Citation : 2021 Latest Caselaw 2574 AP
Judgement Date : 24 July, 2021
HON'BLE SRI JUSTICE M.SATYANARAYANA MURTHY
WRIT PETITION NO.6761 OF 2021
ORDER:
One Atluri Vijaya Babu (Petitioner No.1), Atluri Venkata
Subash Babu (Petitioner No.2) along with Nalanda Estates Private
Limited filed this writ petition under Article 226 of the Constitution
of India, questioning the action of the respondents in withholding the
application of the third petitioner for building permission vide BA
No.1168/1532/B/PMLR/PRNK/2017 dated 19.05.2017 under the
guise of Andhra Pradesh Gazette Extraordinary No.850 dated
31.10.2018 issued for the proposed Inner Ring Road (IRR) as illegal,
arbitrary and violative of Articles 14, 19(1)(g) and 300-A of the
Constitution of India and contrary to the principles of natural justice
and consequently to set-aside the same and direct the respondents
to either sanction the third petitioner application vide BA
No.1168/1532/B/PMLR/PRNK/2017 dated 19.05.2017 or take
steps to acquire the subject property under the applicable land
acquisition law in vogue.
The brief facts of the case are that, Petitioner Nos. 1 & 2 along
with others are the land owners to an extent of Ac.1-20 cents in
Sy.No.479/3, Ac.0-40 cents in Sy.No.480/1C, Ac.0-28 cents in
Sy.No.480/2C and Ac.0-07 cents in Sy.No.481/4 of Poranki Village
and Panchayat, Penamaluru Mandal, Krishna District, (herein after
referred as 'subject property' for convenience).
Petitioner Nos. 1 & 2 intended to construct educational
institute/school building in the subject property and offered the
same to the third petitioner for development on mutually agreed MSM,J WP_6761_2021
terms and conditions, finally entered into Development Agreement on
10.11.2017 recording all the terms and conditions.
The third petitioner - company, in consonance with the
Development Agreement approached the second respondent/
Commissioner, AMRDA, vide BA No.1168/1532/B/PMLR/
PRNK/2017 dated 19.05.2017 for constructing an educational
institute/school building by paying requisite fee.
As per the plan submitted, the total built up area is 5805.85
sq.mts as one single block with cellar and four floors. The third
petitioner - company has complied with the mandatory requirements
for obtaining the building permission. Further, it is contended that,
as per AMRDA Zoning Regulations, the schedule property falls within
public use zone and the petitioners are entitled to construct school
building in the said property without any hindrances or conversion
procedures.
It is contended that, as per Section 110 of Capital Region
Development Act, 2014 (Repealed Act), the third petitioner -
company applied to the second respondent for obtaining building
permission. As per the said provision, the Commissioner shall
examine the plan submitted and he may accept unconditionally or
conditionally or may refuse the same within sixty (60) days. If, the
second respondent fails to accept or refuse the application within
such time, the said application for development shall be deemed as
accepted. The third petitioner - company has applied for the
approval of plan on 19.05.2017 and the second respondent by
18.07.2017 must either have accepted or refused the said
application of the petitioners. however, as the proposed building is
intended to be used as school building, as it involves thousands of MSM,J WP_6761_2021
students future, the petitioners refrained from progressing with the
development activities, taking cue from deeming provision and
diligently waited for the second respondent to give its accord and
asatisfaction in the form of building permission approval
proceedings. It is submitted that, Section 110 of CRDA Act (Repealed
Act) is replaced by Section 84 of AMRDA Act, the law applicable to
Amaravati Region as per CRDA Repeal Act No.27 of 2020. Further,
the petitioners requested the second respondent several times to
release the approved building permission and the second respondent
officials dodged the same on one pretext or the other for the past
three years and recently, when the third petitioner- company staff
insisted the second respondent to take a decision on the permission
application dated 19.05.2017, the second respondent officials
informed the third petitioner - company that subject property/
building is falling within the alignment of the proposed Inner Ring
Road and therefore, permission for the construction cannot be
accorded.
On enquiry, it was revealed that, the second respondent
intended to develop Inner Ring Road for capital region. Accordingly,
alignment of draft IRR was prepared and approved on 08.02.2017,
final draft alignment was approved on 12.02.2018. Pursuant to the
Gazette Notification, published noticed in daily newspaper, notices
were given on 17.02.2018 calling for objections/suggestions from the
public for a period of 30 days from the date of notification i.e.
18.03.2018. After considering all the objections and suggestions to
the draft plan, Respondent Nos. 1 & 2 issued Andhra Pradesh
Gazette Extraordinary No.850 dated 31.10.2018 confirming the draft
master plan for the said IRR. It is submitted that the survey MSM,J WP_6761_2021
numbers in which the subject property is situated is forming part of
the said gazette notification, however it was unclear as to what
portion of the subject property is under the alignment of the
proposed IRR.
It is contended that, since the date of confirmation of the said
master plan for the IRR vide Gazette Notification dated 31.10.2018,
till date Respondent Nos. 1 & 2 did not take any steps to acquire the
land under the alignment of IRR either in part or in full, considering
the present controversy. As such, the petitioners requested the
second respondent to approve the plan submitted by the third
petitioner - company vide application dated 19.05.2017, but no
action was taken.
In response to the application filed under Right to Information
Act, 2005 by one Mr. Lavu Shashank, the authorities gave the
following information:
S.No Information Sought Remarks
1 IRR proposal still in force Inner Ring Road Plan and extension of
or not 27 capital city roads to draft inner ring
road plan in APCRDA region was
notified vide Andhra Pradesh Gazette
extraordinary no.850 dated 31.10.2018.
2 If not in force can we Inner Ring Road Plan and extension of
proceed with the 37 capital city roads to draft inner ring
submitted plans in road plan in APCRDA region was
R.S.No.479/3, 480/1C notified vide Andhra Pradesh Gazette
and 480/2C of Poranki extraordinary No.850 dated
Village. 31.10.2018.
3 If IRR is still in force, how From the notified plan, the extent of
much of land I am going land affected under IRR tentatively is in to lose and how much will be left in RS No.479/3, 480/1C and 480/2C. In 1) RS No.479/3 - 2.6815 acres a nut shell how much 2) RS No.480/1C - 0.1728 acres land exactly are you going
3) RS No.480/2C - Not passing to acquire with exact through IRR specifications of the plan, so that I can go ahead with left out area for construction.
MSM,J WP_6761_2021
4 What is the present Inner Ring Road plan and extension of status of IRR proposal 27 capital city roads to draft inner ring and kindly provide any road plan in APCRDA region was IRR approved G.O's if notified vide Andhra Pradesh Gazette available extraordinary No.850 dated 31.10.2018.
5 IRR detailed plans are Extracts of the IRR plan enclosed.
prepared or not. If
prepared provide plan
copy of RS No.479, 480 of
Poranki Village and
surrounding radius
Despite pendency of proposal for Inner Ring Road, the land
was neither acquired nor permission was granted to this petitioner.
Therefore, keeping the building application pending for such a long
time is contrary to the provisions of APCRDA Act, APMR&UDA Act,
2016.
As per Section 95 of Andhra Pradesh Metropolitan Region and
Urban Development Authorities Act, 2016, Any land required,
reserved or designated in the Perspective Plan [PP] or Master Plan
[MP] or Infrastructure Development Plan [IDP] or Area Development
Plan or Zonal Development Plan or Land Pooling Scheme [LPS] or
Town Planning Scheme [TPS] or a Development Scheme shall be
deemed to be the land needed for public purpose within the meaning
of the Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013 (Act No. 30 of
2013) and may be acquired by the Government on the request by the
Authority or other authority or functional unit.
It is submitted that the petitioners incurred huge amount
towards stamp duty paid towards the Development Agreement dated
10.11.2017, development fee paid to the second respondent
authority on building application submitted, fee paid to the
architects for the designs of the school building proposed to be MSM,J WP_6761_2021
constructed on subject property. The third petitioner - company in
which the first petitioner is a Director had obtained all necessary
authorization from the authority concerned i.e. International
Baccalaureate for conducting classes by admitting students for
primary year programme under the name of Bloomingdale as early as
on 01.03.2016 by which time all the building designs were submitted
and the ground breaking ceremony is completed. Though the
construction is supposed to begin in 2017 and complete by January,
2018. On account of delay, the petitioners are put to serious loss and
thereby, the inaction of the respondents in withholding the
application of the third petitioner for building permission vide BA
No.1168/1532/B/PMLR/PRNK/2017 dated 19.05.2017 under the
guise of Andhra Pradesh Gazette Extraordinary No.850 dated
31.10.2018 issued for the proposed Inner Ring Road (IRR) as illegal,
arbitrary and therefore, the petitioners sought the relief as stated
supra.
The second respondent filed counter affidavit, admitting about
issue of notification for acquisition of property for Inner Ring Road
Project and pendency of the execution of project. The second
respondent denied the ownership of the subject land of Petitioner
Nos. 1 & 2 and that, the second respondent never received building
application vide BA No.1168/1532/B/PMLR/PRNK/2017 dated
19.05.2017 for construction of RCC roof, cellar, ground and 4 floors
in Sy.No.479/3, 480/1C and 480/2C situated at Poranki Village and
the same is lying with the Licensed Technical Personnel (LTP), who is
appointed by the petitioners.
The second respondent specifically contended that, the
petitioner never forwarded any application for scrutiny and the MSM,J WP_6761_2021
present writ petition is filed with an ulterior motive by suppressing
the facts. The second respondent also denied that the building
approval could not be granted as the property falls within alignment
of proposed Inner Ring Road and as such plans are to be in
accordance is denied. The Inner Ring Road was proposed in the year
2017 before the alleged application of the petitioners and the same
was approved vide Gazette No.850 dated 31.10.2018. Though the
permissions are subject to expansion of Inner Ring Road, the
petitioners file was not received and hence approval or rejection does
not arise. The respondents further contended that, there was no
inaction on their part.
It is specifically contended that, in the year 1998, a resolution
was passed by panchayat secretary for formation of road on
15.04.1998 and the same was laid with Janmabhoomi grants of
Rs.2,00,000/-. The said road was shown as part of petitioners land
in the building application. Further, the locals have decided for
formation of 33' road for their easement access and the same was
ratified by the then Village Panchayat Secretary.
Earlier, W.P.No.23384 of 2017 was filed to consider the
representations against the petitioners before granting permissions
to the petitioner and the same is pending. There are still various
complaints by the locals against the petitioner for encroaching the
existing 33' road which was laid by their contribution and once a
road is formed, the same vests with local authority. Therefore, the
petitioners are not entitled to claim any relief in the writ petition and
requested to dismiss the writ petition.
The petitioners filed rejoinder to the counter affidavit denying
the averments made in the counter affidavit, while contending that MSM,J WP_6761_2021
the building permission cannot be rejected or withheld on the ground
that the proposed road or proposed constructions when the same
has not yet been notified in Gazette Notification. (vide Channavajala
Vijaya Lakshmi v. State of Telangana 1 ). In the instant case,
building permission was arbitrarily withheld for eight months even
when there was no notification of the alignment of Inner Ring Road.
Further, upon notification, the respondent authorities must have
acquired the land by paying due compensation. The respondents
filed counter affidavit in W.P (PIL) No.179 of 2019 admitting the fact
that they do not have sufficient funds to carry out any works in
CRDA region and failure to grant permission to the petitioners to
build school, amounting to deprivation of petitioners valuable right
to property and it amounts to violation of constitutional right
guaranteed under Article 300-A of the Constitution of India. The
petitioners specifically denied the allegations made in the counter
affidavit and requested to allow the writ petition.
The petitioners filed material along with the writ petition,
whereas, the second respondent filed counter affidavit along with
certain documents, by uploading the additional material on
08.07.2021.
During hearing, Sri B. Adinarayana Rao, learned senior
counsel appearing for the petitioners contended that, when the
building application was submitted by complying all formalities, it is
the duty of the second respondent to sanction plan or reject it. But,
keeping it pending on the pretext that, Inner Ring Road project is
pending without acquiring land is nothing but depriving these
petitioners to enjoy the property as per their convenience, which is
2015 (5) ALT 620 MSM,J WP_6761_2021
violative of Article 300-A of the Constitution of India, as the
petitioners were deprived of enjoying their property. at the same
time, it is the duty of the second respondent either to reject or grant
permission to these petitioners on the building application within the
stipulated time. But, for one reason or the other, the second
respondent invented a different story that no such application was
received from the petitioners and it is pending with Licensed
Technical Personnel (LTP) appointed by these petitioners, which is
not true, as the building application was scrutinized by the
authorities of the second respondent and screenshot is placed on
record in support of it. Finally, learned Senior Counsel requested to
issue a direction as claimed in the writ petition.
Whereas, Sri Kasa Jagan Mohan Reddy, learned Standing
Counsel appearing for the second respondent would contend that,
when no building application was received by the office of the second
respondent, question of processing the same by the second
respondent does not arise and in the absence of any application,
conduct of the respondents cannot be faulted. However, as per the
material produced by the respondents, the application of the third
petitioner is pending with Licensed Technical Personnel (LTP), but
not before the office of the second respondent. Therefore, the
allegation that the second respondent did not process the building
application of the petitioners and failed to proceed with the
acquisition of the property is neither true nor correct, therefore, the
petitioner cannot compel the respondents to acquire the property.
Apart from that, 33' feet road was already laid by the panchayat, but
the petitioners encroached the said road, which is shown as part of
the road, as alleged in the counter affidavit. Therefore, the petitioners MSM,J WP_6761_2021
are not entitled to claim any relief in the writ petition and requested
to dismiss the writ petition at the stage of admission itself.
Considering rival contentions, perusing the material available
on record, the point that arises for consideration is:
"Whether the action of the respondents in withholding building application No.1168/1562/ B/PMLR/ PRNK/2017 dated 19.05.2017 is against Section 110 of APCRDA Act or Section 84 of AMRDA Act and failure to acquire the property after issuing Andhra Pradesh Gazette Extraordinary No.850 dated 31.10.2018 is illegal, arbitrary and violative of Article 300-A of the Constitution of India. If so, whether a direction be issued to complete the process of building application No.1168/1562/B/PMLR/ PRNK/2017 dated 19.05.2017 or in the alternative to acquire the property in pursuance of Andhra Pradesh Gazette Extraordinary No.850 dated 31.10.2018?
P O I N T:
The ownership of these Petitioner Nos. 1 & 2 with Petitioner
No.3 is not required to be adjudicated by this Court, in view of the
limited scope of dispute in this writ petition, though the second
respondent denied the very ownership of these petitioners at one
stage. the consistent case of these petitioners from the beginning is
that, Petitioner Nos. 1 & 2 are the owners and they entered into
Development Agreement with Petitioner No.3, who in-turn applied for
grant of building permission by complying all formalities and by
paying necessary fees for sanction of plan etc. In support of their
contention, they placed on record, building application
No.1168/1562/B/PMLR/PRNK/2017 dated 19.05.2017. When an
application is uploaded to the website of the second respondent, the
application number will automatically be generated and therefore,
the very generation of building application number
No.1168/1562/B/PMLR/PRNK/2017 dated 19.05.2017 is sufficient MSM,J WP_6761_2021
to conclude that Petitioner No.3 submitted an application seeking
permission of sanction building plan and permission to construct
school. Receipt No.1168/CH/4209/2017 dated 15.05.2017
evidencing payment of Rs.10,000/- by online vide Transaction ID
No.201793 is another additional factor to conclude that application
was submitted by Petitioner No.3. Memo No.1168/CH/4209/2017
dated 13.05.2017 also supports the case of Petitioner No.3 that
building application was submitted by Petitioner No.3. But, the
second respondent filed material papers to show that the application
is pending with Licensed Technical Person and produced a screen
shot to show that the application of Petitioner No.3 is returned to
rectify the plan. The queries mentioned by the concerned officer are
filed along with additional material of the second respondent are as
follows:
Designation Date Remarks
Town 05/06/2020 Document refusal site visit refusal technical
Planning 05:45 PM refusal.
Officer
Building 05/06/2020 Applicant may be informed to rectify the
Inspector 05:34 PM plans as per the documents and upload the
attested copies of the same by LTP and
owner. Further, applicant has to handover
RAP to the gram panchayat through
registered gift deed and submit letter from
panchayat for that effect.
Town 05/06/2020 Please put shortfalls in PDF plans & BA
Planning 05:01 PM form tabs in documents
Officer
Building 05/06/2020 The measurements shown in the submitted
Inspector 01:10 PM plans are not tallying with measurements
shown in the schedule of the ownership
documents submitted. Hence, the applicant
may be informed to rectify the plans as per
the documents. Applicant has to handover
RAP to the gram panchayat.
The remarks column in the above table is itself sufficient to conclude
that an application was submitted by Petitioner No.3. If, really, no
application was submitted by Petitioner No.3, the question of giving MSM,J WP_6761_2021
opinions to rectify the plans as per the documents or to show correct
measurements does not arise. Apart from the above material, the
allegation that 33' feet road laid with Janmabhoomi funds by the
villages also show as part of the land for proposed construction.
Therefore, the contention that, no such application was submitted by
Petitioner No.3 for grant of building permission is false on the face of
record. Thus, the respondents stooped to the extent of denying the
very submission of application, though the document produced by
the second respondent clinchingly established that Petitioner No.3
submitted an application for approval of the plan and grant of
permission for construction of school building. Therefore, the
contention of the learned Standing Counsel appearing for the second
respondent that, no building application was submitted is hereby
rejected.
When a building application was submitted seeking permission
to construct a building, it is the obligation of the second respondent
either to grant permission or to return the application for compliance
or reject the permission, within sixty days in terms of Section 110 of
CRDA Act or Section 84 of AMRDA Act, which is substituted for
CRDA, on its repeal. Therefore, Section 110 of CRDA Act is in pari
materia with Section 84 of AMRDA Act. But, the second respondent
neither granted permission nor returned the application till
05.06.2020, though the application was submitted on 19.05.2017.
Thus, the inaction of the second respondent is arbitrary and illegal.
The second bone of contest is that, the land in which the
petitioners are proposing to construct school building is falling MSM,J WP_6761_2021
within the Inner Ring Road alignment. If, really, the land is falling
within the Inner Ring Road alignment, in terms of Gazette
Notification dated 17.02.2018, keeping it pending for the last three
years without acquiring any land, indirectly refusing to grant
building permission on the ground that it is within the alignment
zone of Inner Ring Road is illegal on the face of it.
It is contended that, when a private property is shown in the
development plan and when application for construction of building
by its own was submitted, keeping the application pending without
any reasonable cause is illegal. In support of his contention, learned
Senior Counsel appearing for the petitioners placed on record the
judgment of Hon'ble Supreme Court in Raju S. Jethmalani v. State
of Maharashtra 2 . In the facts of the above judgment, Plot No. 438
belonged to private person and was shown as a garden in the
development plan of 1966. No effort was made by Municipal
Corporation or Government to acquire this plot for purpose of
developing it as a garden. When it was not acquired for the purpose
of garden owner of this land the appellants moved Government for
de-reserving. Government after resorting to necessary formalities de-
reserved land by the impugned notification, all procedures required
under 1966 Act were observed and notification was issued inviting
objections against de-reservation. Reservation had lapsed due to lack
of funds, had not taken any step to acquire land within the
stipulated statutory period. Hence, the land which is earmarked
earmarked for a particular purpose namely to promote
environmental exigencies can it be de-reserved if not acquired by
(2005) 11 SCC 222 MSM,J WP_6761_2021
state within stipulated time for the said purpose, was the question
before the Apex Court.
The Apex Court, while referring to various provisions of
Bombay Town Planning Act, 1954, Maharashtra Regional and Town
Planning Act, 1966, concluded that the Municipality has to sanction
the plan in terms of Municipalities Act, if the application complies
the formalities.
Similarly, in Channavajala Vijaya Lakshmi v. State of
Telangana (referred supra), the learned Single Judge of High Court
of Telangana held that, building permission cannot be rejected or
withheld on the ground that the proposed road or proposed
constructions when the same has not yet been notified by Gazette
Notification.
In view of the law declared by the Apex Court in Raju S.
Jethmalani case (referred supra), keeping the building application
pending ad infinitum on the ground that private land was identified
for park for public use, as an illegality and keeping the application
for building permission pending without any reasonable or justifiable
cause is contrary to the law laid down therein. In the present facts of
the case, though the third petitioner made application vide BA
No.1168/1532/B/PMLR/PRNK/2017 dated 19.05.2017, process of it
is not completed. But, it appears that in the year 2020, it was
returned for compliance of objections, in view of the screenshot
produced before this Court by the learned Standing Counsel for the
second respondent. It is not known whether the application was
represented after compliance of objections by the third petitioner. If MSM,J WP_6761_2021
the petitioner re-presented the application for building permission, it
is the duty of the second respondent authorities to complete the
process within sixty (60) days from the date of its re-presentation in
terms of Section 110 of CRDA Act or Section 84 of AMRDA Act. But,
here the second respondent did not complete the process for granting
permission to the third petitioner for construction of building, which
is contrary to the law laid down by the Apex Court in the judgment
referred supra. On this ground alone, the inaction of the second
respondent in not completing the process of application for grant of
building permission to construct a building be declared as illegality.
At the same time, this Court in Channavajala Vijaya Lakshmi
v. State of Telangana (referred supra) held that, when a building
application was made, keeping it pending for indefinite period on the
ground that the property is likely to be issued for acquisition is not a
ground. Thus, the failure of the second respondent to complete the
process of application for building permission is a grave illegality
committed by the second respondent.
Though the land is proposed to be acquired and notification is
issued on 18.03.2018 for Inner Ring Road and the land of these
petitioners is also covered by the notification, in such case, the
respondents may complete the process of acquisition, so as to enable
the these petitioners to take appropriate steps to secure alternative
premises or to de-notify the land within a reasonable time. But,
simply, the second respondent issued notification for acquiring the
land of the petitioners along with the land of others under the
Gazette Notification dated 18.03.2018. But, till date, it was not MSM,J WP_6761_2021
acquired and process of acquisition under Act No.30 of 2013 is
commenced though notification was issued on 18.03.2018.
Therefore, issue of Gazette Notification for acquisition of land and
failure to commence the process of acquisition in terms of the
provisions of Act. 30 of 2013 for unreasonable period is contrary to
the law laid down by the Hon'ble Supreme Court in Raju S.
Jethmalani v. State of Maharashtra (referred supra).
As discussed above, as laid down by the Hon'ble Supreme
Court and High Court of Judicature at Hyderabad for the State of
Telangana and Andhra Pradesh, the inaction of the second
respondent in completion of the process of building application for
sanction of plan and inaction in the process of commencement of
acquisition in terms of Act.No.30 of 2013 is illegal and arbitrary and
such act amounts to depriving these petitioners from enjoying their
property and it is in violation of Article 300-A of the Constitution of
India. Hence, I find that it is a fit case to issue a direction as claimed
by these petitioners. Accordingly, the point is answered.
In the result, writ petition is allowed, declaring the action of
the second respondent in not completing the process for grant of
permission for building application and failure to initiate the
proceedings for acquisition or commence the process of acquisition of
land notified in Gazette Extraordinary No.850 dated 31.10.2018
issued for the proposed Inner Ring Road (IRR), as illegal, arbitrary
and violative of Article 300-A of the Constitution of India.
Consequently, the second respondent is directed to complete the
process of building application submitted by the third petitioner MSM,J WP_6761_2021
within sixty days from the date of receipt of copy of this order, in
case, the building application is returned and represented by the
petitioners or in the alternative, the second respondent is directed to
commence the process of acquisition of land in terms of Act 30 of
2013 within sixty days from the date of receipt of copy of the order or
de-notify the land from proposed acquisition vide Gazette Notification
dated 31.10.2018.
Consequently, miscellaneous petitions pending, if any, shall
also stand dismissed.
_________________________________________ JUSTICE M. SATYANARAYANA MURTHY Date: 24.07.2021 SP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!