Citation : 2021 Latest Caselaw 328 AP
Judgement Date : 22 January, 2021
1
HONOURABLE SRI JUSTICE NINALA JAYASURYA
WRIT PETITION No.22765 of 2020
ORDER: (Heard and pronounced through Blue Jeans App (Virtual) mode, since
this mode is adopted on account of prevalence of COVID-19 pandemic)
Heard the learned counsel for the petitioners and learned Assistant
Government Pleader for Land Acquisition. With their consent, the writ
petition is being disposed of at the stage of admission.
The grievance of the petitioners in the present writ petition is that
the respondents have not taken any steps to deposit/pay the enhanced
compensation amounts in respect of the trees in the lands acquired from
the petitioners and that the same is illegal, void, arbitrary, unconstitutional
and violative of rights of the petitioners guaranteed under Articles 14, 21
and 300-A of Constitution of India and therefore seek a direction to the
respondents to deposit/pay the compensation to the petitioners. The
petitioners' lands in different extents as mentioned in the affidavit filed in
support of the writ petition were acquired for the construction of Kandaleru
Reservoir under Telugu Ganga Project pursuant to notification dated
31.07.1990 issued by respondents. The Land Acquisition Officer passed an
Award on 20.01.1992 and on a reference in L.A.O.P.No.33 of 1992, a
judgment was passed on 25.06.2002 enhancing the compensation. Against
the same, the petitioners preferred an appeal to the Hon'ble Common High
Court at Hyderabad in A.S.No.526 of 2004 and the compensation was
further enhanced vide judgment dated 04.10.2017. The State, against the
said judgment has not carried the matter by way of appeal to the Hon'ble
Supreme Court. Thus the quantum of compensation payable to the
petitioners has attained finality. Despite the said position, the compensation
has not been deposited to the petitioners till today.
The learned counsel for the petitioners submits that the respondents
even after lapse of more than three years failed to deposit/pay
compensation to the petitioners which has attained finality by virtue of the
order of Hon'ble Division Bench referred to above. He states that the
petitioners are discriminated in as much as some of the claimants whose
lands/trees were acquired along with the petitioners' lands have been paid
compensation, however due to reasons not known to the petitioners, they
were not paid compensation so far. The learned counsel states that due to
discrimination as well as non payment of the compensation, the petitioners
are seriously prejudiced and under those circumstances, the petitioners are
constrained to approach this Court.
The learned Assistant Government Pleader for Land Acquisition on
instructions submits that the proposals for payment of compensation are in
process, but the same would take some considerable time to finalise the
same. Accordingly, he seeks Four months time for making/depositing the
amounts towards the compensation.
Considered the submissions made by both the parties. This is a
matter where the petitioners' lands along with trees were acquired in the
year 1990 and the compensation has not been paid even after the matter
has attained finality in the year 2017 by virtue of the orders passed by the
Hon'ble Division Bench in A.S.No.526 of 2004 dated 04.10.2017. The
petitioners are entitled for the lawful compensation as determined by the
Courts of Law and they cannot be deprived of fruits of the order due to
undue delays. In the present case, the dispute with regard to
determination of compensation remained unchallenged and thus attained
finality. In such circumstances, the respondents have no other alternative,
except to deposit/pay the compensation due and payable to the petitioners.
Though this Court is not inclined to go into the aspects of the
discrimination, however finds justification in the submissions made by the
learned counsel for the petitioners that the petitioners are deprived of
enjoying the fruits of the orders passed in their favour due to delay on the
part of the respondents. Under the said circumstances, the respondents are
directed to deposit/pay the compensation in respect of the trees in the
lands acquired from the petitioners, within a period of four (4) weeks from
the date of receipt of copy of the order.
Accordingly, the Writ Petition is disposed of. There shall be no order
as to costs.
As a sequel, all the pending miscellaneous applications, if any, shall
stand closed.
______________________ NINALA JAYASURYA, J
Date: 22.01.2021.
BLV
HON'BLE SRI JUSTICE NINALA JAYASURYA
WRIT PETITION No.22765 of 2020 Dt:22.01.2021
BLV
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!