Citation : 2021 Latest Caselaw 169 AP
Judgement Date : 19 January, 2021
1
HON'BLE SRI JUSTICE D.V.S.S.SOMAYAJULU
WRIT PETITION No.20824 of 2020
ORDER:
With the consent of both the parties the Writ Petition
itself is taken up for hearing.
This Court has heard Sri N.Ashwani Kumar, learned
counsel for the petitioners and the learned Government
Pleader for Revenue appearing for the 5 respondent and Sri th
S. Lakshminarayana Reddy, learned standing counsel for the
GVMC, appearing for the 2nd to 4threspondents. The main
answering respondent is the 2ndrespondent, who has filed a
detailed counter.
This Writ Petition is filed for the following relief:
"....to issue a Writ, order or direction more particularly, one in the nature of "Writ of Mandamus: declaring the notice in Lr.Roc.No.17880/2011/ACP-Ii, dated 06.11.2020 served on the representatives of petitioners on 06.11.2020 issued by the 2 respondent nd
invoking Section 636 of APMC Act, 1955 as being illegal, arbitrary, lacking application of mind, in violation of principles of natural justice, in violation of provisions of APMC Act, 1955 and in violation of Articles 14, 19 and 300-A of the Constitution of India, and consequently to set aside the notice in Lr.Roc.No.17880/2011ACP-II dated 06.11.2020 issued by the 2 nd respondent and pass such other order or orders as this Hon'ble Court may deem fit just and proper in the circumstances of the case."
PETITIONERS' SUBMISSIONS:
Sri N.Ashwani Kumar, learned counsel for the
petitioners, draws the attention of this Court to the long
history of this case. He points out that the petitioners are the
owners of 925 Sq.yards of land or 773 Sq.Mtrs., of property
situated in ChinnaWaltair, Visakhapatnam. In the said
property they are running a hotel in the name and style of Sri
SampathVinayakaKamat Hotels. Learned counsel argues that
in the year 2011 they had submitted an application to the
2ndrespondent-Corporation for approval of the building plan
in B.A.No.14472, dated 10.11.2011 seeking permission to
construct a temporary AC Sheet roof shed in the said site. As
it was neither approved nor rejected, relying upon the
deeming provision in the HMC Act viz., Section 437, the
petitioners started the construction of the temporary shed.
When the 2ndrespondent Corporation sought to demolish the
same they filed civil suit in O.S.No.1263 of 2011 before the VI
Additional Junior Civil Judge, Visakhapatnam, which was
decreed on merits in the year 2015. An interim order initially
granted was vacated. Thereafter, C.M.A.No.14 of 2012 was
also filed and the same was allowed in April, 2012. He,
therefore, submits from the date of suit till the decree there
was an injunction, later the suit itself was decreed in April,
2015.
Learned counsel for the petitioners also submits that in
order to protect the subject property and also their customers
from dust, rain, heat and pollution they wanted to put
another temporary tensile cover (roof) over the existing floor
by using flexible and environmental friendly material. This
representation was made in July, 2018. Thereafter, learned
counsel submits that on 06.11.2020 two notices were served
at the same time i.e., at 2.20 p.m., (a) under Sections 452 and
461 of the Municipal Corporation Act and (b) a notice under
Section 636 was also served directing the petitioners to
remove the deviated portions, unauthorised first floor and
also the encroachment on the Government land within 24
hours. Learned counsel relies upon the endorsement made
on the said two notices, which are filed as material papers, to
argue that they are served at the same moment of time. He
submits that the notices are totally contrary to law, rules of
natural justice and reflect a clear case of non-application of
mind. It is argued by the learned counsel that the section
itself mandates a show cause notice and an explanation
within a reasonable time. He submits that by giving both the
notices at the same moment of time the entire process is
vitiated. He also points out that as per the judgment of the
Full Bench of the Combined High Court reported in 3 Aces,
Hyderabad v Municipal Corporation of
Hyderabad1demolition should not be carried out on holidays,
weekends etc. He also argues that the permission was
granted for construction of the temporary AC roof shed in the
site even before the suit was decreed in its totality. He relies
upon the proceedings from the Commissioner to the GVMC
and also the approval of the Principal Secretary, dated
AIR 1995 AP 17
18.10.2012, permitting the temporary constructions. He also
draws the attention of this Court to the judgment and decree
in O.S.No.1263 of 2011 and argues that once there is a decree
of competent Civil Court the 2ndrespondent Corporation
cannot take action again to demolish the structures. He also
relies upon the compilation of case law, which is filed as a
separate material paper. These are under four heads -
1. That the notice under Section 452 should be issued
before the power is exercised under Section 636 of
the Act;
2. That demolition cannot be a penalty in the absence of
public safety etc., being involved and for technical
infirmities;
3. That a counter affidavit cannot improve the contents
of the impugned proceedings; and
4. That the Commissioner cannot enquire into the title
of the property.
This is the sum and substance of the submissions made
by the learned counsel for the petitioners.
RESPONDENTS CONTENTIONS:
On behalf of the 5 respondent a counter affidavit is th
filed. It is argued that the petitioners have occupied 290
sq.yards of Government land in Sy.No.30 which is classified
as of a "Vague Poramboku" (Water channel/Water body).
Learned Government Pleader for Revenue argues that a duty
is cast upon the Courts as per the settled law on the subject
to protect the VaguPoramboku, GaddaPoramboku and other
water bodies. Learned Government Pleader argues that the
petitioners have also applied for regularisation of the
encroachment of Government land. The said proposal was
actually rejected by the Government on 25.09.2020. It is
submitted that the request for regularisation of this
encroachment was negatived on the ground that the land is
VaguPoramboku. Learned Government Pleader argues that
the petitioners have suppressed these facts in the writ
affidavit. It is also stated that in this occupied bit of land AC
roof sheds were also constructed. He relies upon the GOs.,
which are mentioned in his counter affidavit, and also the
settlement Fair Adangal, which shows that the land in
Sy.No.130 is classified as Vague. He argues that this is a
permanent record. Lastly, he submits that the circular, dated
22.04.2013, issued by the Collector and District Magistrate
clearly states that the water bodies, Tank Poramboku lands
should not be alienated, regularised etc.
The learned standing counsel for GVMC also submitted
a forcible argument in this case. According to him the first
notice under Section 452, dated 29.10.2020, was sought to be
served on the petitioners. As their staff had refused to receive
the said notice it was affixed to the wall of the premises. He,
therefore, submits that as no reply was received for the show
cause notice dated 29.10.2020 a final order was passed on
06.11.2020. He relies upon the endorsement given by the
staff of the Corporation, who stated that they have affixed the
first Notice dated 29.10.2020 on the wall of the premises. He,
therefore, argues that there is a valid service. He points out
that the self servingendorsement is made by the petitioners'
own people on their office copy stating that both the notices
were served on 06.11.2020 at 2.20 p.m., but not on the
GVMC copy
He also argues that the initial building plan that was
given was for construction of temporary AC sheet shed only.
He points out that what was permitted by the approval on
18.10.2012 was only an AC sheet roof shed, which was
subject to certain conditions. However, contrary to the same,
the 1 floor was also constructed on this shed. Therefore, it is st
his contention that what is actually built is not a temporary
AC shed as per the approved plan.
Coming to the 1stfloor that is constructed, learned
standing counsel submits that the petitioners had applied in
2018 for grant of a building permission over the existing AC
sheet shed. This was not formally granted and an
endorsement dated 08.08.2018 was issued to the petitioners
informing them that the temporary structures over the
existing AC Roof sheet shed would be permitted subject to
certain conditions. The most important of which was that the
petitioners have to obtain the change of land use from open
space / recreational area to commercial use. Learned
standing counsel argues that till date the said permission is
not been granted and despite the same the 1stfloor was
constructed and is being used for a wholly commercial
purpose viz., the running of an air conditioned restaurant in
two floors. He also submits that even if there is an approved
building plan still no activity can be carried out in the
property without obtaining an occupancy certificate. It is his
contention that obtaining of occupancy certificate is
mandatory under the law and particularly Section 455 (1) and
(2) read with 26 of the A.P. Building Rules. Relying upon the
orders passed in W.A.No.1156 of 2017 learned standing
counsel argues that the petitioners should not be permitted to
carry on commercial operations. Thereafter, coming to the
occupation of the Government land learned standing counsel
submits that the petitioners have occupied the Government
land and have constructed a shed etc., in the said occupied
Government land. They do not have right to construct in the
occupied place. He also submits that the petitioners have
suppressed all these facts and particularly W.P.No.16425 of
2014, which was filed by the very same petitioners against the
action proposed to be taken in 2014 for demolition of the
structures in the occupied land. He points out that when the
structures were sought to be demolished the petitioners
themselves, through his counsel, agreed to remove the
remaining portion of the shed within two days and also stated
that they would not raise any constructions without the prior
permission. Learned counsel points out that in total
contravention of what is agreed in this order the present
constructions were carried out. Relying upon the case law
learned standing counsel argues that the Court should be
firm in such cases and the Court should not permit the
people who have exploited the law to get any advantage. It is
his contention that any order granted would send a wrong
message to the public and he argues that there is a long line
of case law which clearly stated that the unauthorised
constructions should not be allowed to stand.
REJOINDER:
Learned counsel for the petitioners has filed a rejoinder
to the counter affidavit filed by the Municipal Corporation.
Learned counsel for the petitioners again reiterates the
arguments on similar lines and submits that the issuance of
two notices on the very same day vitiates the entire
proceedings. He, therefore, states that as the petitioners have
been in settled possession and enjoyment of the property they
should be allowed to continue.
CONSIDERATION BY THE COURT:
The first and foremost issue that has to be considered
by this Court is the effect of the Decree of the Civil Court in
O.S.No.1263 of 2011, which was passed on 07.12.2015. The
suit is filed on the ground that the plan that was submitted
for approval of construction of a temporary structure in the
land belonging to the petitioners was neither rejected nor
approved within the stipulated time. Hence, the
plaintiffs/petitioners argued that the construction is "deemed
to be approved" and cannot be demolished. Relying upon a
deeming provision the suit was filed. The matter went to trial
and after considering the oral and documentary evidence the
trial Court granted a decree by granting a permanent
injunction in favour of the plaintiffs 1 and 2 restraining the
defendant in the suit not to interfere with the structure in the
suit schedule property, which was subject to reclassification
of the plaint schedule area from CRW-III to CRZ-II. This
decree and judgment is passed for the property (temporary
shed) which is situated in the site measuring 925 sq.yards of
land. It is clearly mentioned that in the plaint schedule
(which is filed as a material paper) that within the property is
a temporary shed, which was under construction. The
boundaries of this property are described as follows:
"East : Property of Buddiga family
South : Burial ground site
West : Bheemili Beach Road
North : Drain"
This Court also notices that the permission that was
also formally granted for construction of this temporary shed
in B.A.14472/11/ACP II/G2, dated 09.11.2012. Setbacks
that were permitted are also mentioned. This is preceded by
a memo dated 18.10.2012, by which the Principal Secretary
to the Government directed the GVMC to accord permission
for construction of "Temporary constructions only" (AC sheet
roof shed). This is subject to reclassification as per the CRZ
norms and all other land use and other building regulations.
Therefore, the decree as it stands in favour of the petitioners
is for a temporary AC Roof Shed only with particular setbacks
etc., in a demarcated bit of land and for nothing more.
FIRST FLOOR AND "LAND" OCCUPIED:
Coming to the first floor that has now been added to the
building, in the writ affidavit that is filed it is clearly
mentioned that the petitioners wanted to put up temporarily
another roof over the existing floor by using flexible and
environmental friendly material. This proposal was moved on
04.07.2018. In the counter affidavit, the endorsement dated
08.08.2018 by which this request was kept in abeyance by
the respondent is filed. It is clearly stipulated that the
petitioners should comply with the following conditions:
1. The applicant has to obtain change of land use form open space & recreational use to Commercial use.
2. The applicant shall provide parking area as per prevailing norms.
3. The applicant shall obtain prior clearance form APCZMA as the subject site is falling under CRZ.
The counter affidavit filed by the Revenue Department
represented by the Tahsildar clearly shows that the proposal
submitted by the petitioners for change in land use was in
fact negatived. Learned Government Pleader pointed out that
as there is vaagu or water body the same could not be
regularisedin view of the law on the subject and also the
relevant GOs. Apart from this, this Court also notices that
the petitioners had filed W.P.No.16425 of 2014 and a copy of
the order passed on 16.06.2014 is enclosed. In that case, it
was argued that the subject land is a Government land and
that the proposals for regularisation are still pending. After
recording the submissions of the learned counsel for the
petitioners and the respondents, the High Court permitted the
petitioners to remove the unauthorised constructions. The
petitioners also gave an undertaking to the Court that they
would not raise any further constructions without prior
permission from the GVMC. The Writ Petition was closed
recording the said submissions. The order passed in
W.P.No.16425 of 2014 clearly shows that the petitioners did
not have permission for construction; that they have clearly
admitted that the part of the land (which is the subject matter
of the present dispute), is Government land which is
occupied. Therefore, as far as the first floor is concerned it is
clear that the petitioners have not been able to demonstrate
before this Court that the three conditions stipulated in the
endorsement dated 08.08.2018 have been complied with or
that the same is an approved construction in land for which
the petitioners have title.
Apart from this a lot of case law was also cited about the
Commissioner of the GVMC deciding on the title to the
property. This Court is of the opinion that in view of the clear
and categorical conduct of the petitioners - by applying for
regularisation, they are estopped from changing their stand.
The admissions recorded by this Court in W.P.No.16425 of
2014 (which is not challenged anywhere else) make it clear
that the petitioners clearly admitted that they have occupied
the Government land and pending consideration of their
application for regularisation, coercive action was being taken
by the GVMC. It was also agreed that they would not make
any further constructions without prior permission from the
GVMC. These aspects highlighted in the counter affidavits
are not controverted. This Court has to conclude that the
petitioners had occupied Government land; that they did not
get it regularised and that they had made constructions
including the first floor contrary to the undertaking given by
them in the Court also. They do not also have an approved
plan for the first floor.
OCCUPANCY CERTIFICATE:
Coming to the issue of the Occupancy Certificate the
learned standing counsel for GVMC vehemently argued that
no commercial activity can be started nor can the building be
occupied without obtaining the occupancy certificate.
Learned standing counsel relying upon the counter affidavit
filed argued that the decree passed by the Civil Court would
only apply to the temporary shed in the ground floor and that
it does not authorise the petitioners to make a construction in
the first floor and convert the land and building for
commercial purpose without prior approval and without
Occupancy Certificate. Learned counsel for the
petitioners,however, argued that the issue before this Court is
about the manner of service of two notices flouting the rules
of natural justice etc. He submits that the issue of
Occupancy Certificate is now being added as an additional
ground against the petitioners. Relying upon the case law
that he has submitted, including the well-known judgment of
Mohindhr Singh Gill and Another v Chief Election
Commissioner, New Delhi and Others2 learned counsel
argued that such an improvement should not be permitted
and that the contents of the noticesalone have to be taken
into consideration and further improvements cannot be
considered. The case law on the subject is not in doubt. But
this Court notices that the permission that has been granted
to the petitioners in 2012 clearly mentions that they are
permitted to make temporary construction only subject to the
outcome of the case and reclassification of the land from CRZ-
III to CRZ-II by ensuring that no pollution shall occur and
duly following CRZ norms, all other manuals and other
building regulations. The actual endorsement issued to the 1 st
(1978) 1 SCC 405
petitioner on 25.10.2012 also supports this contention of the
learned standing counsel for the respondents that it shall be
subject to the land use and building regulations.
While it is true that there is an order passed in favour of
the petitioners restraining the respondent from demolishing
the AC sheet in the ground floor, the fact, however, remains
that the approval for occupancy is governed by Section 455 of
HMC Act. A person who wishes to occupy and use a building
shall have to seek the completion certification. However, this
Court does not wish to go further into this area of
controversy. The GVMC has to take action as warranted by
law on this issue. It cannot be urged as a ground of defence
in the present Writ Petition. It is left open to the GVMC to
pursue the issue.
TWO NOTICES:
The last issue that survives for consideration is whether
the available record shows that both the notices under
Sections 452 and 636 were served at the same time. The
petitioners have filed copies of the notices with an
endorsement thereon that they were served on 06.11.2020 at
2.20 p.m. The endorsement is made by one Sri K.V. Subba
Raju for the petitioners. Relying on this endorsement on the
two notices, dated 29.10.2020, and 06.11.2020 learned
counsel argued that these two notices were issued at one
moment only. It is his contention that hence the entire
exercise is vitiated.
In reply to this the Corporation has come up with the
contention that the 1stnotice dated 29.10.2020 was affixed on
the wall on the premises as the petitionersstaff did not receive
the said notice. Thereafter, it is asserted that the 2ndnotice
was issued on 06.11.2020. In fact, the copy of the notice
dated 06.11.2020 filed by the GVMC shows that it was in fact
served at 2.20 p.m. However, the copy of the notice dated
29.10.2020 filed by the GVMC does not contain any
endorsement. The GVMC has also filed the proceedings by
which the Municipal staff has confirmed that they attempted
to serve the Notice dated 29.10.2020 on the hotel owners. As
per this the hotel owners were not present at that place and
the staff refused to receive the notice. Therefore, they state
that they have affixed the notice on the wall on 31.10.2020 at
10 a.m.
This Court notices that the affidavit of Sri K.V. Subba
Raju, who made the endorsement has not been filed in this
case. The affidavit in this case was sworn by the owner of the
hotel. The endorsement is made on the copies that were
served to the petitioners by Sri K.V.Subba Raju. In addition,
an endorsement is normally given in "receipt" of a
notice/document. This Court could have attached greater
value to the endorsement if it is present on the notices which
are with the respondent Municipal Corporation. The 1stnotice
dated 29.10.2020 does not contain any endorsement of the
petitioners or their representative. The 2ndnotice dated
06.11.20202 contains an endorsement of the time / date.
Hence, this Court cannot come to a firm conclusion that both
the notices were served on 06.11.2020 at the same. If the
endorsement of time / date of service are there on the
document with the GVMC, this Court could have decided
otherwise.
In addition, the GVMC specifically stated that when the
notice was sought to be served the owners were not present
and as the staff refused the same it was affixed on the wall. A
document to this effect was also filed. There is a presumption
in law that official acts are validly performed. This is not
rebutted. In the light of the above discussion this Court has
to hold that the petitioners could not prove that the notice
dated 29.102.2020 was actually served on 06.11.2020 (with
the final order).
CONCLUSION:
After examining the contents of the notices dated
29.102.2020 and 06.11.2020 this Court notices that the site
in which the sanction was given for construction is 663.71
sq.mtrs., whereas the actual site on the ground is 1065.60
sq.mtrs., All the setbacks on the front, rear and sides are
flouted. In fact, there are no set backs on the front, rear and
the side. The number of floors sanctioned was one floor.
Construction was made for ground + first floor. The road
widening area is also occupied. There is a specific reference
to the notice dated 29.10.2020 being given to the petitioners
and their failure to give a reply. The Municipal Corporation
has specifically pointed out the deviations and the occupation
of the Government land. It was also clearly specified that the
petitioners had violated the provisions of the A.P. Municipal
Corporation Act. It is specified that the petitioners should
remove the deviated portions including the unauthorised first
floor and vacate the encroachment in the Government land.
The petitioners have only got a decree in their favour for a
particular site measuring 925 sq.yards or 773 sq.meters
along with one temporary roof shed therein. All other
constructions made either in the first floor or in the
neighbouring/abutting land (which as per the petitioner's own
application for regularisation etc., is Government land) are
unauthorised constructions. The respondents 2 to 4 are
therefore given liberty to remove all the unauthorised
constructions viz., (a) the 1 floor (b) constructions made in st
the land which is occupied by the petitioners.
The impugned notice also clearly states that it is being
given in order to restore the entire building to the conformity
with the approved plan. Therefore, all the other structures,
not in conformity with the approved plan, are directed to be
removed immediately. As far as the land occupied is
concerned, the State can take steps as per law to recover
possession.
In view of the conclusions, this Court has reached that
the notices were not served on the same day this Court holds
that there is no failure of natural justice or compliance with
the provisions of Sections 452 and 636 of the Act. Therefore,
this Court holds that the case law which is peculiar to the
facts and circumstances of the respective cases is not
applicable to the present case.
Learned counsel also relied upon the lot of case law to
argue that the Commissioner cannot decide on the issue of
title etc. This was relating to the land occupied by the
petitioners. As pointed out by this Court, the Commissioner
is not "deciding" the title about the land which is occupied by
the petitioners. The petitioners own conduct in applying for
regularization of the land makes it clear that it is the
Government land. Even in the Writ Petition No.16425 of 2014
there is a clear admission that the land is Government land.
In that view of the matter, this Court holds that the said case
law is also not applicable. The conduct of the petitioners is
not free from doubt. Without approvals the second floor is
raised. Setbacks etc., are violated and the existing structure
is not as per the approved plan and within the petitioners
own site. Hence, this Court has to direct the removal of all
the unauthorized structures which are contrary to the
approved plan.
For all the above reasons, this Writ Petition is
dismissed. There shall be no order as to costs.
Consequently, the miscellaneous applications, pending
if any, shall also stand dismissed.
__________________________ D.V.S.S.SOMAYAJULU, J Date:19.01.2021 ssv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!