Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vimal Negi vs Union Of India & Others
2023 Latest Caselaw 3042 UK

Citation : 2023 Latest Caselaw 3042 UK
Judgement Date : 10 October, 2023

Uttarakhand High Court
Vimal Negi vs Union Of India & Others on 10 October, 2023
             IN THE HIGH COURT OF UTTARAKHAND
                                  AT NAINITAL
                   HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
                                          AND
                      HON'BLE SRI JUSTICE RAKESH THAPLIYAL

                  WRIT PETITION (M/B) NO. 285 OF 2023

                            10TH OCTOBER, 2023

Vimal Negi                                                         .....Petitioner.
                                        Versus

Union of India & others                                            ....Respondents.

Counsel for the Petitioner : Mr. Navnish Negi, learned counsel.

Counsel for the Respondent No.2 : Ms. Puja Banga, learned Brief Holder.

Counsel for the Respondent No.3 : Mr. S.S. Chauhan, learned counsel.

The Court made the following:

JUDGMENT:(per Hon'ble The Chief Justice Sri Vipin Sanghi)

We have heard learned counsels and proceed to

dispose of this writ petition.

2. The petitioner has preferred the present writ

petition to assail the order dated 24.09.2023, whereby the

respondents have declared the petitioner's bid to be

technically disqualified. The petitioner had participated in the

bids invited by the respondents for construction of "T04-

Khaludanda to Bhaoun to Apolosera MR & MRL 11- Listiyakhet

to Khaludanda MR under Package Nos.UT08553 & UT08554".

3. The case of the petitioner is that the petitioner is

registered as a Micro & Small Enterprise (for short 'MSE'). The

petitioner is, therefore, exempted under Government Orders

from compliance with, either the past experience

requirement, or the turnover criteria fixed under the tenders

issued by the Government. The case of the petitioner is that,

despite that being the position, the petitioner's bid has been

rejected, inter alia, on the ground that the petitioner did not

meet, either the turnover criteria, or the past experience

criteria, stipulated in Clauses 4.4A(a)(ii) and 4.4A(b) of the

Standing Bidding Documents (for short 'SBD'). The reasons

given by the respondents for rejection of the petitioner's bid

are the following:-

"1. As per SBD ITB clause 4.4A (a)(ii) Turnover is less than required.

2. As per SBD ITB clause 4.4A (b) Experience is less than required.

3. As per SBD ITB clause 4.6 Bid capacity is less than required.

4. As per SBD ITB clause 4.4B (b)(i) Lease agreement/ ownership evidence of Lab equipment and machinery is partially submitted".

4. The above would show that the petitioner has been

disqualified on four grounds, including the ground that the

petitioner did not meet either the turnover, or the past

experience criteria. The other two grounds on which the

petitioner's technical bid has been rejected, are less bid

capacity than required under Clause 4.6, and the lease

agreement/ ownership evidence of Lab equipment and

machinery is partially submitted, as required under Clause

4.4B (b)(i).

5. The bid capacity stipulated under the tender is over

Rs.19.00 crores. The manner of calculation of the bid capacity

is stipulated in Clause 4.6. The same, insofar, as it is

relevant, reads as follows:-

"The available bid capacity will be calculated as under:- Assessed Available Bid Capacity = (A*N*M - B) Where A= Maximum value of civil engineering works executed in any one year during the last five years (updated to the price level of the last year at the rate of 8 percent a year) taking into account the completed as well as works in progress.

N= Number of years prescribed for completion of the works for which bids are invited (period upto 6 months to be taken as ½ and more than 6 months as 1 in a year).

M= 2 or such higher figure not exceeding 3 as may be specified in the Appendix to ITB. B= Value, at the current price level, of existing commitments and on-going works to be completed during the period of completion of the works for which bids are invited".

6. The submission of Mr. Negi is that, for the purpose

of calculation of the bid capacity, the bidder should have past

experience which, in the formula, provided in Clause 4.6 is

indicated by 'N'. He submits that, since the petitioner is a new

enterprise and does not have past experience, the said

formula cannot apply to the petitioner. Mr. Negi submits that,

therefore, there is no requirement of any bid capacity with a

bidder who is a new MSE.

7. Mr. Chauhan, who has appeared on advance notice,

has drawn the attention of the Court to the certificate issued

in favour of the petitioner by the National Small Industries

Corporation Limited, on 04.09.2023. The said certificate,

apart from enlisting the definition of activity/ services, which

the petitioner could offer, also sets out "quantitative capacity/

services PA", which is stipulated as Rs.8.00 crore per annum.

8. Mr. Chauhan submits that the bid capacity of the

petitioner was, therefore, only Rs.8.00 crore, and even if the

formula stipulated in Clause 4.6 is not applied to the

petitioner, the petitioner still does not meet the bid capacity,

which, as aforesaid, is in excess of Rs.25.00 crores.

9. So far as the aspect of the petitioner not submitting

the proof of, either lease agreement/ ownership evidence of

Lab testing equipment is concerned, Mr. Chauhan submits

that the documents provided by the petitioner with regard to

the testing equipment, did not establish that the petitioner

was either in the ownership/ lease of the equipment.

10. In this regard, Mr. Negi has produced a photocopy

of a Bill issued by the Tilok Chand Narsingh Lal, dated

16.10.2020, issued in the name of the petitioner, in respect

of purchase of testing equipment. He states that the said

document was filed with the petitioner's bid.

11. On the other hand, Mr. Chauhan has shown to the

Court softcopy of the document provided by the petitioner

along with the tender on the letter head of Tilok Chand

Narsingh Lal, which only enlists the testing equipment without

mentioning the name of the petitioner, either as the

purchaser, or the lease of the equipment.

12. Even if, we were to agree with the submission of

Mr. Negi in relation to the three reasons for rejection of the

petitioner's technical bid, namely, that the turnover of the

petitioner is less; the experience of the petitioner is less, and'

the lease agreement/ ownership evidence of Lab equipment

and machinery is partially submitted, we are of the view that

the petitioner must fail, since the petitioner does not have the

requisite bid capacity in terms of Clause 4.6 of the SBD.

13. Admittedly, the stipulation of the bid capacity under

the tender is Rs.2575.69 Lakhs, which is the estimated

construction cost. Even if the submission of Mr. Negi were to

be accepted that the bid capacity of the petitioner cannot be

computed under Clause 4.6, since the petitioner has no past

experience, or turnover, it does not mean that such a bidder,

which belongs to a MSE category, need not have any bid

capacity at all. After all, a sizable public work is required to

be executed by the successful bidder, and it cannot be that

the bidder with either no bid capacity, or very little bid

capacity, can stake a claim to be considered for such a work.

The bid capacity of the petitioner, as per the certificated

issued to him by the National Small Industries Corporation

Limited is stated to be Rs.8.00 crores per annum. The

respondents have computed the same at Rs.1426.62 lakhs.

Either of these figures is much below the estimated cost of

work, which is also the bid capacity, required by the bidder.

14. Therefore, the rejection of the petitioner's bid on

the ground that the petitioner does not have the bid capacity,

appears to be correct, and does not call for interference. If

the petitioner is correctly disqualified even on one ground,

that is enough, and we are, therefore, not inclined to interfere

with the same. We need not examine the correctness of the

petitioner's disqualification on other grounds.

15. For the aforesaid reasons, we do not find any merit

in this petition, and the same is, accordingly, dismissed.

16. Pending application, if any, also stands disposed of.

(VIPIN SANGHI, C.J.)

(RAKESH THAPLIYAL, J.) Dated: 10th October, 2023 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter