Citation : 2021 Latest Caselaw 3863 AP
Judgement Date : 1 October, 2021
IN THE HIGH COURT OF ANDHRA PRADESH: AMARAVATI
HON'BLE Mr. JUSTICE ARUP KUMAR GOSWAMI, CHIEF JUSTICE
ARBITRATION APPLICATION No.110 of 2018
(Through Video-Conferencing)
M/s. Global Agency, represented by its Managing
Partner, 172, 1st Cross, 1st Block, BSK 3rd Stage,
3rd Phase, Bengaluru - 560085 ... Applicant
Versus
The General Manager, South Central Railway,
Rail Nilayam, Secunderabad - 500071, and another ... Respondents
Counsel for the applicant : Mr. Prasad Rao Vemulapalli
Counsel for the respondent : Mr. P. Bhaskar
ORAL JUDGMENT
Dt. 01.10.2021
Heard Mr. Prasad Rao Vemulapalli, learned counsel for the
applicant as well as Mr. P. Bhaskar, learned counsel for the
respondents.
2. By this application filed under Section 11(5) and (6) of the
Arbitration and Conciliation Act, 1996 (for short, "the Act of 1996") read
with the Scheme for Appointment of Arbitrator, 2000, the applicant
prays for appointment of a sole arbitrator to resolve the disputes
between the parties that had arisen in connection with Agreement
No.24/16.07.205 dated 09.10.2005.
3. Pursuant to a tender notice issued by the respondents on
28.04.2015 for the contract work of mechanized cleaning including pest
control (anti-fly and other insects) & rag picking upto home signal at
TPTY Railway Station for 2 years, i.e. 2015-2017, the applicant
participated and in such tender process, being successful, contract was 2 HCJ A.A.No.110 of 2018
awarded to it by way of Letter of Acceptance dated 09.07.2015 for the
contract value of Rs.3,21,80,397/-. Subsequent thereto, an agreement
was entered into on 09.10.2015. The period of contract was for 24
months commencing from 16.07.2015 to 15.07.2017. It was extended
for 2 months from 16.07.2017 to 15.09.2017 by a letter dated
08.07.2017. The contract, however, was completed on 31.08.2017.
4. A subsidiary agreement was entered into by the applicant and
the respondents on 13.05.2016, by which value of the contract was
reduced to Rs.2,81,68,244/- from Rs.3,21,80,397/-.
5. It is the case of the applicant that since an amount of Rs.32.00
lakh was lying with the respondents by way of securities and as the
applicant was doing similar works for other zonal railways, because of
apprehension of the said amounts being forfeited, the fear of
termination of the agreement and similar coercive acts in respect of
other ongoing works, it was compelled to sign the subsidiary
agreement and, therefore, such subsidiary agreement was executed by
it under financial duress and not out of its free volition. Accordingly, by
a letter dated 01.07.2017, the circumstances under which the
subsidiary agreement was executed, was notified to the respondents.
By a letter dated 05.04.2018, the applicant invoked arbitration clause
as per clauses 63 and 64 of the General Conditions of Contract, which
was incorporated under clause 39 of the agreement dated 09.10.2015.
In the said letter dated 05.04.2018, three claims were raised by the
applicant, which are as follows:
"Claim No.1: The difference amount of Rs.40,12,153.00/-
(Rupees Forty Lakhs twelve thousand one hundred and fifty
three only) between the original contract and revised 3 HCJ A.A.No.110 of 2018
contract without any legal basis and logical perceptive
unilaterally. The same is evident from the records available
with you.
Claim No.2: The amount of penalties imposed without any
basis time to time during the currency of the contract
amounting to Rs.63,26,643/- (Rupees sixty three lakhs
twenty six thousand six hundred and forty three only).
Claim No.3: Variation in labour wage index published by the
union ministry of Labour from the date of award to the date
of completion as applicable to this contract and the same will
be quantified at the time of submission of detailed Claim
statement."
6. Accordingly, request was made for constitution of an arbitral
Tribunal consisting of a sole arbitrator or a panel of arbitrators.
7. No response having come, the applicant has approached this
Court by filing this application.
8. In the counter-affidavit filed by the respondents, no dispute is
raised with regard to the existence of the arbitration agreement. The
plea taken for dismissal of the arbitration application on the ground of
non-maintainability is that the applicant had given a 'no claim
certificate'. It is stated that the subsidiary agreement was signed by the
applicant without any protest or objection. The letter dated 01.07.2017
giving reasons for signing the subsidiary agreement was also
addressed after one year of signing of the subsidiary agreement on
13.05.2016. The pleas that the applicant was under financial duress or
the same was not signed out of free volition, are now raised for the 4 HCJ A.A.No.110 of 2018
purpose of this case as an after-thought. It is also stated that all
payments had been received by the applicant without any protest.
9. Reliance is also placed on clause 28.2 of the General Conditions
of Contract in this regard.
10. Learned counsel for the parties had made submissions in tune
with the stand taken in the application and the counter-affidavit.
Mr. Prasad Rao, learned counsel for the applicant, submits that in view
of Section 11 (6-A) of the Act of 1996, this Court, at this stage, has to
confine examination to only existence of arbitration agreement and it is
not necessary for this Court to go into the question as to whether the
applicant had voluntarily executed 'no claim certificate' or for that
matter, the subsidiary agreement, and the same are to be decided by
the arbitral tribunal.
11. In this connection, he has relied on a decision of the Hon'ble
Supreme Court in the case of Vidya Drolia and others v. Durga
Trading Corporation, reported in (2021) 2 SCC 1.
12. I have considered the submissions of the learned counsel for the
parties and have perused the materials on record.
13. The 'no claim certificate', 'no due certificate' and 'certificate' are
all part of one single page and it is appropriate to quote the same
hereinbelow:
"NO CLAIM CERTIFICATE
I have no other claim outsourcing against S.C.
Railway towards release of my performance
Guarantee/Security Deposit and payment of the SD/PG 5 HCJ A.A.No.110 of 2018
shall the final settlement of all my claims in respect of the
SD/PG to which contract work for Mechanized Cleaning of
Tirupathi Railway Station and Premises relates under
Agreement No: 24-G/MD/52/MCC.TPTY/15-17 Dated:
16/07/2015.
NO DUES CERTIFICATE
Certificate that there are no dues to be recovered
from M/s. Global Agency, Bangalore against the contract
work for Mechanized Cleaning of Tirupathi Railway Station
and Premises relates under Agreement No. 24-
G/MD/52/MCC.TPTY/15-17 Dated: 16/07/2015.
CERTIFICATE
Certificate that the purpose to which security deposit
on amount deposited for the work which contract work for
Mechanized Cleaning of Tirupathi Railway Station and
Premises relates under Agreement No. 24-
G/MD/52/MCC.TPTY/15-17 Dated: 16/07/2015.
The security deposit may kindly be return to the
contractor, M/s. Global Agency Bangalore. No Claim
Certificate has been received from contractor. There are
no dues to be recovered from the Global Agency and there
are no pending Audit, Accounts and Vigilance objections
against the contractor as far as this agreement is
concerned."
14. Though there is no date in the 'no claim certificate', the signature
of Chief Medical Superintendent, S.C. Rly. Divn. Hospital, Guntakal, 6 HCJ A.A.No.110 of 2018
appearing below therein, appears to be 22.05.2018. It, thus, appears
that 'no claim certificate' was signed by the applicant subsequent to
issuance of the letter dated 05.04.2018. It is to be remembered that
prior to that, the applicant had written a letter dated 01.07.2017,
indicating the circumstances under which the subsidiary agreement
was executed.
15. Clause 28.2 of the general conditions of contract at page 85 of
the application, reads as follows:
"Signing of "No Claim" Certificate: The contractor
shall not be entitled to make any claim whatsoever
against the Railway under or by virtue of or arising out
of this contract, nor shall the Railway entertain or
consider any such claim, if made by the contractor
after he shall have signed a "No Claim" Certificate in
favour of the Railway, in such form as shall be
required by the Railway after the works are finally
measured up and paid for by the Railways. The
contractor shall be debarred from disputing the
correctness of the items covered by "No claim"
certificate or demanding a clearance to Arbitration in
respect thereof."
16. Mr. Prasad Rao has submitted that unless and until the 'no claim
certificate' is given by the applicant or by any contractor, dues payable
are not released and, therefore, they had no option but to execute such
certificate. Therefore, he submits that signing of the 'no claim
certificate' in the circumstances cannot be construed to be voluntary.
7 HCJ
A.A.No.110 of 2018
17. The Hon'ble Supreme Court in Vidya Drolia (supra), at
paragraphs 139, 140 and 141, observed as follows:
"139. We would not like to be too prescriptive, albeit
observe that the court may for legitimate reasons, to
prevent wastage of public and private resources, can
exercise judicial discretion to conduct an intense yet
summary prima facie review while remaining conscious
that it is to assist the arbitration procedure and not
usurp jurisdiction of the Arbitral Tribunal. Undertaking a
detailed full review or a long-drawn review at the
referral stage would obstruct and cause delay
undermining the integrity and efficacy of arbitration as a
dispute resolution mechanism. Conversely, if the court
becomes too reluctant to intervene, it may undermine
effectiveness of both the arbitration and the court.
There are certain cases where the prima facie
examination may require a deeper consideration. The
court's challenge is to find the right amount of and the
context when it would examine the prima facie case or
exercise restraint. The legal order needs a right balance
between avoiding arbitration obstructing tactics at
referral stage and protecting parties from being forced
to arbitrate when the matter is clearly non-arbitrable.
140. Accordingly, when it appears that prima facie
review would be inconclusive, or on consideration
inadequate as it requires detailed examination, the
matter should be left for final determination by the 8 HCJ A.A.No.110 of 2018
Arbitral Tribunal selected by the parties by consent. The
underlying rationale being not to delay or defer and to
discourage parties from using referral proceeding as a
ruse to delay and obstruct. In such cases a full review
by the courts at this stage would encroach on the
jurisdiction of the Arbitral Tribunal and violate the
legislative scheme allocating jurisdiction between the
courts and the Arbitral Tribunal. Centralisation of
litigation with the Arbitral Tribunal as the primary and
first adjudicator is beneficent as it helps in quicker and
efficient resolution of disputes.
141. The court would exercise discretion and refer the
disputes to arbitration when it is satisfied that the
contest requires the Arbitral Tribunal should first decide
the disputes and rule on non-arbitrability. Similarly,
discretion should be exercised when the party opposing
arbitration is adopting delaying tactics and impairing the
referral proceedings. Appropriate in this regard, are
observations of the Supreme Court of Canada in Dell
Computer Corpn. v. Union des Consommateurs &
Olivier Dumoulin [Dell Computer Corpn. v. Union des
Consommateurs & Olivier Dumoulin, 2007 SCC OnLine
Can SC 34 : (2007) 2 SCR 801 : 2007 SCC 34] , which
read: (SCC OnLine Can SC paras 85-86)
85. If the challenge requires the production and
review of factual evidence, the court should
normally refer the case to arbitration, as arbitrators 9 HCJ A.A.No.110 of 2018
have, for this purpose, the same resources and
expertise as courts. Where questions of mixed law
and fact are concerned, the court hearing the
referral application must refer the case to arbitration
unless the questions of fact require only superficial
consideration of the documentary evidence in the
record.
86. Before departing from the general rule of referral,
the court must be satisfied that the challenge to the
arbitrator's jurisdiction is not a delaying tactic and
that it will not unduly impair the conduct of the
arbitration proceeding. This means that even when
considering one of the exceptions, the court might
decide that to allow the arbitrator to rule first on his
or her competence would be best for the arbitration
process."
18. In the case of V.B. Cold Storage Private Limited v. Bajaj
Allianz General Insurance Company Limited (Arbitration Application
No.165 of 2014), which was decided on 24.09.2021, this Court was
confronted with a similar situation and a plea was set up by the
respondent that the applicant therein having executed Indemnity Bond,
Discharge Bond and consent letter as full and final settlement of all the
claims of the applicant, there was no dispute regarding any outstanding
claim and, therefore, the application was misconceived.
19. This Court at paragraphs 18, 19, 20, 22, 26 & 27, observed as
follows:
10 HCJ
A.A.No.110 of 2018
"18. Section 11 (6-A) of the Act of 1996 was inserted by
Act 3 of 2016 with effect from 23.10.2015. Section 11 (6-A)
reads as follows:
"11. (6-A) The Supreme Court or, as the case may
be, the High Court, while considering any
application under sub-section (4) or sub-section
(5) or sub-section (6), shall, notwithstanding any
judgment, decree or order of any court, confine
to the examination of the existence of an
arbitration agreement."
19. Section 11(6-A) was omitted by Act 33 of 2019.
However, Section 3 of the Amendment Act of 2019 insofar as
it pertains to this omission has not yet been brought into
force.
20. In Duro Felguera, SA v. Gangavaram Port Ltd.,
reported in (2017) 9 SCC 729, at para 48, the Hon'ble
Supreme Court had observed that the intention of the
legislature is crystal clear that the court should and need only
look into one aspect, which is the existence of an arbitration
agreement. What are the factors for deciding as to whether
there is an arbitration agreement is the next question. The
resolution to that is simple, in that it needs to be seen if the
agreement contains a clause which provides for arbitration
pertaining to the disputes which have arisen between the
parties to the agreement. At para 59, it was observed that
scope of the power under Section 11(6) of the Act of 1996
was considered in the decisions in SBP & Co. v. Patel 11 HCJ A.A.No.110 of 2018
Engg. Ltd., reported in (2005) 8 SCC 618 and Boghara
Polyfab (P) Ltd. (supra) and the said position continued till
the amendment was brought about in the year 2015. It was
emphasized that after the amendment, all that the courts
need to see is whether an arbitration agreement exists -
nothing more nothing less. It was further observed that the
legislative policy and purpose is essentially to minimise the
Court's intervention at the stage of appointing the arbitrator
and this intention as incorporated in Section 11(6-A) ought to
be respected.
22. Following Duro Felguera (supra), the Hon'ble
Supreme Court in Mayavati Trading Private Limited
(supra) observed that the law prior to the 2015 Amendment
that has been laid down by the court which would have
included going into whether accord and satisfaction has
taken place, has now been legislatively overruled. It was
held that Section 11(6-A) is confined to the examination of
the existence of an agreement and is to be understood in the
narrow sense as has been laid down in the judgment in Duro
Felguera (supra) and taking that view, the judgment in
Antique Art Exports Private Limited (supra) was overruled
as having not laid down the correct law.
26. In view of the decision rendered in Mayavati Trading
Private Limited (supra), wherein a three-Judge Bench of the
Hon'ble Supreme Court had observed that as Section 11(6-
A) is confined to the examination of the existence of an
arbitration agreement and is to be understood in a narrow 12 HCJ A.A.No.110 of 2018
sense and as the law which enabled the court to examine as
to whether accord and satisfaction had taken place has been
legislatively overruled, it will not be necessary for this Court
to go into the aforesaid question as to whether the applicant
had voluntarily executed Indemnity Bond, Discharge Bond
and also consent letter or whether the applicant had signed
such indemnity bond, discharge bond and also consent letter
unconditionally and the same is left open to be decided by
the Arbitral Tribunal.
20. In view of the above, I am of the considered opinion that the
applicant having raised various pleas with regard to execution of the
subsidiary agreement as also the execution of the 'no claim certificate',
the dispute between the parties is required to be referred to an
arbitrator as there is a valid arbitration agreement.
21. Resultantly, the Arbitration Application is allowed. Dr. Justice
B. Siva Sankara Rao is appointed as arbitrator to adjudicate the
disputes between the parties. No costs. Pending miscellaneous
applications, if any, shall stand closed.
22. The fee of the arbitrator as well as the other terms and
conditions shall be settled by the parties in consultation with the
arbitrator so appointed. Registry will send a copy of this order to
Dr. Justice B. Siva Sankara Rao in his proper address.
Sd/-
ARUP KUMAR GOSWAMI, CJ MRR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!