Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

WPMS/2652/2021
2021 Latest Caselaw 5075 UK

Citation : 2021 Latest Caselaw 5075 UK
Judgement Date : 13 December, 2021

Uttarakhand High Court
WPMS/2652/2021 on 13 December, 2021
     IN THE HIGH COURT OF UTTARAKHAND
                         AT NAINITAL
        ON THE 13TH DAY OF DECEMBER, 2021
                                 BEFORE:
     HON'BLE SHRI JUSTICE MANOJ KUMAR TIWARI

         Writ Petition (M/S) No. 2652 of 2021

BETWEEN:
M/s Bharat Construction (India) Pvt. Ltd.                       ...Petitioner
        (By Mr. Sagar Kothari, Advocate)


AND:

State of Uttarkahand & others.                                ...Respondents
        (By   Mr.   Pradeep   Hairiya,   Standing   Counsel   for   the   State   of
        Uttarakhand/respondents)




                              JUDGMENT

Petitioner submitted bid pursuant to a Notice Inviting Tender for road construction work. Petitioner's bid has been rejected by respondent nos. 2, 3 & 4, vide order dated 07.12.2021. Thus, feeling aggrieved, petitioner has approached this Court.

2. In the impugned rejection order, the reason assigned for rejecting petitioner's bid is 'non furnishing of affidavit of correctness of the bid'.

3. It is the contention of learned counsel for the petitioner that petitioner had duly uploaded the affidavit of correctness of the bid and also supplied hard copy of the said affidavit along with other document, in a sealed envelope, however, respondents have misplaced the said affidavit and

have rejected petitioner's bid, on unfounded ground.

4. Learned Standing Counsel was asked to get instructions. He has produced the written instructions received from the office of Superintending Engineer, 8th Circle, Public Works Department, New Tehri, in Court, which is taken on record. Based on the instructions, learned Standing Counsel made a statement that petitioner had not furnished affidavit of correctness of the bid with his technical bid, which was an essential condition, thus, according to learned Standing Counsel, petitioner's bid was rightly rejected.

5. Learned counsel appearing for the petitioner submits that if affidavit was not found with petitioner's technical bid, then respondents could have asked the petitioner to furnish the same within some stipulated time, to ensure competitive price.

6. Learned Standing Counsel then submitted that in view of the high valuation of the work in question, only 'A' Class Contractors could have submitted bid, while, petitioner is not registered as 'A' Class Contractor, therefore, he was not eligible. He further pointed out that petitioner is not a registered contractor for road construction work. In such view of the matter also, he was not qualified for participating in the bidding process for the work in question.

7. Since the issues raised by learned Standing Counsel have not been indicated in the rejection order dated 07.12.2021, therefore, this Court will not go into the question as to whether petitioner was qualified to participate in the bidding process or not. However, this Court is not impressed by the submission made on behalf of the petitioner that he should have been given time for submitting affidavit. Affidavit of correctness of bid is needed to rule out possibility of false claims by bidders regarding financial capacity/ infrastructure and also for taking penal action against recalcitrant bidders, who give incorrect information. Therefore, non-furnishing of such affidavit creates doubt over veracity of claims made/ documents submitted by a bidder.

8. Since petitioner's bid was not supported by such affidavit, which goes to the root of the matter, therefore, the contention made on behalf of petitioner that the employer should have informed him about the defect/deficiency, to enable the petitioner to cure the defect, cannot be accepted.

9. Having regard to the purpose of affidavit of correctness of bid, due to non-submission of such affidavit, bid of the petitioner became substantially non-responsive, therefore, the employer was under no duty to give opportunity to the petitioner, to cure the defect by filing an affidavit.

10. The sole issue which falls for consideration in the present writ petition, is as to whether petitioner had uploaded/submitted affidavit of correctness of bid with his technical bid.

11. Petitioner contends that he had submitted such affidavit, while, employer contends that such affidavit was not submitted/uploaded by the petitioner.

12. There is no evidence with the petitioner to show that he had actually submitted such affidavit. Thus, the writ petition cannot be decided without recording statement of witnesses, which would not be proper by this Court while exercising extraordinary jurisdiction under Article 226 of the Constitution.

13. Even otherwise also, it is settled position in law that public remedy under Article 226 of the Constitution cannot be invoked for adjudication of disputed question of facts.

14. Having regard to the factual dispute between the parties, this Court declines to entertain this writ petition.

15. Accordingly, the writ petition is dismissed with liberty to the petitioner to approach an appropriate forum available to him under law.

(MANOJ KUMAR TIWARI, J.) Navin

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter