Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

ARBAP/20/2020
2021 Latest Caselaw 2900 UK

Citation : 2021 Latest Caselaw 2900 UK
Judgement Date : 6 August, 2021

Uttarakhand High Court
ARBAP/20/2020 on 6 August, 2021
           IN THE HIGH COURT OF UTTARAKHAND
                               AT NAINITAL
        THE HON'BLE THE CHIEF JUSTICE SRI RAGHVENDRA SINGH CHAUHAN

        ARBITRATION APPLICATION NO. 20 OF 2020

                           06TH AUGUST, 2021

BETWEEN:

Harjinder Pal Singh                                   .....Applicant.


And

Cantonment Board, Dehradun                            ....Respondent.

Counsel for the applicant            :     Mr. Mahanand Joshi and Mr.
                                           Kanti Ram.

Counsel for the respondent           :     Mr. B.S. Adhikari.

The Court made the following:

                                JUDGMENT

The present Arbitration Application has been filed

under Section 11(6) the Arbitration and Conciliation Act, 1996

(''the Act' for short), for appointment of the sole Arbitrator.

2. According to the learned counsel for the applicant,

the applicant is the contractor who undertakes government

contracts for supplying material/goods in relation to contracts

entered with the Government and the Semi-Government

Organization.

3. The respondent, the Cantonment Board, had

invited tenders for "repair and maintenance of roads" in the

year 2016. Consequently, the applicant had submitted his

rates for the work on 15.11.2016. By order dated

30.03.2017, the said tender was accepted by the respondent.

Therefore, the work order contract was issued on 06.04.2017.

4. According to the work order contract, it was agreed

that the respondent shall make payments within the time

stipulated under the agreement. Moreover, the respondent

was under the duty to clear all the bills of the applicant within

18 days' after which the amounts had become due.

5. According to the applicant, despite the fact that the

work order was completed with utmost satisfaction, no

payments were received by the applicant in relation to the

four work orders, which are as under:-

S. No.     Work Order            Amount/Valu      Amount of Bill    Date of
                                  e (in INR)        (in INR)           Bill
  1.     Repairs     to     door   34,319/-        34,319.43/-     25.06.2018
         window glazing of
         Cantt.           Quarter
         No.4      (2nd     June,
         2017)
  2.     Public            Group    3,71,755/-    3,71,755.57/-
         Latrine          Double
         Compartment           in
         Cantt. Area 6 nos.
         (17th     November,
         2017)
  3.     Construction          of   11,49,019/-    11,49,019/-
         vacation room &
         extension             of
         playground            at
         Cantt.             Inter
         College, Chakrata
         (19th    September,
         2017)
  4.     Repairs to Ceiling          65,262/-      65,262.48/-     25.06.2018
         Gate      and       Mile
         Steel      Grill      of


       Cantt. Qtr. No.18
       (5th March, 2018)
Amount Payable             16,20,355/-   16,20,356.48/-



6. The applicant has also done work under the Work

Orders in relation to the Guest House, Chilmiri to the

satisfaction of the respondent. However, no payments were

received by the applicant in relation to the said work orders.

Therefore, according to the learned counsel for the applicant,

the respondent owes Rs.84,78,552/- along with the GST.

7. Since the respondent was not heeding to the

request of the applicant, on 17.06.2020 the applicant sent a

legal notice requesting the respondent to both clear the

outstanding bills and, since disputes had arisen between the

parties to appoint the sole Arbitrator, 'the Garrison Engineer'.

8. According to Clause 19 of the Agreement, the

parties had agreed that, in case disputes were to arise, 'the

Garrison Engineer' shall be appointed as the sole Arbitrator.

9. In the letter dated 17.06.2020, the applicant had

clearly stated that the Garrison Engineer shall be appointed

within a period of thirty days from the date of the letter.

10. According to the learned counsel for the applicant,

letter dated 17.06.2020 was replied by the respondent on

14.08.2020. However, in the letter dated 14.08.2020, the

respondent maintained a study silence with regard to the

appointment of the sole Arbitrator. In the letter dated

14.08.2020, the respondent merely directed the applicant to

submit further documents including photographs of the

construction work carried out by the applicant. There was no

whisper about the appointment of an Arbitrator.

11. Since, even after making a request for appointment

of an Arbitrator, and due to laxity on the part of the

respondent in appointing the Arbitrator, left with no other

option, the applicant filed the present Arbitration Application

under Section 11(6) of the Act.

12. The respondent has filed its counter-affidavit.

According to Mr. B.S. Adhikari, the learned counsel for the

respondent, on 15.10.2020, the respondent has appointed

'the Garrison Engineer' as the sole Arbitrator. The learned

counsel for the respondent submits that, although, it is true

that Section 12(5) of the Act, does contain a bar which

prevents the appointment of any person whose relationship is

with the parties or the counsel or the subject matter of the

dispute. However, the proviso to said sub-section clearly

provides that the parties may, subsequent to disputes having

arisen between them waive the applicability of the sub-

section by an express agreement in writing.

13. According to Mr. B.S. Adhikari, the learned counsel

for the respondent, since the request to appoint 'the Garrison

Engineer' as the sole Arbitrator was made by the applicant by

letter dated 17.06.2020, the applicant has waived the bar

contained in Section 12(5) of the Act. Therefore, the applicant

is not entitled to pray to this Court for appointment of the

sole Arbitrator. Hence, according to the learned counsel for

the respondent, only 'the Garrison Engineer' can be appointed

as the sole Arbitrator.

14. On the other hand, Mr. Mahanand Joshi, the

learned counsel for the applicant, submits that, in the letter

dated 17.06.2020, the period for appointment 'the Garrison

Engineer' as the sole Arbitration was clearly stated 'within

thirty days'. Therefore, if there is any waiver of the bar

contained in Section 12(5) of the Act, the waiver extends only

for a period of thirty days and not beyond. Secondly, despite

the option of the waiver made by the applicant for a period of

thirty days, the respondent did not accept the request, in

fact, made mentioned hereinabove. Even in its reply dated

14.08.2020, there was not a single word about the

appointment of an Arbitrator. Thus, there silence is a clear

indication that it has rejected the request of the applicant for

appointing 'the Garrison Engineer' as the sole Arbitrator.

Thirdly, since the respondent maintained a study silence and

did not appoint the Arbitrator, as requested within a period of

thirty days, the applicant had no option but to approach this

Court under Section 11(6) of the Act for appointment of the

sole Arbitrator. Therefore, according to the learned counsel

for the applicant, once this Court is seized of the matter

under Section 11(6) of the Act, it is only this Court which has

the power to appoint the sole Arbitrator. Hence, according to

the learned counsel for the applicant, the contentions raised

by Mr. B.S. Adhikari, the learned counsel for the respondent

is highly misplaced.

15. Heard the learned counsel for the parties and

perused the record.

16. Section 12(5) of the Act is as under:-

"12(5). Notwithstanding any prior agreement

to the contrary, any person whose relationship,

with the parties or counsel or the subject-matter of

the dispute, falls under any of the categories

specified in the Seventh Schedule shall be ineligible

to be appointed as an arbitrator:

Provided that parties may, subsequent to

disputes having arisen between them, waive the

applicability of this sub-section by an express

agreement in writing".

17. A bare perusal of the proviso clear reveals that it

creates a bar with regard to the appointment of an Arbitrator

who is in relationship with the parties or with the counsel or

with the subject matter of the dispute. However, the proviso

contained an exception. The exception is that, after disputes

have arisen between the parties, both the parties agreed by

'an express agreement in writing', only then can the bar

contained in Section 12(5) of the Act be said to be the waiver

by the parties.

18. Admittedly, in the letter dated 17.06.2020, the

applicant had requested for appointing 'the Garrison Engineer'

as the sole Arbitrator. However, the request had to be acted

upon within a period of thirty days. Undoubtedly, the

respondent did not act on the said request within a period of

thirty days. Moreover, in the present case, there has been no

'express agreement in writing', with regard to the waiver of

the bar contained in Section 12(5) of the Act. Therefore, the

learned counsel for the respondent is not justified in claiming

that, by letter dated 17.06.2020, the applicant had waived

the bar imposed by Section 12(5) of the Act. Moreover,

admittedly, the applicant had filed the present applicant on

24.09.2020 before this Court. Even after the filing of the

present application, the respondent sat quietly over the

request of the applicant for appointing 'the Garrison Engineer'

as the sole Arbitrator till 15.10.2020. Therefore, the learned

counsel for the respondent is not justified in claiming that the

respondent is legally justified in appointing 'the Garrison

Engineer' as the sole Arbitrator in accordance with the arbitral

clause. Hence, the contention raised by the learned counsel

for the respondent is clearly unacceptable.

19. Admittedly, the disputes continue to exist between

the parties. Obviously, the dispute needs to be resolved

through the arbitral proceedings. Therefore, this Court

appoints Mr. B.C. Kandpal, Retd. Judge, High Court of

Uttarakhand, R/o 117 Rajeshwar Nagar, Phase-I,

Sahastradhara Road, Dehradun, as the sole Arbitrator after

his disclosure in writing is obtained in terms of Section 11(8)

of the Act; and only after receipt thereof, shall his

appointment, as an arbitrator, come into force.

20. On giving consent to arbitrate the disputes between

the parties, Mr. B.C. Kandpal, Retd. Judge, High Court of

Uttarakhand, R/o 117 Rajeshwar Nagar, Phase-I,

Sahastradhara Road, Dehradun, shall enter reference, and

shall pass an award in accordance with law. The learned

arbitrator shall fix his fees in consultation with both the

parties.

21. The arbitration application is disposed of

accordingly.

(RAGHVENDRA SINGH CHAUHAN, C.J.)

Dated: 06th August, 2021 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter