading of the other terms of the contract would further indicate that under Clauses 13 and 14 of the agreement, the parties have agreed for payment of compensation and non-payment of compensation in certain situations. Significantly, Clauses 13 and 14 of the agreement do not have any finality clause which indicates that any dispute arising out of such clauses may be a dispute referable to arbitration. However, in respect of levy of compensation for the delay, Clause 2 of the

agreement specifically makes the decision of the Superintending Engineer, final. The entire contract between the parties and the terms thereon have to be read as a whole to decide the rights and liabilities of the parties arising out of the contract. In claim No.6, the contractor has sought for declaration "that the penalty under Clause 2 imposed by ONGC was illegal and unwarranted and the amount withheld by ONGC was payable to the contractor with interest @ 24%". Claim No.6 sought for by the contractor is clearly in violation of Clause 2 of the agreement between the parties, in and by which, the parties have agreed that the decision taken by the Superintending Engineer levying compensation shall be final. The finality clause in the contract cannot therefore be frustrated by calling upon the arbitrator to decide on the correctness of levy of compensation by the Superintending Engineer.

22. While considering similar contractual provisions viz. Clause 2 of the agreement as in the present case, in Vishwanath Sood v. Union of India and Another (1989) 1 SCC 657, the Supreme Court held as under:-

"8. ......... As we see it, clause 2 contains a complete machinery for determination of the compensation which can be claimed by the Government on the ground of delay on the part of the contractor in completing the contract as per the time schedule agreed to between the parties. The decision of the Superintending Engineer, it seems to us, is in the nature of a considered decision which he has to arrive at after considering the various mitigating circumstances that may be pleaded by the contractor or his plea that he is not liable to pay compensation at all under this clause. In our opinion the question regarding the amount of compensation leviable under clause 2 has to be decided only by the Superintending Engineer and no one else.

9. ........After referring to certain judicial decisions regarding the meaning of the word "final" in various statutes, the Division Bench concluded that the finality cannot be construed as excluding the jurisdiction of the arbitrator under Clause 25. We are unable to accept this view. Clause 25 which is the arbitration clause starts with an opening phrase excluding certain matters and disputes from arbitration and these are matters or disputes in respect of which provision has been made elsewhere or otherwise in the contract. These words in our opinion can have reference only to provisions such as the one in parenthesis in clause 2 by which certain types of determinations are left to the administrative authorities concerned. If that be not so, the words "except where otherwise provided in the contract" would become meaningless. We are therefore inclined to hold that the opening part of clause 25 clearly excludes matters like those mentioned in clause 2 in respect of which any dispute is left to be decided by a higher official of the Department. Our conclusion, therefore, is that the question of awarding compensation under clause 2 is outside the purview of the arbitrator and that the compensation, determined under clause 2 either by the Engineer-in-charge or on further reference by the Superintending Engineer will not be capable of being called in question before the arbitrator.

10. ....... But we should like to make it clear that our decision regarding non-arbitrability is only on the question of any compensation which the Government might claim in terms of Clause 2 of the contract. We have already pointed out that this is a penalty clause introduced under the contract to ensure that the time schedule is strictly adhered to. It is something which the Engineer-in-charge enforces from time to time when he finds that the contractor is being recalcitrant, in order to ensure speedy and proper observance of the terms of the contract. This is not an undefined power. The amount of

compensation is strictly limited to a maximum of 10 per cent and with a wide margin of discretion to the Superintending Engineer, who might not only reduce the percentage but who, we think, can even reduce it to nil, if the circumstances so warrant. It is this power that is kept outside the scope of arbitration. We would like to clarify that this decision of ours will not have any application to the claims, if any, for loss or damage which it may be open to the Government to lay against the contractor, not in terms of clause 2 but under the general law or under the Contract Act. As we have pointed out at the very outset so far as this case is concerned the claim of the Government has obviously proceeded in terms of clause 2 and that is the way in which both the learned Single Judge as well as the Division Bench have also approached the question. Reading clauses 2 and 25 together we think that the conclusion is irresistible that the amount of compensation chargeable under clause 2 is a matter which has to be adjudicated in accordance with that clause and which cannot be referred to arbitration under clause 25". [Underlining added]

23. The ratio of the above decision squarely applies to the present case. Once the parties have decided that certain matters are to be decided by the Superintending Engineer and his decision would be final, the same cannot be the subject matter of arbitration.

24. In this regard, reliance was also placed upon Food Corporation of India v. Sreekanth Transport (1999) 4 SCC 491 wherein, the Supreme Court interpreted Clause 12 of the agreement thereon. Clause 12 of the agreement in Food Corporation of India reads as under:-

"The decisions of the Senior Regional Manager regarding such failure of the contractors and their liability for the losses etc. suffered by the Corporation shall be final and binding on the contractors....".

25. While interpreting the clause on 'excepted matters', in Food Corporation of India, the Supreme Court held as under:- "3. "Excepted matters" obviously, as the parties agreed, do not require any further adjudication since the agreement itself provides a named adjudicator -- concurrence to the same obviously is presumed by reason of the unequivocal acceptance of the terms of the contract by the parties and this is where the courts have been found out lacking in their jurisdiction to entertain an application for reference to arbitration as regards the disputes arising therefrom and it has been the consistent view that in the event of the claims arising within the ambit of excepted matters, the question of assumption of jurisdiction of any arbitrator either with or without the intervention of the court would not arise. The parties themselves have decided to have the same adjudicated by a particular officer in regard to these matters; what these exceptions are however are questions of fact and usually mentioned in the contract documents and form part of the agreement and as such there is no ambiguity in the matter of adjudication of these specialised matters and being termed in the agreement as the excepted matters.

........

9. ......... The Food Corporation, therefore, as a matter of fact desired an adjudication of their claim to the extent of Rs 1,89,775 together with interest at the rate of 18 per cent per annum from the civil court rather than relying on the adjudicatory process available in the contract itself through their own Senior Regional Manager. The agreement as noticed above expressly provides that the adjudication shall be effected by the Senior Regional Manager and by no other authority and the decision, it has been recorded in the agreement, of the Senior Regional Manager would be final and binding on the parties.....".

26. In the present case, the parties themselves have agreed that the decision of the Superintending Engineer in levying compensation is final and the same is an "excepted matter" and the determination shall be only by the Superintending Engineer and the correctness of his decision cannot be called in question in the arbitration proceedings and the remedy if any, will arise in the ordinary course of law.

27. The learned counsel for the appellant has relied upon Bharat Sanchar Nigam Limited and another v. Motorola India (P) Ltd. (2009) 2 SCC 337 and by referring to Clause 16(2) in the concerned agreement submitted that for quantification of liquidated damages, first of all, there has to be a delay and for ascertaining as to who was responsible for the delay, such an issue will be within the jurisdiction of the arbitrator. The learned ASG however, submitted that in the present case, Clause 2 of the agreement is not only a mechanism for quantification of liquidated damages, but Clause 2 also makes the contractor liable for payment of the same and in terms of Clause 2 of the agreement, the decision of the Superintending Engineer is final and the present case is therefore, distinguishable from BSNL's case.

28. As rightly contended by the learned ASG, in BSNL's case, Clause 16(2) of the agreement does not create any kind of liability to pay liquidated damages; but only provides for entitlement of BSNL to collect the damages in case of any delay in supply on the part of the supplier under Clause 16(2). While interpreting Clause 16(2) and Clause 21 of the contract which was under consideration in BSNL's case, in paras (23) and (26), the Supreme Court held as under:-

"23. The question to be decided in this case is whether the liability of the respondent to pay liquidated damages and the entitlement of the appellants, to collect the same from the respondent is an excepted matter for the purpose of

Clause 20.1 of the general conditions of contract. The High Court has pointed out correctly that the authority of the purchaser (BSNL) to quantify the liquidated damages payable by the supplier Motorola arises once it is found that the supplier is liable to pay the damages claimed. The decision contemplated under Clause 16.2 of the agreement is the decision regarding the quantification of the liquidated damages and not any decision regarding the fixing of the liability of the supplier. It is necessary as a condition precedent to find that there has been a delay on the part of the supplier in discharging his obligation for delivery under the agreement.

...........

Quantification of liquidated damages may be an excepted matter as argued by the appellants, under Clause 16.2, but for the levy of liquidated damages, there has to be a delay in the first place. In the present case, there is a clear dispute as to the fact that whether there was any delay on the part of the respondent. For this reason, it cannot be accepted that the appointment of the arbitrator by the High Court was unwarranted in this case. Even if the quantification was excepted as argued by the appellants under Clause 16.2, this will only have effect when the dispute as to the delay is ascertained. Clause 16.2 cannot be treated as an excepted matter because of the fact that it does not provide for any adjudicatory process for decision on a question, dispute or difference, which is the condition precedent to lead to the stage of quantification of damages."

29. In BSNL's case, Clause 16 provided for entitlement of the party to recover liquidated damages. In Clause 16(2), the phrases used "value of delayed quantity" and "for each week of delay" clearly show that it is necessary to find out whether there has been delay on the part of the supplier in discharging his obligation. Thus, in BSNL's case, in determining whether there is delay or not, a process of

adjudication is envisaged. Per contra, in the present case, Clause 2 of the agreement is a complete mechanism for determination of liability. The right to levy damages for delay is exclusively conferred upon the Superintending Engineer and Clause 2 of the present agreement is a complete mechanism for determination of liability and when such compensation is levied by the Superintending Engineer, the same is final and binding. The parties have also consciously agreed that for the delay caused, the Superintending Engineer shall levy the compensation of the amount equal to half per cent and the said amount shall not exceed from 10% of the cost of the work and the determination by the Superintending Engineer is final and cannot be the subject matter of arbitration. In claim No.6, the prayer sought for by the contractor to declare the compensation levied by the Superintending Engineer as illegal is contradictory to the agreed terms between the parties. So far as the liquidated damages determined and levied, by virtue of Clause 2, is out of the purview of the arbitration especially in view of the fact that under the very same clause, the parties have agreed that the decision of the Superintending Engineer shall be final."

With due respect to the judgment of the Hon'ble Apex

Court, in the contract, which fell for consideration before the

Hon'ble Supreme Court in the above-referred judgment, there

was a clause in the contract which stipulated that the

decision of the Engineer should be final, and in the instant

case, the same is not the contingency even as per clause

No.21.3 of the General Conditions of Contract. Therefore, the

said judgment of the Hon'ble Apex Court would not render

any assistance to the case of the appellant herein.

31. Coming to the judgments relied on, by the learned

counsel for respondent No.1, in J.G.Engineers Private Limited

v. Union of India and another16, the Hon'ble Apex Court, at

paragraphs 18 to 20, 22 to 24, held in the following manner.

"18. Thus what is made final and conclusive by clauses (2) and (3) of the agreement, is not the decision of any authority on the issue whether the contractor was responsible for the delay or the department was responsible for the delay or on the question whether termination/rescission is valid or illegal. What is made final, is the decisions on consequential issues relating to quantification, if there is no dispute as to who committed breach. That is, if the contractor admits that he is in breach, or if the Arbitrator finds that the contractor is in breach by being responsible for the delay, the decision of the Superintending Engineer will be final in regard to two issues. The first is the percentage (whether it should be 1% or less) of the value of the work that is to be levied as liquidated damages per day. The second is the determination of the actual excess cost in getting the work completed through an alternative agency. The decision as to who is responsible for the delay in execution and who committed breach is not made subject to any decision of the respondents or its officers, nor excepted from arbitration under any provision of the contract.

19. In fact the question whether the other party committed breach cannot be decided by the party alleging breach. A contract cannot provide that one party will be the arbiter to decide whether he committed breach or the other party committed breach. That question can only be decided by only an adjudicatory forum, that is, a court or an Arbitral Tribunal.

20. In State of Karnataka vs. Shree Rameshwara Rice Mills (1987 (2) SCC 160) this Court held that adjudication upon the issue relating to a breach of condition of contract and adjudication of assessing damages arising out of the breach are two different and distinct concepts and the right to assess damages arising out of a breach would not include a right to adjudicate upon as to whether there was any breach at all. This Court held that one of the parties to an agreement cannot reserve to himself the power to adjudicate whether the other party has committed breach. This court held :

"Even assuming for argument's sake that the terms of Clause 12 afford scope for being construed as empowering the officer of the State to decide upon the question of

(2011) 5 SCC 758

breach as well as assess the quantum of damages, we do not think that adjudication by the other officer regarding the breach of the contract can be sustained under law because a party to the agreement cannot be an arbiter in his own cause. Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication should be by an independent person or body and not by the other party to the contract. The position will, however, be different where there is no dispute or there is consensus between the contracting parties regarding the breach of conditions. In such a case the officer of the State, even though a party to the contract will be well within his rights in assessing the damages occasioned by the breach in view of the specific terms of Clause 12. We are, therefore, in agreement with the view of the Full Bench that the powers of the State under an agreement entered into by it with a private person providing for assessment of damages for breach of conditions and recovery of the damages will stand confined only to those cases where the breach of conditions is admitted or it is not disputed." ...

22. In view of the above, the question whether appellant was responsible or respondents were responsible for the delay in execution of the work, was arbitrable. The arbitrator has examined the said issue and has recorded a categorical finding that the respondents were responsible for the delay in execution of the work and the contractor was not responsible. The arbitrator also found that the respondents were in breach and the termination of contract was illegal. Therefore, the respondents were not entitled to levy liquidated damages nor entitled to claim from the contractor the extra cost (including any escalation in regard to such extra cost) in getting the work completed through an alternative agency. Therefore even though the decision as to the rate of liquidated damages and the decision as to what was the actual excess cost in getting the work completed through an alternative agency, were excepted matters, they were not relevant for deciding claims 1, 3 and 11, as the right to levy liquidated damages or claim excess costs would arise only if the contractor was responsible for the delay and was in breach.

23. In view of the finding of the arbitrator that the appellant was not responsible for the delay and that the respondents were responsible for the delay, the question of respondents levying liquidated damages or claiming the excess cost in getting the work completed as damages, does not arise. Once it is held that the contractor was not responsible for the delay and the delay occurred only on account of the omissions and commissions on the part of the respondents, it follows that provisions which make the decision of the Superintending Engineer or the Engineer- in-Charge final and conclusive, will be irrelevant. Therefore, the Arbitrator would have jurisdiction to try

and decide all the claims of the contractor as also the claims of the respondents. Consequently, the award of the Arbitrator on items 1, 3 and 11 has to be upheld and the conclusion of the High Court that award in respect of those claims had to be set aside as they related to excepted matters, cannot be sustained.

Re : Question (ii)

24. The arbitrator had considered and dealt with claims (1), (2, 4 and 5), (6), (7 and 8), (9) and (11) separately and distinctly. The High Court found that the award in regard to items 1, 3, 5 and 11 were liable to be set aside. The High Court did not find any error in regard to the awards on claims 2, 4, 6, 7, 8 and 9, but nevertheless chose to set aside the award in regard to these six items, only on the ground that in the event of counter claims 1 to 4 were to be allowed by the arbitrator on reconsideration, the respondents would have been entitled to adjust the amounts awarded in regard to claims 2, 4, 6, 7, 8 and 9 towards the amounts that may be awarded in respect of counter claims 1 to 4; and that as the award on counter claims 1 to 4 was set aside by it and remanded for fresh decision, the award in regard to claim Nos. 2, 4, 6, 7, 8 and 9 were also liable to be set aside."

In Bharat Sanchar Nigam Limited & another v. Motorola

India Private Limited17, it is held thus: (paragraphs 5, 9, 18,

23 and 32).

" It is the case of the appellants that the respondent had failed to complete phase I and phase II of the project within the schedule as provided in the tender document, and therefore, liquidated damages were imposed by the Tamil Nadu Circle of the appellant on 21st of May, 2004 under clause 16.2 of the tender document, quantification of which was beyond the purview of the arbitration agreement.

...

The High Court, as noted herein earlier, by the impugned judgment allowed the arbitration request of the respondents holding that the imposition of liquidated damages by the appellant was not an "excepted matter" and therefore, subject to arbitration. It is this judgment of the High Court, which is impugned in this appeal, in respect of which leave has already been granted.

...

(2009) 2 SCC 337

We may keep on record that the appellants alleged that respondents had not completed phase I and phase II of the project within the schedule as provided in the tender document whereupon the appellants had to impose liquidated damages and invoke clause 16.2 of the tender document. But the respondents refuted these allegations. The contention of the respondent in this case was that the delay, if any, was caused due to the appellant's delay in supplying necessary inputs to the respondent. So the respondent contends that it had performed its part of the contract in time and the blame for delay lies on the appellant. Thus it is to be noted that there is a dispute between the parties on the question whether any breach was committed in this case.

...

The question to be decided in this case is whether the liability of the respondent to pay Liquidated Damages and the entitlement of the appellant, to collect the same from the respondent is an excepted matter for the purpose of clause 20.1 of the General Conditions of contract. The High Court has pointed out correctly that the authority of the purchaser (BSNL) to quantify the Liquidated Damages payable by the supplier Motorolla arises once it is found that the supplier is liable to pay the damages claimed. The decision contemplated under clause 16.2 of the agreement is the decision regarding the quantification of the Liquidated Damages and not any decision regarding the fixing of the liability of the supplier. It is necessary as a condition precedent to find that there has been a delay on the part of the supplier in discharging his obligation for delivery under the agreement.

...

In view of the discussions made hereinabove, we hold that the disputes raised by the respondents are arbitrable and not excepted from the scope of arbitration."

32. In view of the above reasons, this Court finds

sufficient force in the submission of the learned counsel for

respondent No.1 that having regard to clause 26.3 of the

General Conditions of Contract, contention of the appellant

that these are excepted matters and there cannot be any

claim for the same in view of clause 21.3 of the General

Conditions of Contract, is not tenable, and it cannot be said

that these claims are excepted matters. Therefore, this

Court is not inclined to interfere with the findings recorded

by the Special Judge and the Arbitral Tribunal in respect of

the claims 4 and 7 in the absence of any patent illegality and

in the absence of necessary requirements and contingencies

as stipulated under Section 34 of the Act, 1996.

33. Finding on Claim No.13:

Claim No.13 reads as follows:

Additional expenditures met by the claimant for development of fabrication site to the extent possible as the allotted fabricated site area was slushy pond. Claim amount: Rs.4,15,000/- (+) service tax and interest.

Against the abovesaid claim, the Arbitral Tribunal

granted Rs.3,81,800/-. The essence of the stance of the

learned Senior Counsel appearing for the appellant as

regards this claim is that in view of Clause 9.3 of the General

Conditions of Contract, respondent No.1 is not entitled for

any amount under this head. In this connection, it would be

apposite to refer to the said clause No.9.3 of the General

Conditions of Contract, which reads as follows:

"Clause No.9.3: Inspection of Site: The Contractor shall visit, inspect and examine the Site and its surroundings and shall satisfy himself before submitting the Tender as to the various facilities available at the Site for the receipt storage and custody of the materials, as to the nature of the ground and sub-soils (as far as it is practicable) the form and nature of the Site, the conditions, the quantities and nature

of the work and materials, facilities necessary for transportation, erection, testing and other works and the means of access to the Site, the accommodation and other facilities that may be required and, in general, shall himself obtain all necessary information as to the working conditions, risk, contingencies and other circumstances which may influence or affect his Tender. The Tenderer shall note that no claim on this ground will be admissible."

The learned Arbitral Tribunal, while dealing with this

claim, took into consideration the obligation on the part of

the employer to make available the land, free of charge,

within and/or near the employer's work site for the

contractor to put up stores, site fabrication yard, office, etc.

as required for execution of the contract. The Tribunal also

took into consideration the photographs depicting the site

conditions and found that it was not possible to be used for

keeping the raw material, for carrying out fabrication and

stacking fabricated structures, and found further that

movement of heavy cranes was impossible and it was difficult

event to walk. Having regard to the findings of the learned

Arbitral Tribunal, on factual situations, in the absence of any

patent illegality, this Court is not inclined to meddle with the

Award rendered by the learned Arbitral Tribunal, as

confirmed by the learned Special Judge.

34. Finding on claim No.14: The sum and substance

of the case of the appellant as regards this claim is that in

view of Clause 28.4 of the General Conditions of Contract

read with Section 31(7) (a) of the Arbitration and Conciliation

Act, 1996, the Arbitral Tribunal has no jurisdiction to award

the interest. It is also the submission of the learned counsel

for the appellant that the Arbitral Tribunal grossly erred in

granting interest under the provisions of the MSMED Act,

2006 and the said Act cannot be pressed into service and the

Arbitral Tribunal being creature of the statute i.e. the 1996

Act, it cannot usurp the jurisdiction of the Facilitation

Council as per the MSMED Act, 2006. In this context, it may

be appropriate to refer Clause 28.4 of the General Conditions

of Contract.

"Clause 28.4: No interest shall be awarded by the Arbitrator in any Arbitration proceedings."

35. In order to adjudicate claim No.14, it would also

be appropriate to refer to the provisions of the Micro, Small

and Medium Enterprises Development Act, 2006. The said

legislation, enacted by the Parliament, came into force on

18.07.2006, and the Parliament brought the said legislation

to provide for facilitating the promotion and development and

enhancing the competitiveness of micro, small and medium

enterprises and the matters connected therewith or

incidental thereto. Section 2(d) and (n) of the Act, 2006

define the terms 'buyer' and 'supplier' and the said provisions

of law read as follows:

"Section 2(d): "Buyer" means whoever buys any goods or receives any services from a supplier for consideration.

Section 2(n): "Supplier" means a micro or small enterprise, which has filed a memorandum with the authority referred to in sub-section (1) of section 8, and includes,--

(i) the National Small Industries Corporation, being a company, registered under the Companies Act, 1956 (1 of 1956);

(ii) the Small Industries Development Corporation of a State or a Union territory, by whatever name called, being a company registered under the Companies Act, 1956 (1 of 1956);

(iii) any company, co-operative society, trust or a body, by whatever name called, registered or constituted under any law for the time being in force and engaged in selling goods produced by micro or small enterprises and rendering services which are provided by such enterprises;"

Sections 15 to 18 of the said enactment read as under:

"Section 15: Liability of buyer to make payment.-- Where any supplier supplies any goods or renders any services to any buyer, the buyer shall make payment therefor on or before the date agreed upon between him and the supplier in writing or, where there is no agreement in this behalf, before the appointed day: Provided that in no case the period agreed upon between the supplier and the buyer in writing shall exceed forty-five days from the day of acceptance or the day of deemed acceptance.

Section 16: Date from which and rate at which interest is payable.--Where any buyer fails to make payment of the amount to the supplier, as required

under section 15, the buyer shall, notwithstanding anything contained in any agreement between the buyer and the supplier or in any law for the time being in force, be liable to pay compound interest with monthly rests to the supplier on that amount from the appointed day or, as the case may be, from the date immediately following the date agreed upon, at three times of the bank rate notified by the Reserve Bank.

Section 17. Recovery of amount due.--For any goods supplied or services rendered by the supplier, the buyer shall be liable to pay the amount with interest thereon as provided under section 16.

Section 18. Reference to Micro and Small Enterprises Facilitation Council.--

(1) Notwithstanding anything contained in any other law for the time being in force, any party to a dispute may, with regard to any amount due under section 17, make a reference to the Micro and Small Enterprises Facilitation Council.

(2) On receipt of a reference under sub-section (1), the Council shall either itself conduct conciliation in the matter or seek the assistance of any institution or centre providing alternate dispute resolution services by making a reference to such an institution or centre, for conducting conciliation and the provisions of sections 65 to 81 of the Arbitration and Conciliation Act, 1996 (26 of 1996) shall apply to such a dispute as if the conciliation was initiated under Part III of that Act.

(3) Where the conciliation initiated under sub-section (2) is not successful and stands terminated without any settlement between the parties, the Council shall either itself take up the dispute for arbitration or refer it to any institution or centre providing alternate dispute resolution services for such arbitration and the

provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) shall then apply to the dispute as if the arbitration was in pursuance of an arbitration agreement referred to in sub-section (1) of section 7 of that Act.

(4) Notwithstanding anything contained in any other law for the time being in force, the Micro and Small Enterprises Facilitation Council or the centre providing alternate dispute resolution services shall have jurisdiction to act as an Arbitrator or Conciliator under this section in a dispute between the supplier located within its jurisdiction and a buyer located anywhere in India.

(5) Every reference made under this section shall be decided within a period of ninety days from the date of making such a reference."

Section 24 of the said Act reads as follows:

Section 24. Overriding effect.--The provisions of sections 15 to 23 shall have effect notwithstanding anything inconsistent therewith contained in any other law for the time being in force.

36. While referring to the provisions of Section 16 of

the said Act, it is submitted by the learned counsel for

respondent No.1 that respondent No.1 is entitled for interest

as stipulated under Section 16 of the MSMED Act, 2006, i.e.,

three times of the bank rate. In terms of the said legislation,

the Arbitral Tribunal granted interest in favour of respondent

No.1 herein. To substantiate his submission as regards the

applicability of this enactment, learned counsel for

respondent No.1 places reliance on the judgment of the

Bombay High Court in M/s. Steel Authority of India Ltd., and

another Vs. Micro, Small Enterprise Facilitation Council,

through Joint Director of Industries, Nagpur Region, Nagpur

reported in AIR 2012 Bombay 178. Relevant portion of the

said judgment at paragraph 11, reads as follows:

"11. Having considered the matter, we find that Section 18 (1) of the Act, in terms allows any party to a dispute relating to the amount due under Section 17 i.e. an amount due and payable by buyer to seller; to approach the facilitation Council. It is rightly contended by Mrs. Dangre, the learned Addl. Government Pleader, that there can be variety of disputes between the parties such as about the date of acceptance of the goods or the deemed day of acceptance, about schedule of supplies etc. because of which a buyer may have a strong objection to the bills raised by the supplier in which case a buyer must be considered eligible to approach the Council. We find that Section 18(1) clearly allows any party to a dispute namely a buyer and a supplier to make reference to the Council. However, the question is; what would be the next step after such a reference is made, when an arbitration agreement exists between the parties or not. We find that there is no provision in the Act, which negates or renders an arbitration agreement entered into between the parties ineffective. Moreover, Section 24 of the Act, which is enacted to give an overriding effect to the provisions of Section 15 to 23-including section 18, which provides for forum for resolution of the dispute under the Act-would not have the effect of negating an arbitration agreement since that section overrides only such things that are inconsistent with Section

15 to 23 including Section 18 notwithstanding anything contained in any other law for the time being in force. Section 18(3) of the Act in terms provides that where conciliation before the Council is not successful, the Council may itself take the dispute for arbitration or refer it to any institution or centre providing alternate dispute resolution and that the provisions of the Arbitration and Conciliation Act, 1996 shall thus apply to the disputes as an arbitration in pursuance of arbitration agreement referred to in Section 7 (1) of the Arbitration and Conciliation Act, 1996. This procedure for arbitration and conciliation is precisely the procedure under which all arbitration agreements are dealt with.

We, thus find that it cannot be said that because Section 18 provides for a forum of arbitration an independent arbitration agreement entered into between the parties will cease to have effect. There is no question of an independent arbitration agreement ceasing to have any effect because the overriding clause only overrides things inconsistent therewith and there is no inconsistency between an arbitration conducted by the Council under Section 18 and arbitration conducted under an individual clause since both are governed by the provision of the Arbitration Act, 1996."

37. According to the learned Senior Counsel appearing

for the appellant, since the Arbitral Tribunal, in the instant

case, exercised the jurisdiction under the provisions of the

1996 Act, the Tribunal is bound by the terms of the contract

and Sections 37 and 31 (7) (a) of the 1996 Act. It is not in

dispute that as per Clause 28.4 of the General Conditions of

Contract, as referred to, supra, grant of interest by the

Arbitral Tribunal, is prohibited. Section 31(7) (a) of the Act,

1996 reads as follows:

"Section 31 (7) (a): Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made."

38. Admittedly, in the instant case, there is a

condition in the form of Clause 28.4 of the General

Conditions of Contract, which bars the grant of interest by

the Arbitral Tribunal. Therefore, this Court finds sufficient

force in the submission of the learned senior counsel

appearing for the appellant that in view of Section 31(7)(a) of

the Act, 1996 read with Clause 28.4 of the General

Conditions of Contract, the Arbitral Tribunal is prohibited

from granting interest. In the considered opinion of this

Court, the provisions of the MSMED Act, 2006, cannot be

made applicable to the arbitration proceedings initiated

under the Arbitration and Conciliation Act, 1996. In the

considered opinion of this Court, the judgment sought to be

relied upon by the learned counsel for respondent No.1 in

M/s. Steel Authority of India Ltd., and another Vs. Micro,

Small Enterprise Facilitation Council, through Joint Director of

Industries, Nagpur Region, Nagpur reported in AIR 2012

Bombay 178 would not render any assistance to respondent

No.1 herein to sustain its stand on claim No.14. In this

context, it may be appropriate to refer to the judgments cited

by the learned Senior Counsel appearing for the appellant.

(a) in Union of India v. Ambica Construction (8 supra),

wherein the Hon'ble Supreme Court held thus: (paragraphs

25 to 28)

"25. A 3-Judge Bench of this Court in Union of India v. Bright Power Projects (India) Pvt. Ltd. (2015) 9 SCC 695 has considered the provisions contained in section 31(7)(a) of the Arbitration and Conciliation Act, 1996 and considered the words "unless otherwise agreed by parties" in the said section and held that the Arbitrator is bound by the terms of the contract so far as award of interest from the date of execution to the date of award is concerned. This Court considered clause 13(3) of the contract and came to the conclusion that once agreed that contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed the interest. The Arbitrator while awarding interest failed to consider the provisions of section 31(7)(a) and binding nature of clause 13(3) of the terms of agreement. With respect to section 31(7)(a) of the Arbitration & Conciliation Act, 1996 this Court in Union of India v. Bright Power Projects (supra) has observed thus :

"18. Section 31(7)(a) of the Act ought to have been read and interpreted by the Arbitral Tribunal before taking any decision with regard to awarding interest. The said section, which has been reproduced hereinabove, gives more respect to the agreement entered into between the parties. If the parties to the agreement agree not to pay interest to each other, the Arbitral Tribunal has no right to award interest pendente lite." Section 31(7)(a) of the 1996 Act confers power on Arbitrator to award interest pendente lite, "unless otherwise agreed by parties". Thus, it is clear from the provisions contained in section 31(7)(a) that the contract between the parties has been given importance and is binding on the Arbitrator. Arbitration clause is also required to be looked into while deciding the power of the Arbitrator and in case there is any bar contained in the contract on award of interest, it operates on which items and in the arbitration clause what are the powers conferred on Arbitrator and whether bar on award of interest has been confined to certain

period or it relates to pendency of proceedings before Arbitrator.

26. In Sree Kamatchi Amman Constructions (supra), it was observed that the words "unless otherwise agreed by the parties" in section 31 of new Act of 1996 clarify that Arbitrator is bound by the terms of contract for award of interest pendente lite. It was also held thus :

"19. Section 31(7) of the new Act by using the words "unless otherwise agreed by the parties" categorically clarifies that the Arbitrator is bound by the terms of the contract insofar as the award of interest from the date of cause of action to the date of award. Therefore, where the parties had agreed that no interest shall be payable, the Arbitral Tribunal cannot award interest between the date when the cause of action arose to the date of award.

20. We are of the view that the decisions in Engineers-De- Space-Age (supra) and Madnani (supra) are inapplicable for yet another reason. In Engineers- De-Space-Age (supra) and Madnani (supra) the Arbitrator had awarded interest for the pendente lite period. This Court upheld the award of such interest under the old Act on the ground that the Arbitrator had the discretion to decide whether interest should be awarded or not during the pendente lite period and he was not bound by the contractual terms insofar as the interest for the pendente lite period. But in the instant case the Arbitral Tribunal has refused to award interest for the pendente lite period. Where the Arbitral Tribunal has exercised its discretion and refused award of interest for the period pendente lite, even if the principles in those two cases were applicable, the award of the Arbitrator could not be interfered with. On this ground also the decisions in Engineers-De-Space- Age (supra) and Madnani (supra) are inapplicable. Be that as it may."

27. This Court in Union of India v. Krafters Engineering & Leasing Pvt. Ltd. (2011) 7 SCC 279 has held that by a provision in the agreement, the jurisdiction of the Arbitrator to award interest can be excluded. This Court considered the nature of the claim vis-à-vis the provision contained in the relevant clause.

28. It is apparent from various decisions referred to above that in G.C. Roy (supra) Constitution Bench of this Court has laid down where agreement expressly provides that no interest pendente lite shall be payable on amount due. The arbitrator has no power to award interest. In N.C. Budharaj (supra) a Constitution Bench has observed that in case there is nothing in the arbitration agreement to exclude jurisdiction of arbitrator to entertaining claim for interest, the jurisdiction of arbitrator to consider and award interest in respect to all periods is subject to section 29 of the Act. In Hindustan Construction Co.

Ltd. (supra) this Court has followed decision in G.C. Roy (supra) and laid down that on the basis of principles of section 34 arbitrator would have the power to award pendente lite interest also. In B.N. Agarwalla (supra), this Court has again followed G.C. Roy (supra) and Hindustan Construction Co. Ltd. (supra) with respect to power of arbitrator to award pendente lite interest and it was held that arbitrator has power to award interest. In Harish Chandra (supra) this Court interpreted the clause 1.9 which provided that no claim for interest or damages will be entertained by the Government in respect to any moneys or balances which may be lying with the Government. It was held that there was no provision which could be culled out against the contractor not to claim interest by way of damages before the arbitrator on the relevant items placed for adjudication. In Ferro Concrete Construction (P) Ltd. (supra) this Court considered clause 4 containing a stipulation that no interest was payable on amount withheld under the agreement. It was held that clause 4 dealt with rates, material and workmanship did not bar award of interest by the arbitrator on claims of the contractor made in the said case. In Sayeed Ahmed (supra) this Court has emphasized that award of interest would depend upon nature of the clause in the agreement. In Bright Power Projects (India) Pvt. Ltd. (supra) this Court has considered the expression "unless otherwise agreed by parties" employed in section 31(7)(a) of the Act of 1996 and laid down that in case contract bars claim of interest contractor could not have claimed interest. The provision of section 31(7)(a) of the Act of 1996 is binding upon the arbitrator. In Sree Kamatchi Amman Constructions (supra) similar view has been taken."

(b) In Sri Chittaranjan Maity v. Union of India (9 supra),

it is held as follows: (paragraphs 14 to 20).

"14. The total interest awarded by the Arbitral Tribunal is Rs.12,44,546/- which includes interest for the pre- reference period and also pendente lite interest. Section 31(7)(a) of the 1996 Act provides for payment of interest, as under:

"31(7)(a) - Unless otherwise agreed by the parties, where and insofar as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made." In this Section, a specific provision has been created, whereby if the agreement prohibits

award of interest for the pre-award period (i.e. pre- reference and pendente lite period), the Arbitrator cannot award interest for the said period.

15. Admittedly, the GCC, governing the contract between the parties, contains a clause which bars the payment of interest, which is as under:

"16(2) - No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract, but government securities deposit in terms of sub-clause (1) of this clause will be repayable (with) interest accrued thereon."

16. Relying on a decision of this Court in M/s. Ambica Construction vs. Union of India (2017) SCC OnLine SC 678, (C.A.No.410 of 2008, disposed of on 26.04.2017) learned senior counsel for the appellant submits that mere bar to award interest on the amounts payable under the contract would not be sufficient to deny payment on pendente lite interest. Therefore, the Arbitrator was justified in awarding the pendente lite interest. However, it is not clear from M/s. Ambica Construction (supra) as to whether it was decided under The Arbitration Act, 1940 (for short 'the 1940 Act') or under the 1996 Act. It has relied on a judgment of Constitution Bench in Secretary, Irrigation Department, Government of Orissa and Others. vs. G.C. Roy (1992) 1 SCC 508. This judgment was with reference to the 1940 Act. In the 1940 Act, there was no provision which prohibited the Arbitrator from awarding interest for the pre-reference, pendente lite or post award period, whereas the 1996 Act contains a specific provision which says that if the agreement prohibits award of interest for the pre-award period, the Arbitrator cannot award interest for the said period. Therefore, the decision in M/s. Ambica Construction (supra) cannot be made applicable to the instant case.

17. Learned Additional Solicitor General appearing for the respondent submits that the position of law for cases covered under the 1996 Act, i.e. if agreement prohibits award of interest then the grant of pre-award interest is impermissible for the Arbitrator, has been reiterated by this Court in various judgments.

18. In Sayeed Ahmed and Company vs. State of Uttar Pradesh and Others (2009) 12 SCC 26, this Court noted that the 1940 Act did not contain any provision relating to the power of the Arbitrator to award interest. However, now a specific provision has been created under Section 31(7)(a) of the 1996 Act. As per this Section, if the agreement bars payment of interest, the Arbitrator cannot award interest from the date of cause of action till the date of award. The Court has observed that in regard to the provision in the 1996 Act, the difference between pre- reference period and the pendente lite interest has disappeared insofar as award of interest by the Arbitrator

is concerned. Section 31(7)(a) recognizes only two periods, i.e. pre-award and post-award period.

19. In Sree Kamatchi Amman Constructions vs. Divisional Railway Manager (Works), Palghat and Others (2010) 8 SCC 767, this Court was dealing with an identical case wherein Clause 16 of the GCC of Railways had required interpretation. This is the same Clause 16(2) of the GCC prohibiting grant of interest which is also applicable in the facts of the present case. The Court held that where the parties had agreed that the interest shall not be payable, the Arbitral Tribunal cannot award interest between the date on which the cause of action arose to the date of the award.

20. In Union of India vs. Bright Power Projects (India) Private Limited (2015) 9 SCC 695, a three-Judge Bench of this Court, after referring to the provisions of Section 31(7)(a) of the 1996 Act, held that when the terms of the agreement had prohibited award of interest, the Arbitrator could not award interest for the pendente lite period. It has been held thus:

"10. Thus, it had been specifically understood between the parties that no interest was to be paid on the earnest money, security deposit and the amount payable to the contractor under the contract. So far as payment of interest on government securities, which had been deposited by the respondent contractor with the appellant is concerned, it was specifically stated that the said amount was to be returned to the contractor along with interest accrued thereon, but so far as payment of interest on the amount payable to the contractor under the contract was concerned, there was a specific term that no interest was to be paid thereon.

11. When parties to the contract had agreed to the fact that interest would not be awarded on the amount payable to the contractor under the contract, in our opinion, they were bound by their understanding. Having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal." Therefore, it is clear that the appellant is not entitled for any interest on the amount awarded by the Arbitral Tribunal."

Accordingly, this point as regards claim No.14 is

answered in favour of the appellant and against respondent

No.1.

39. Yet another contention of the learned Senior

Counsel appearing for the appellant is that the Award stands

vitiated as the Tribunal did not have a person with judicial

knowledge. In order to rebut the said contention, learned

counsel for respondent No.1 places reliance on the following

judgments of the Hon'ble Apex Court :

(a) In Municipal Corporation of Delhi v. M/s. Jagannath

Ashok Kumar and another (10 supra), wherein it is held thus:

(paragraphs 4 and 5).

"4. In this case, there was no violation of any principles of natural justice. It is not a case where the arbitrator has refused cogent and material factors to be taken into consideration. The award cannot be said to be vitiated by non-reception of material or non-consideration of the relevant aspects of the matter. Appraisement of evidence by the arbitrator is ordinarily never a matter which the Court questions and considers. The parties have selected their own forum and the deciding forum must be conceded the power of appraisement of the evidence. In the instant case, there was no evidence of violation of any principle of natural justice. The Arbitrator in our opinion is the sole judge of the quality as well as quantity of evidence and it will not be for this Court to take upon itself the task of being a judge of the evidence before the arbitrator. It may be possible that on the same evidence the Court might have arrived at a different conclusion than the one arrived at by the arbitrator but that by it self is no ground in our view for setting aside the award of an arbitrator.

5. It is familiar learning but requires emphasis that section 1 of the Evidence Act, 1872 in its rigour is not intended to apply to proceedings before an arbitrator. P.B. Mukharji, J. as the learned Chief Justice then was, expressed the above view in Haji Ebrahim Kassam Cochinwall v. Nothern Indian oil Industries Ltd., A.I.R. 1951 Calcutta 230 and we are of the opinion that this represents the correct statement of law on this aspect. Lord Goddard, C.J. in Mediterranean & Eastern Export Co. Ltd. v. Fortress Fabrics Ltd., [1948] 2 All E.R. 186 observed at pages 188/189 of the report as follows: "A man in the trade who is selected for his experience would be likely to know and indeed to be expected to

know the fluctuations of the market and would have plenty of means of informing himself or refreshing his memory on any point on which he might find it necessary so to do. In this case according to the affidavit of sellers they did take the point before the Arbitrator that the Southern African market has slumped. Whether the buyers contested that statement does not appear but an experienced Arbitrator would know or have the means of knowing whether that was so or not and to what extent and I see no reason why in principle he should be required to have evidence on this point any more than on any other question relating to a particular trade. It must be taken I think that in fixing the amount that he has, he has acted on his own knowledge and experience. The day has long gone by when the Courts looked with jealousy on the jurisdiction of the Arbitrators. The modern tendency is in my opinion more especially in commercial arbitrations, to endeavour to uphold Awards of the skilled persons that the parties themselves have selected to decide the questions at issue between them. If an Arbitrator has acted within the terms of his submission and has not violated any rules of what is so often. called natural justice the Courts should be slow indeed to set aside his award.""

(b) In P.R.Shah, Shares and Stock Brokers Private

Limited v. B.H.H. Securities Private Limited & others (11

supra), wherein it is held thus: (paras 22 and 23 )

"22. The appellant contends that the arbitration had used personal knowledge to decide the matter. Attention was drawn to the following observation in the award by the majority :

"Also, it is known fact which is known to the arbitrators that as per the market practice such kind of transactions of one Broker takes place with another Broker either in their own name or in their firm's name or in the name of different entity which is also owned by the member." Same way these transactions are done by respondent no.2 (appellant herein) in the name of respondent no.1 (second respondent herein)."

23. An arbitral tribunal cannot of course make use of their personal knowledge of the facts of the dispute, which is not a part of the record, to decide the dispute. But an arbitral tribunal can certainly use their expert or technical knowledge or the general knowledge about the particular trade, in deciding a matter. In fact, that is why in many arbitrations, persons with technical knowledge, are appointed as they will be well-versed with the practices and customs in the respective fields. All that the

arbitrators have referred is the market practice. That cannot be considered as using some personal knowledge of facts of a transaction, to decide a dispute."

Therefore, the contention contra advanced by the

learned Senior Counsel appearing for the appellant, cannot

stand for judicial scrutiny and is, accordingly, rejected.

40. For the aforesaid reasons, the COM.CA is partly

allowed, setting aside the Award passed by the Arbitral

Tribunal vide Award dated 15.12.2006, as confirmed in the

order and decree dated 16.08.2019 passed by the Court of

the Special Judge for trial and disposal of the Commercial

Disputes, Visakhapatnam, in CAOP No.38 of 2017 (Old AAP

No.306 of 2017) to the extent of Claim No.14 and in respect

of all other claims, this Appeal is dismissed. No costs.

Miscellaneous Petitions pending, if any, in this case

shall stand closed.

__________________ A.V.SESHA SAI, J

__________________ J.UMADEVI , J.

22.09.2021 Siva/DRK

THE HON'BLE SRI JUSTICE A.V.SESHA SAI AND THE HON'BLE MS JUSTICE J.UMADEVI

COMCA No.11 OF 2019

.09.2021 Siva/DRK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter