Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

WPMB/28/2023
2023 Latest Caselaw 1542 UK

Citation : 2023 Latest Caselaw 1542 UK
Judgement Date : 6 June, 2023

Uttarakhand High Court
WPMB/28/2023 on 6 June, 2023
             IN THE HIGH COURT OF UTTARAKHAND
                                  AT NAINITAL
                   HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
                                          AND
                      HON'BLE SRI JUSTICE RAKESH THAPLIYAL

                   WRIT PETITION (M/B) NO. 28 OF 2023
                               06TH JUNE, 2023
BETWEEN:
M/s Lakshay Constructions                                      .....Petitioner.
And

State of Uttarakhand & others                                  ....Respondents.

Counsel for the Petitioner : Mr. Nagesh Aggarwal and Mr. Rajendra Singh Azad, learned counsel.

Counsel for the State : Mr. Gajendra Tripathi, learned Brief Holder.

Counsel for the Respondent No.5 : Mr. Arvind Vashistha, learned Senior Counsel assisted by Mr. Imran Ali Khan, learned counsel.

The Court made the following:

JUDGMENT:(per Hon'ble The Chief Justice Sri Vipin Sanghi)

In pursuance of our order dated 17.05.2023, Mr.

Anil Kumar, Superintending Engineer, is present in Court. We

have interacted with him. He states that the petitioner had

left the relevant column in its technical bid blank, and did not

indicate expressly that the petitioner had not executed any

work in the past. Therefore, it was assumed that the technical

bid of the petitioner was incomplete and deficient, and that

there was suppression of the relevant information by the

petitioner.

2. In our view, since clause 'L', notice whereof, we

have taken in our order dated 17.05.2023, applied only to

those contractors, who had executed earlier works in the

same department, it could not be assumed by the

respondent- department, if the bidder had left a blank in

response to the query under clause 'L', that he had earlier

executed the works, and did not make disclosure of the same.

Pertinently, no clarification was sought by the respondents

from the petitioner.

3. The Superintending Engineer states that there were

several other bidders whose bids were rejected on the same

ground.

4. In our view, the respondents, firstly, could not have

assumed that there was suppression, and secondly, could

have easily called for a clarification in case, there was any

doubt in the mind of the respondent-department.

5. It is argued by learned counsel today that the

petitioner had been awarded the work in the year 2017,

which he did not execute, and there was an order of

permanently debarment of the petitioner from executing any

works in the respondent- department. It is also argued that

the petitioner had suppressed the said fact.

6. Learned counsel for the petitioner submits that the

petitioner had represented against the said debarment, and

its representation has not been disposed of till date.

Moreover, the petitioner's registration certificate was renewed

on 19.01.2023, and the registration is valid till 31.06.2025.

Therefore, it could not be argued that the petitioner was

debarred on the date of his participation in the tender, in

question. The respondents have not taken the aforesaid as a

ground for rejection of the petitioner's technical bid.

7. The debarment of the petitioner could not have

been for an indefinite period, and open ended. The fact that

the petitioner's registration has been renewed on 19.01.2023

by the Chief Engineer himself, shows that the respondents

have lifted the debarment of the petitioner. The only purpose

of registration of a contract with the respondent-department

is to enable the registered contractor to participate in bids

invited by the respondent-department for execution of works.

Therefore, in our view, the rejection of petitioner's technical

bid on the aforesaid ground is completely erroneous.

8. The petitioner claims that the petitioner's bid was

lower than that of the successful bidder. The petitioner's

financial bid was not opened, and therefore, on this aspect,

no finding can be returned in these proceedings. The

petitioner's technical bid was rejected as early as on

27.03.2023, whereafter, the work was awarded to respondent

no.5, and he started execution of work in the beginning of

April, 2023. This writ petition was preferred by the petitioner

on 11.04.2023. However, it appears that the same was lying

under defects, and came to be listed before this Court only on

17.05.2023. During this period, the successful bidder has

continued to execute the work.

9. Mr. Vashisth, learned Senior Counsel for

respondent no.5, submits that respondent no.5 has executed

about 20% of the work till the passing of the status quo order

dated 17.05.2023 by this Court.

10. Clearly, there is some delay and laches on the part

of the petitioner in approaching this Court. We are, therefore,

not inclined to interfere with the ongoing works by

respondent no.5. We vacate our order of status quo dated

17.05.2023.

11. We dispose of this writ petition with liberty to the

petitioner to pursue its claims for damages against the

respondent-department.

12. The writ petition stands disposed of in the aforesaid

terms.

13. Pending application, if any, also stands disposed of.

(VIPIN SANGHI, C.J.)

(RAKESH THAPLIYAL, J.) Dated: 06th June, 2023 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter