Citation : 2021 Latest Caselaw 1276 UK
Judgement Date : 1 April, 2021
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
THE HON'BLE THE CHIEF JUSTICE SRI RAGHVENDRA SINGH CHAUHAN
AND
THE HON'BLE SRI JUSTICE ALOK KUMAR VERMA
APPEAL FROM ORDER NO. 63 OF 2021
1ST APRIL, 2021
Between:
Triveny Consultants, a proprietorship firm, through its
Proprietor Shri Kuldeep Mehta.
...Appellant
and
State of Uttarakhand and another. ...Respondents
Counsel for the : Mr. Shobhit Saharia, learned
appellant counsel.
Counsel for respondent : Mr. C.S. Rawat, learned Chief
Nos. 1 & 2. Standing Counsel with Mr. B.S.
Parihari, learned Standing
Counsel.
The Court made the following:
JUDGMENT : (per Hon'ble The Chief Justice Sri Raghvendra Singh Chauhan)
The appellant has challenged the legality of the
order dated 12.03.2021, passed by the learned Additional
District Judge/Commercial Court, Dehradun, whereby the
learned Commercial Court has dismissed the application
filed by the appellant, in an application filed under Section
2
9 of the Arbitration and Conciliation Act, 1996 (for short,
"the Arbitration Act").
2. Since a very limited prayer has been made before
this Court, therefore, it is not necessary to narrate all the
facts of the case. It is sufficient to state that the
Superintendent Engineer, Irrigation Circle, Haridwar had
invited bids for construction of Dhanauri-SIDCUL, link road
on the right bank of Upper Ganga Canal in District
Haridwar. Since the appellant's bid was found to be
lowest, therefore, vide order dated 19.12.2019, the work
order was granted to the appellant. According to the work
order, the work had to be completed by 20.04.2020.
However, due to certain factors, the said assigned work
could not be completed within the stipulated period of
time. Therefore, by order dated 14.07.2020, the work
order was cancelled by the respondents. Subsequently,
the appellant has sought for extension of time for
completing the work order. It was granted for a short
period of 36 days. Since the appellant was concerned that
the work carried out by him should be measured, and his
running bills should be cleared by the department, and no
third party right should be created, the appellant filed an
application under Section 9 of the Arbitration Act. In the
said application, the appellant filed another application.
3
However, by the impugned order the said application has
been dismissed. Hence, the present appeal before this
Court.
3. Mr. Shobhit Saharia, learned counsel for the
appellant, submits that despite the fact that the appellant
was directed by the Department to be present on
15.02.2021 for measuring the work carried out by the
appellant, no one from the Department was present.
Therefore, the work carried out by the appellant is yet to
be measured. Moreover, the appellant's running bills are
still pending with the Department. Therefore, he prays
that the Department should be directed to hold a joint
inspection of the work carried out by the appellant.
Moreover, the department should be directed to clear all
the bills pending with them.
4. The learned counsel for respondent No.2-
Department has no objection if a joint inspection were to
be carried out on a given date.
5. Therefore, the appellant and the Chief Engineer,
Irrigation Department are directed to remain present at
the site on 08.04.2021 at 10:00 a.m. The Chief Engineer
is further directed to carry out the complete inspection of
4
the work carried out by the appellant in the presence of
the appellant. The Chief Engineer is further directed to
ensure that the running bills of the appellant are cleared
by the Department within a period of one month from the
date of the inspection. Moreover, it is hereby clarified that
merely because the inspection of the work carried out by
the appellant is completed by the Department, and merely
because the running bills are cleared by the Department, it
would not pre-empt the appellant from initiating arbitral
proceedings against the Department.
6. With these directions and observations, this appeal
stands disposed of accordingly.
7. Let a certified copy of this order be issued to the
learned counsel for the appellant today itself as per Rules.
_____________________________
RAGHVENDRA SINGH CHAUHAN, C.J.
___________________
ALOK KUMAR VERMA, J.
Dt: 1st April, 2021 Mamta/Neha
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!