Citation : 2023 Latest Caselaw 2924 UK
Judgement Date : 3 October, 2023
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
AND
HON'BLE SRI JUSTICE ALOK KUMAR VERMA
03rd OCTOBER, 2023
WRIT PETITION (M/B) No. 181 OF 2023
Kishan Datt Sharma.
...Petitioner
Versus
State of Uttarakhand and others.
...Respondents
Counsel for the petitioner. : Mr. Sandeep Kothari, learned counsel.
Counsel for the State of : Mr. Amarendra Pratap Singh, learned Uttarakhand/ respondents. Additional Advocate General for the State of Uttarakhand.
JUDGMENT : (per Sri Vipin Sanghi, C.J.)
We have heard learned counsels, and proceed to
dispose of the Writ Petition, since counter affidavit has
already been filed by respondent nos. 2 and 3.
2. The petitioner has preferred the present Writ
Petition to assail the order dated 11.07.2023 passed by
respondent no. 3, i.e. the Superintending Engineer, 9th
Circle, Public Works Department, Dehradun, whereby the
Superintending Engineer cancelled the Tender ID No.
2023_pwd_58405_1, which was opened on 12.06.2023, for "unavoidable reasons". The petitioner participated in
the aforesaid tender invited by the respondents for the
work, namely "Under One Time Maintenance Head, the
Maintenance Work of Kyarapul Damta to Kota Mudha
Motor Road". The tender was initiated on 08.05.2023, and
the last date for submission of the bids, and for opening of
the bids, was fixed as 12.06.2023. The bids were invited
through the e-tendering process, and the bidders were
also required to submit their bids physically by the last
date of submission, i.e. 12.06.2023 by 03:00 P.M. The
bids were opened immediately thereafter. The case of the
petitioner is that the petitioner emerged as the lowest
bidder upon opening of the tender. On 14.06.2023, the
respondents also required the petitioner to submit a
clarification, which communication reads as follows :-
"उपरो� िवषयक स�िभ�त पत्र के क्रम म� अवगत करवाना है िक िदनांक 12.06.2023 को उपरो� काय� की Financial Bid खोली गई िजसमे आपकी िनिवदा प्रथम �ूनतम पाई गई है। इस काय� की BOQ के मद सं�ा 2 म� Unit म� त्रुिटवंश Cum की जगह Rmt हो गया था, यिद आप मद सं�ा 2 म� "Cum" Unit से काय� करने को सहमत है तो पत्र के मा�म से अपनी सहमित िवभाग को प्रेिषत करना सुिनशिचत करे, तािक िनिवदा िन�ारण की अिग्रम काय�वाही की जा सक�।"
3. The petitioner provided the clarification on the
same day, as desired. Thereafter, the respondents have
issued the impugned communication.
4. Upon service of notice, requiring the
respondents to explain their said conduct, they have filed
their counter affidavit. The stand of the respondents, in
their counter affidavit, is that a total of 120 online bids
were received for the work in question. However, only 09
physical bids were submitted by the bidders up till 03:00
P.M. on 12.06.2023. In relation to another work, namely
"One time Anurakshan Maintenance Work Radu Mundhol
Motor Road", for which e-bids were also invited, up till
12.06.2023, 03:00 P.M., 107 e-bids were received, and 14
physical bids were received. The stand of the respondents
is that on 12.06.2023, 09 bidders, who had submitted
their e-bids in response to the tender in question, made a
complaint that some persons prevented them from
submitting their physical bids, when they sought to do so
on 12.06.2023. The stand of the respondents is that, in
the light of the said complaints, the order was issued by
respondent no. 3, cancelling the tendering process for
"unavoidable reasons".
5. Mr. Kothari, learned counsel for the petitioner
points out that the said complaint, which is annexed as
Annexure No. CA-3 along with the counter affidavit, is
completely vague. It does not name any person, or
describe any person, who physically obstructed the
complainants from submitting their bids. No complaint to
Police was made by any of the said bidders
contemporaneously by calling Dial 100 Number. No officer
of the respondents was contacted for that purpose on the
same day, on real time basis. He submits that the office
of the respondents, where the bid was to be submitted, is
situated in Dehradun, and if the complaint of the said 09
bidders is to be believed, it would follow that in broad
daylight, the said 09 bidders were prevented from
submitting their bids by some unknown persons. Even the
number of such persons is not named. It is not explained,
as to how 09 bidders, including the petitioner, were able to
submit the physical copies of their bids. It is also argued
that if the complaint of these complainants were to be
ignored, there were still 102 bidders, who had submitted
their e-bids, and had not submitted their physical bids by
03:00 P.M. on 12.06.2023, who did not raise a grievance
like the 09 bidders, who made the complaint.
6. Counsel for the petitioner further submits that
the respondents proceeded to cancel the tender in
question, without undertaking any inquiry whatsoever, and
without identifying any person, who may have allegedly
obstructed the 09 complainants from submitting their
physical bids. He further submits that if this modus
operandi of the complainants were allowed to succeed,
and if this becomes the norm, it would become practically
impossible for any tender to proceed, as any bidder, or
even a non-bidder, may file a complaint of being
prevented from submitting the bid, by making a vague and
unsubstantiated complaint. Mr. Kothari submits that the
cancellation of the tender, after opening of the bids is
mindless, unreasonable, and arbitrary. The fact that the
respondents proceeded to open the bids, shows that
sufficient number of bids had been received, and there
was healthy competition.
7. On the other hand, the submission of Mr.
Amarendra Pratap Singh - learned Additional Advocate
General for the State, is that the cancellation of the tender
has been undertaken for good reasons, on the basis of the
complaint received by the respondents. He submits that it
is only 09 out of 120 bidders - who had submitted their e-
bids, who were able to submit their physical bids, and this
probabilizes the complaint made, and grievance raised by
the said 09 bidders.
8. We have considered these submissions of the
parties, and examined the records. We find merit in the
submission of Mr. Kothari that, merely because some of
the bidders (09 of them), made a complaint that they
were not able to submit their physical bids, on being
obstructed physically by some unknown persons, the
tendering process could not have been cancelled,
particularly, when there was absolutely no substantiation
of the said complaint, and no inquiry whatsoever was
conducted by the respondents, before taking the decision
to cancel the tendering process. The complaint is vague,
inasmuch as, it neither names any person, or describe
anyone, who may have caused such alleged obstruction.
The number of such persons; the place where the
obstruction took place, and; the manner of such
obstruction, are not disclosed. The complaint appears to
be as vague, as could be. The police was not called, and
no officer of the respondents was contacted, who may
have been manning the office, where the bids were
required to be submitted. It is not explained, as to how
09 bidders were actually allowed to submit their bids in
respect of the tender in question, and how in respect of
another tender, out of 107 bidders, who had submitted
their e-bids, 14 physical bids were permitted to be
submitted. The complainants do not even name any
person, who may have been behind the alleged
obstruction. It is not that such a complaint was supported
by any statement by any officer of the respondents, who
was posted in the office, where the bids were being
received. It is not explained, as to why only 09
complainants submitted the complaint, when a total of 120
e-bids were received. Even if the 09 bidders, who had
submitted their physical bids, and the 09 bidders, who had
submitted their complaints, were to be excluded, that
would still leave 102 bidders, who had submitted their e-
bids, but not submitted their physical bids, and it is not
explained as to why such a large number of bidders, or a
majority of them, had not made a similar complaint.
9. The submission of Mr. Amarendra Pratap Singh,
that only 09 bidders had submitted their physical bids out
of 120, and this fact probabilizes the complaint, has no
merit, since a vast majority of the bidders, who had
submitted their e-bids, did not similarly complain to the
respondents. It could well be, that the said bidders after
submitting their online bids, may have subsequently
decided not to proceed with their participation.
10. We also find merit in the submission of Mr.
Kothari that if this modus operandi - adopted by the 09
complainant-bidders, were to be allowed to succeed,
without there being any credible material to substantiate
such a complaint, it would become very easy for any
person to scuttle the tendering process, which is
undertaken with a lot of prior preparation and expense.
11. The works in question are time-sensitive in
nature. They have to be executed on time, and public
interest demands that such works are not delayed. The
whole tendering process has been cancelled, which would
mean that the respondents would have to reinitiate the
same. No one can guarantee that a similar complaint
would not be received in respect of the same, or other
tenders in future. The approach adopted by the
respondent-authorities would be completely destructive of
the tendering process, and ensure that it never succeeds,
if this yardstick were to be adopted by them. We could
have appreciated if the complaints were substantiated, or
there was any other cogent material to probabilize the
truth of the same. However, there is none at all in the
present case. The impugned decision taken by the
respondents, in the facts and circumstances of the case, is
completely baseless, mindless and arbitrary and,
therefore, cannot be sustained.
12. We, accordingly, quash the impugned Office
Memorandum dated 11.07.2023 issued by the
respondents. The Writ Petition is allowed in the aforesaid
terms, with costs quantified at Rs. 20,000/- to be paid by
the respondents.
13. Consequently, pending application(s), if any,
also stand disposed of, accordingly.
________________ VIPIN SANGHI, C.J.
___________________ ALOK KUMAR VERMA, J.
Dt: 13th SEPTEMBER, 2023 Rahul
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!