Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

SPA/222/2018
2021 Latest Caselaw 688 UK

Citation : 2021 Latest Caselaw 688 UK
Judgement Date : 5 March, 2021

Uttarakhand High Court
SPA/222/2018 on 5 March, 2021
           IN THE HIGH COURT OF UTTARAKHAND
                              AT NAINITAL
       THE HON'BLE THE CHIEF JUSTICE SRI RAGHVENDRA SINGH CHAUHAN

                                     AND

                     THE HON'BLE SRI JUSTICE N.S. DHANIK

                REVIEW APPLICATION NO. 6705 OF 2021

  DELAY CONDONATION APPLICATION IN REVIEW NO. 6707 of 2021

                                      IN

               SPECIAL APPEAL NO. 222 OF 2018

                          05TH MARCH, 2021

BETWEEN:

State of Uttarakhand & others                              .....Appellants.


And

Rajendra Singh Panwar & another                            ....Respondents.

Counsel for the appellants : Mr. Anil K. Bisht, learned Additional Chief Standing Counsel.

Counsel for the respondents            :     Mr.       Yogesh         Pacholia,
                                             learned       counsel          for
                                             respondent no.1.

The Court made the following:

ORDER: (per Hon'ble The Chief Justice Sri Raghvendra Singh Chauhan)

The State has filed this Review Application (MCC

No.6705 of 2021). Since the application is delayed by 146

days, the State has also filed an application under Section 5

of the Limitation Act.

2. The reason stated by the State with regard to the

delay is that, with regard to the order dated 29.07.2020, the

State sought permission from the Law Department for filing

the review application. By order dated 30.09.2020, the Law

Department granted permission for filing the review

application. Having receipt the sanction from the Law

Department, vide letter dated 06.10.2020, the Director,

Animal Husbandry Department, was directed to prepare the

review application. Subsequently, the Director, Animal

Husbandry Department, sent a letter dated 14.10.2020 to the

learned counsel for preparing the review application and the

concerned Advocate contacted the superior authorities and

had the file allotted to him. On 22.09.2020, he wrote back to

the State Law Officer for mentioning the ground for review.

The grounds for review were communicated to him by letter

dated 28.09.2020.

3. Since the order dated 29.07.2020 was directly

based on the judgment of this Court, pronounced in Special

Appeal No.53 of 2020, the State Government had filed the

review application in the said case, namely, Review

Application No.565 of 2020. However, by order dated

06.11.2020, the said Review Application was dismissed. Thus,

according to the review applicant, the Government had taken

a decision not to file any review application in any other

matters where the judgment was based on the decision of a

learned Coordinate Bench in Special Appeal No.53 of 2020.

4. However, subsequently, the Government has

changed its mind, and has filed the present review

application. Thus, according to the learned counsel for the

review applicant, sufficient cause has been shown for

condoning the delay.

5. On the other hand, Mr. Yogesh Pacholia, learned

counsel for respondent no.1, submits that bureaucratic delays

have never been the basis for condoning the delay. Moreover,

even on merit, the appellant-review applicant does not have a

good case. For the order dated 29.07.2020 is squarely based

on the decision of a learned Coordinate Bench in Special

Appeal No.53 of 2020. This was a concession made by the

learned counsel for the Government itself. Therefore, there is

no error apparent on the face of the record. Hence, the

Government cannot be permitted to resile from its

commitment and concession that it had made before the

learned Coordinate Bench. Thus, according to the learned

counsel for respondent no.1, there is neither sufficient cause

for condoning the delay, nor any cause for allowing the

review application on merit.

6. In catena of cases, the Hon'ble Supreme Court has

clearly opined that the State is like any other litigant. If the

State is slack in taking recourses to the legal remedies which

are available to it, only because of bureaucratic red tapism,

delays cannot be condoned. Therefore, the State has failed to

show sufficient cause for condonation of delay.

7. A bare perusal of the order dated 29.07.2020

clearly reveals that a concession was made by the learned

counsel for the State, that the controversy in the intra court

appeal is squarely covered by the decision of this Court dated

24.06.2020, passed in Special Appeal No.53 of 2020. Once

this concession is made before and recorded by the Court,

naturally there is no error apparent on the face of the record.

Most importantly, admittedly, even the review application

filed against the order dated 24.06.2020 in Special Appeal

No.53 of 2020, was dismissed by order dated 06.11.2020.

Therefore, the judgment dated 24.06.2020 has attained

finality.

8. Hence, even on merit, the present review

application has not legs to stand upon. Therefore, this review

application is dismissed both on the ground of delay and

merit. No order as to costs.

(RAGHVENDRA SINGH CHAUHAN, C.J.)

(N.S. DHANIK, J.) Dated: 05th March, 2021 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter