Citation : 2023 Latest Caselaw 1132 UK
Judgement Date : 26 April, 2023
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
AND
HON'BLE SRI JUSTICE ALOK KUMAR VERMA
26TH APRIL, 2023
WRIT PETITION (M/S) No. 1308 OF 2022
Between:
Gautam Associates. ...Petitioner
and
State of Uttarakhand and others. ...Respondents
Counsel for the petitioner. : Mr. Sandeep Kothari, learned counsel.
Counsel for respondent nos. 1 to 5. : Mr. S.S. Chaudhary, learned Brief Holder for the State of Uttarakhand.
Counsel for respondent no. 6. : Mr. B.S. Adhikari, learned counsel.
JUDGMENT : (per Sri Vipin Sanghi, C.J.)
We have heard learned counsels for the
parties.
2. The petitioner has preferred the present Writ
Petition to seek the following reliefs :-
"a) Issue a writ, order or direction in the nature of Certiorari to call for the record and to quash/ set aside impugned the order dated 05.05.2022 (Annexure No.- 10) issued by the Chief Engineer, Regional Office, Public Works Department, Yamuna Colony, Dehradun, whereby, the Superintendent Engineer, Public Works Department has directed, if M/s Shiva Associates has deposited the performance or additional performance security, up-till 05.02.2022 then the further steps for the acceptance of the tender may be taken.
b) Issue a writ, order or direction in the nature of Certiorari to call for the record and to quash/ set aside the consequential order dated 07.05.2022 (Annexure No.- 11) issued by the Office of Superintending Engineer, Ninth Circle, Public Works Department, Dehradun, whereby, the Executive Engineer, Public Works Department, Rishikesh has been directed to do the needful in terms of the order dated 05.05.2022 issued by the office of Chief Engineer, Regional Office, Public Works Department, Dehradun.
c) Issue a writ, order or direction in the nature of Mandamus directing the respondents to issue letter of acceptance and the letter of award to the petitioner pursuant to the order dated 24.12.2021."
3. The case of the petitioner is that the
petitioner, along with other bidders - which included
respondent no. 6, participated in the National
Competitive Bidding Process for construction of Ghuttu
Gandhakpani Motor Road in Doiwala Constituency,
district Dehradun under State Sector (From KM 11.500
to KM 16.000). The tender was invited by the
Superintending Engineer 9th Circle, Public Works
Department, Dehradun.
4. The petitioner, and respondent no. 6, were
both found to be technically qualified. Upon opening of
the financial bids, respondent no. 6 emerged as the L-1
bidder. Accordingly, the respondent-authorities offered
the contract to respondent no. 6 - M/s Shiva Associates.
The respondent no. 6 was called upon to furnish the
earnest money, and the security deposit. Admittedly,
respondent no. 6 did not furnish the security deposit to
the tune of Rs. 75,61,000/- within the time granted for
the said purpose. Consequently, on 24.12.2021, the
respondent-authorities decided to cancel the award of
the contract to respondent no. 6, and forfeited the
security of respondent no. 6. Simultaneously, the
respondent-authorities called upon the petitioner to
convey its acceptance, and furnish the earnest money
deposit. In pursuance of the said communication dated
24.12.2021, the petitioner furnished the earnest money
deposit in the form of a Fixed Deposit. It appears that,
subsequently, the respondent-authorities decided to
grant one more opportunity to respondent no. 6 to
furnish the security deposit, and, in pursuance of the
said opportunity, respondent no. 6 furnished its security
deposit of Rs. 75,61,000/- on 02.02.2022.
5. Since the petitioner was left in lurch after it
furnished the earnest money deposit, the petitioner has
preferred the present Writ Petition to seek the reliefs, as
aforesaid.
6. The submission of Mr. Kothari, learned counsel
for the petitioner is that once the respondent-authorities
had decided to cancel the offer made to respondent
no.6, and forfeited its security deposit, it was not open
to the respondent-authorities to unilaterally withdraw
the said action, and grant further time to respondent
no.6 to furnish the performance security. In the
meantime, the petitioner had been called upon to accept
the offer, and also to furnish the earnest money deposit,
which the petitioner had done.
7. The respondent-authorities have filed their
counter affidavit, wherein respondent no. 5 - Executive
Engineer, Temporary Division, Rishikesh, District
Dehradun has stated as follows :-
"8. That before issuing the letter of acceptance, M/s Shiva Associates was directed to provide Rs. 75.59 Lacs against performance and additional performance security and vide order dated 30.09.2021 issued by the respondent, letter of acceptance was issued to M/s Shiva Associates and further directed to furnish performance and additional performance security amounting Rs. 75,58,809/- within 28 days in favour of Executive Engineer, Temporary Division, Rishikesh, Dehradun.
9. That M/s Shiva Associates has not deposit the additional performance security then he wrote a letter dated 21.10.2021 to the Superintending Engineer, 9th Circle Dehradun in which he seeks exemption in view of the office memorandum dated 12.11.2020 issued by Government of India and issued by State Government.
10. That vide letter dated 15.12.2021 written by Executive Engineer, Temporary Division, PWD, Rishikesh which is addressed to Superintending Engineer by informing that M/s Shiva Associates has not deposited the additional performance security till date, therefore he has recommended to cancel the letter of acceptance under clause 39 of standard bid document.
11. That the Superintending Engineer vide its order dated 22.12.2021 cancelled the letter of acceptance in view of recommendation made by Executive Engineer, Temporary Division, Rishikesh and forfeited the bid security amount Rs. 3,10000/-."
8. It is further disclosed by respondent no. 5 that
respondent no. 6 had approached this Court by filing
Writ Petition (M/S) No. 2787 of 2021. That Writ Petition
was disposed of on 27.12.2021 with a direction to the
respondent-authorities to take a decision on the
representation made by M/s Shiva Associates, i.e.
respondent no. 6 herein. The representation of
respondent no. 6 herein was rejected by the
Superintending Engineer, 9th Circle, PWD, Dehradun on
11.01.2022. The affidavit further goes on to state :-
"15. That vide letter dated 24.12.2021 issued by the Executive Engineer, Temporary Division inform the petitioner that M/s Shiva Associate has not been deposited the additional performance security till 22.12.2021, therefore, letter of acceptance issued to M/s Shiva Associate has been cancelled and the petitioner has been directed since the petitioner is being second lowest he was directed to submit a consent letter as well as the earnest money deposit in the office. It is further submitted that on 08.01.2022, code of conduct was issued for general election of Legislative Assembly by the Election Commission of India, therefore, letter of acceptance has not been issued in favour of petitioner.
16. That the Chief Engineer, Regional Office, PWD, Dehradun issued a letter dated 05.05.2022 which is addressed to the Super tending Engineer, 9th Circle, Dehradun in which it is mentioned that on 01.02.2022 Engineer-in-Chief directed the Superintending Engineer, 9th Circle to accept the performance and additional
performance security of M/s Shiva Associates till 05.02.2022 if such security has been deposited pursuant to the order passed by Engineer-in- Chief further steps for acceptance of tender may be taken.
17. That in pursuance to the letter issued by the Chief Engineer on 05.05.2022 the Superintending Engineer written a letter dated 07.05.2022 to the Executive Engineer, Temporary Division, Rishikesh to take necessary action in view of the letter dated 05.05.2022.
18. That vide letter dated 20.05.2022 issued by the Executive Engineer, Temporary Division, PWD, Rishikesh, Dehradun which is addressed to the Superintending Engineer, 9th Circle, PWD, Dehradun wherein it is mentioned that the M/s Shiva Associates furnished performance and additional performance security amounting Rs. 72,51,000/- as against Rs. 75,58,809/-, rest of the amount Rs. 3,07,809/- has not been deposited as yet and further requested to take decision in the matter and as yet no decision has been taken by the Superintending Engineer."
9. From the above, it will be seen that, even
after rejection of the representation of respondent no. 6,
the Chief Engineer, Regional Office, PWD, Dehradun
sought to grant more time to respondent no. 6 to furnish
the security deposit. Though it is claimed that the
security furnished by respondent no. 6 was short by Rs.
3,07,809/-, this position is disputed by respondent no.6,
to claim that the entire security deposit amount has
been deposited by respondent no. 6.
10. Be that as it may, we are of the view that
once the offer made to respondent no. 6 had been
cancelled, and the security deposit of respondent no. 6
has been forfeited, the respondent-authorities could not
have blown hot and cold at the same time, and granted
more time to respondent no. 6 to furnish the
performance security, particularly when, in the
meantime, the petitioner had been asked to convey its
acceptance of its offer, and to furnish the earnest money
deposit.
11. The power to review such administrative
decision did not inhere in the respondent-authorities.
Such an act on the part of the respondent-authorities
has the potential of abuse of such power for extraneous
considerations.
12. We are, therefore, of the view that the
aforesaid action of the Chief Engineer was not in
consonance with administrative law and, even otherwise,
was not permissible. We may also observe that the offer
made by respondent no. 6 was to the tune of Rs. 2.76
crores, whereas the offer made by the petitioner was to
the tune of Rs. 2.90 crores. In response to our query,
learned counsel or the petitioner, on instructions from
the petitioner, who is present in Court, states that the
petitioner would match the bid offered by respondent
no. 6, and would perform the contract at the same price,
as was quoted by respondent no. 6. The aforesaid stand
of the petitioner would ensure that the public exchequer
does not suffer in any way.
13. We, therefore, allow the present Writ Petition,
and quash the order dated 05.05.2022 issued by the
Chief Engineer, Regional Office, Public Works
Department, Yamuna Colony, Dehradun. We further
direct the respondent-authorities to proceed to execute
the contract with the petitioner. The petitioner shall
comply with all the contractual obligations, inter alia, by
furnishing the performance security. The petitioner shall
also abide by its offer of executing the contract at the
rates offered by respondent no. 6.
14. The Writ Petition stands disposed of in the
aforesaid terms.
15. Consequently, pending applications, if any,
also stand disposed of accordingly.
________________ VIPIN SANGHI, C.J.
___________________ ALOK KUMAR VERMA, J.
Dt: 26th April, 2023 Rahul
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!