Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sri Suvajit Paul vs Food Corporation Of India
2026 Latest Caselaw 2384 Tri

Citation : 2026 Latest Caselaw 2384 Tri
Judgement Date : 8 April, 2026

[Cites 1, Cited by 0]

Tripura High Court

Sri Suvajit Paul vs Food Corporation Of India on 8 April, 2026

                      HIGH COURT OF TRIPURA
                            AGARTALA
                            RFA No.3 of 2024
Sri Suvajit Paul, S/o Shri Swapan Kumar Paul, resident of B.K. Road,
Banamalipur, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.
                                                      ......... Appellant (s).
                               VERSUS
1. Food Corporation of India, a Government of India undertaking having its
office at 16-20, Barakhamba Road, New Delhi-11006 represented by its
Chairman-cum-Managing Director.
2. The General Manager(R), Food Corporation of India, North-Eastern
Region, Mid-Land, Shillong-3.
3. The Area Manager, Food Corporation of India, District Office, Colonel
Chowmuhani, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.
                                                     ......... Respondent(s).
For Appellant(s) :      Mr. Kundan Pandey, Advocate
For Respondent(s) :     Mr. Ratan Datta, Advocate
                        Mr. Aditya Baidya, Advocate


1. Food Corporation of India, a Government of India undertaking having its office at 16-20, Barakhamba Lane, New Delhi-110001, represented by its Chairman-cum-Managing Director.

2. The General Manager(R), Food Corporation of India, Regional Office, North East Frontier Region, Mawlai Mawroh, Shillong-793008.

3. The Divisional Manager erstwhile Area Manager, Food Corporation of India, District Office, Colonel Chowmuhani, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.

......... Appellant (s).

VERSUS Sri Suvajit Paul, Son of Sri Swapan Kumar Paul, resident of B.K. Road, Banamalipur, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.

......... Respondent(s).

1. Food Corporation of India, a Government of India undertaking having its office at 16-20, Barakhamba Lane, New Delhi-110001 represented by its Chairman-cum-Managing Director.

2. The General Manager(R), Food Corporation of India, Regional Office, North East Frontier Region, Mawlai Mawroh, Shillong-793008.

3. The Divisional Manager erstwhile Area Manager, Food Corporation of India, District Office, Colonel Chowmuhani, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.

......... Appellant (s).

VERSUS Sri Suvajit Paul, S/o Sri Swapan Kumar Paul, resident of B.K. Road, Banamalipur, P.O.-Agartala, P.S.-West Agartala, District-West Tripura.

......... Respondent(s).

For Appellant(s)            :    Mr. Ratan Datta, Advocate
                                 Mr. Aditya Baidya, Advocate
For Respondent(s) :              Mr. Kundan Pandey, Advocate

  HON'BLE THE CHIEF JUSTICE MR. M.S. RAMACHANDRA RAO
           HON'BLE MR. JUSTICE BISWAJIT PALIT
                           CAV reserved on               :   11.03.2026.
                           Judgment delivered on         :   08.04.2026
                           Whether fit for reporting :       YES

                                  JUDGMENT & ORDER

(Biswajit Palit, J)

Since all the three commercial appeals have arisen out of a

common judgment and decree and the subject matter of these appeals is

identical, so these three commercial appeals are taken up together for disposal

by this common judgment and order.

2. Heard Learned Counsel, Mr. Kundan Pandey appearing on behalf

of the appellant/plaintiff i.e. the contractor in RFA No.3 of 2024 and for the

respondent in RFA No.8 of 2024 and RFA No.9 of 2024. Also heard Learned

Counsel, Mr. Ratan Datta appearing on behalf of the respondents-FCI in RFA

No.3 of 2024 and for the appellants in RFA No.8 of 2024 and RFA No.9 of

2024.

3. Short facts of the case of the appellant/plaintiff i.e. the

contractor are as follows:

The original suit was filed by the appellant/plaintiff i.e. the

contractor before the Learned Trial Court, claiming detention charges along

with interest for delay in unloading of food grains beyond the stipulated period

due to shortage of storage space, as per the tender agreement.

3.1. The case of the appellant, in short, is that he runs a transport

business in the name of M/s Suvajit Paul and the respondents-FCI appointed

him as a transport contractor for a period of 2(two) years for transportation of

food grains/sugar and other allied materials including loading and unloading

works at Food Storage Depots from railway siding/FSD Dharmanagar to FSD

Arundhutinagar, Agartala. As per the tender agreement, the appellant started

transportation of food grains w.e.f. 01.05.2012 and had been carrying out the

work of loading of food grains from Railway Wagon at railway siding, FSD

Dharmanagar and transporting the same to FSD, Arundhutinagar, Agartala,

Tripura by using trucks/lorries under road movement permits issued by the

Depot in-charge, FCI, Dharmanagar, mentioning the date of dispatch with a

validity period of 3(three) days, including the date of dispatch and the date of

delivery at the destination. The appellant executed the work of loading and

unloading of food grains during the period of contract.

3.2. It was the case of the appellant that due to shortage of

accommodation in the FCI storage/go-down at Arundhutinagar, Agartala, the

delivery of food grains could not be effected within the stipulated period and

the respondents-FCI almost in all the occasions had detained the loaded

vehicles at the destination point for a period of about 4 to 20 days for which

the appellant had to suffer huge financial losses and also had to pay recovery

charges. The appellant had claimed a sum of Rs. 800/- per day for detention of

every loaded truck at the destination point by writing several letters to the

respondent-Area Manager but they did not pay any heed to those letters.

3.3. It was further the case of the appellant-contractor that the General

Manager, FCI, Regional Office, NEFR, Shillong by a letter dated 12.07.2013

supplying copy to the appellant/plaintiff informed the Director of Food and

Civil Supplies and Consumer Affairs, Govt. of Tripura that due to increase in

induction of food grains and inadequate storage capacity in the FCI go-down

in the State of Tripura, the respondent-Area Manager was not in a position to

unload the trucks. The appellant, from time to time, made claims for detention

charges of the vehicles to the respondents-FCI by submitting bills, but no

action was taken. Hence, the appellant/plaintiff filed the case before the

Learned Court below seeking relief(s) as stated above.

4. Defence of the respondents/defendants i.e. FCI:

The respondents-FCI contested the suit by filing written

statement stating inter alia that the appellant/plaintiff had entered into a tender

agreement with the respondents-FCI for transportation of food grains from the

railway siding/FSD Dharmanagar to FSD Arundhutinagar, Agartala. The

entrustment of the work of transportation of food grains was accepted by the

respondent no.2 i.e. the General Manager, pursuant to the NIT dated

13.09.2011 by a letter of acceptance dated 30.04.2012. According to the

respondents-FCI, due to failure of the appellant/contractor to supply trucks as

per indents issued by the respondents, the respondents-FCI had incurred huge

financial losses in terms of "demurrage charges" imposed by the railways.

4.1. It was further the case of the respondents-FCI that as per Clause-

X of the tender agreement, the appellant/plaintiff i.e. the contractor was liable

for all costs, damage, registration fees, charges and expenses incurred by the

Corporation due to negligence of the contractor and as per Clause-XII, the

Corporation would be at liberty to reimburse themselves for any loss, damage,

charges, costs or expenses suffered or incurred by the Corporation.

The respondents-FCI further took the plea that the rate quoted by

the appellant-contractor pertaining to transportation work was accepted by the

respondent No.2 i.e. the General Manager on 30.04.2012 and the appellant-

contractor was appointed as transport contractor for a period of 2(two) years

with effect from 01.05.2012 to 30.04.2014 which was subsequently extended

for a further period of 2(two) months. However, the respondents-FCI denied

the allegation of the appellant-contractor regarding shortage of

accommodation at the receiving depot. The respondents-FCI stated that as per

Clause-XVIII(vi) of tender agreement, no compensation was admissible to the

contractor in respect of detention of trucks at go-down or any other loading/

unloading points or any other place unless such detention is of an

"extraordinary kind" and the decision of the General Manager shall be final in

all such matters.

4.2. The respondents-FCI also denied the allegation of the appellant/

plaintiff regarding detention of 450 to 500 trucks at the receiving depots and

submitted that the said allegation was false and fabricated. It was further

stated that an enquiry was held in that regard and the appellant-contractor was

warned not to report any false compliant in future without verifying the facts.

The respondents-FCI further stated that the claim of the contractor for a sum

of Rs. 1,52,52,800/- along with interest was baseless, imaginary, arbitrary,

having no legal nexus.

4.3. The respondents-FCI further took the plea that the FCI was under

the process of calculating the exact amount of loss incurred by the FCI as

railway demurrage due to un-workmanlike performance of the contractor in

respect of transportation contract for transportation from Rail Head

Siding/FSD Dharmanagar to FSD Arundhutinagar, Agartala which was

awarded by FCI Regional Office, Shillong by a letter dated 30.04.2012. Thus,

by the written statement, the respondents-FCI denied the claim of the

appellant/plaintiff made in the original suit and prayed for dismissal of the suit

with costs.

5. Counterclaim of the respondents-FCI against the original

suit:

The respondents-FCI in their counterclaim took the plea that the

FCI is a Government of India undertaking primarily engaged for supplying of

food grains to maintain the public distribution system smoothly in each State

including the State of Tripura by engaging contractors for carrying of food

grains/allied materials etc. from railway sidings to various depots in the State

of Tripura.

5.1. It was pleaded in their counterclaim that the FCI had issued an

NIT on 13.09.2011 under a two-bid tendering system for appointment of

transport contractors for a period of 2(two) years for transportation of food

grains/sugar and also for loading and unloading of trucks at Food Storage

Depots from railway siding/FSD Dharmanagar to FSD Arundhutinagar,

Agartala. According to the respondents-FCI, the bid offered by the appellant-

contractor was accepted by the FCI and by a letter dated 30.04.2012, the FCI

appointed the appellant-contractor as a transport contractor for a period of

2(two) years for transportation of the food grains/sugar and other allied

materials. The period of contract was extended for a further period of 2(two)

months by the respondents-FCI. The respondent further took the plea that as

per agreement, the appellant-contractor was under obligation for placement of

adequate number of trucks in compliance of the indents issued in favor of the

appellant-contractor by the Siding/Depot in-charge, but for failure of clearing

the wagons, demurrage charges were being imposed by the railways on the

respondents-FCI and they had to incur huge loss.

5.2. It was further stated that the performance of the appellant-

contractor in carrying the food grains was not up to the mark, for which the

respondents-FCI had to pay railway demurrage w.e.f. May, 2012 to

September, 2013; October, 2013 to March, 2014 and April, 2014 to July, 2014

and the said demurrage charges could not be recovered from the bill of the

appellant-contractor due to a stay order passed by this Court.

5.3. It was stated that the respondents-FCI issued a letter on

22.12.2015 to the appellant-contractor explaining the grounds regarding the

demurrage suffered by the FCI for the above financial years on account of

failure to supply trucks for timely unloading of wagons at the siding, but after

several persuasions with the appellant-contractor, the performance of the

appellant-contractor was not improved, and due to their poor performance,

huge detention of wagons took place at Dharmanagar which caused serious

disruption to the Public Distribution Systems in the State of Tripura.

Consequently, the FCI had to pay huge amount of demurrage charges.

6. Reply of the appellant-contractor to the counterclaim:

The appellant-contractor contested the counterclaim by filing

written statement stating inter alia that the respondents-FCI had no cause of

action to file the counterclaim and as such, they are not entitled to get any

relief.

6.1. It was stated that there was no such provision for claiming

demurrage charges in the tender agreement. Further, as per the contract, there

was no clause for railway demurrage charges and the Division Bench of this

Court by a common judgment and order dated 03.10.2016 in WA No.25 of

2016 and other connected appeals held that FCI could not claim demurrage

charges in absence of any provision in the contract. So, the appellant-

contractor prayed for dismissal of the counterclaim filed by the respondents-

FCI.

6.2. To determine the suit, the Learned Commercial Court framed

four issues in the main suit filed by the appellant-contractor and four issues in

the counterclaim filed by the respondents-FCI.

7. Arguments on behalf of the appellant contractor:

On behalf of the appellant-contractor, Learned Counsel, Mr.

Kundan Pandey submitted that the appellant-contractor filed the suit seeking

recovery of money amounting to Rs.1,52,52,800/- along with interest for delay

in unloading of food grains beyond the stipulated period as per the tender

agreement.

7.1. It was further submitted that the Learned Court below at the time

of delivery of judgment, ignoring the evidence on record, only awarded a sum

of Rs.4,42,800/- with 9% interest per annum from the date of filing the main

suit till payment for which the appellant-contractor has been compelled to file

the appeal bearing RFA No.3 of 2024 for interference.

7.2. Learned Counsel for the appellant-contractor further submitted

that the appellant/plaintiff claimed Rs.800/- per day as detention charge per

vehicle from the respondent authority, which was not considered, although no

such amount in this regard was mentioned in the tender agreement. According

to Learned Counsel, as per road movement permit, a stipulated period of

3(three) days was fixed from the place of receipt of goods to the place of

delivery, but due to inadequate place of storage, the respondents-FCI did not

take any step for unloading of trucks, resulting which the appellant/plaintiff

had to incur huge amount of financial losses for payment of detention charges

of vehicles to the owners of the trucks beyond the stipulated period. The

respondent authority was informed on several occasions in this regard, but no

steps were taken by them to resolve the issue. Learned Counsel further

submitted that the respondents-FCI although filed written statement and

counterclaim, but in support of their contention, no documentary evidence was

adduced by the respondents-FCI.

7.3. Learned Counsel further submitted that on behalf of the

respondents-FCI, one Mr. Mukesh Pal, Divisional Manager, FCI appeared and

filed examination-in-chief in affidavit. His examination-in-chief in affidavit

was nothing but the replica of the written statement filed by the respondents-

FCI and that he had no personal knowledge about the subject matters in

dispute. Further, Learned Counsel submitted that before the Learned Trial

Court, the respective Area Manager who was posted on that relevant period of

time was not produced for examination by the respondents-FCI. Learned

Counsel, Mr. Pandey further submitted that there was no clause of demurrage

charges in the agreement.

7.4. It was further submitted that as stated by the respondents-FCI

regarding submission of inquiry report, no such report was produced before

the Learned Trial Court for marking of exhibit to substantiate the defence

case.

7.5. Learned Counsel further submitted that the appellant-contractor

filed the examination-in-chief in affidavit on his behalf and relied upon certain

documents which were marked as Exhibit Nos.1 to 72. Further, referring the

cross-examination of the said appellant-contractor, Learned Counsel submitted

that the respondents-FCI by cross-examination could not make any cloud to

disbelieve the case of the appellant-contractor. The said appellant as PW-1, in

course of his cross-examination submitted that they had to complete the work

of loading and unloading within 3 to 4 days of issuing requisition/indent and

after completion of such loading and unloading, next requisition is being

issued. The appellant, in his cross-examination further stated that as per

Clause-XVIII(a)(vi), he is entitled to get detention charges if such detention is

of "extraordinary kind" and in this connection, decision of General Manager is

final. It is further stated that the term "extraordinary kind" is not defined in the

agreement. The appellant/plaintiff approached to the Zonal Office of the FCI

for dispute resolution in terms of Clause-XX of the NIT. It is further stated

that the rate towards detention charges was not specified in the agreement.

Nothing more came out relevant from the cross-examination of the appellant-

contractor.

7.6. Learned Counsel for the appellant/plaintiff further submitted that

considering the evidence on record, Learned Trial Court, in respect of period

of detention beyond 3(three) days made a cut-off date of 6(six) days and

accordingly, made calculation without any basis for which the compensation

claimed by the appellant/plaintiff could not be properly ascertained by the

Learned Trial Court.

7.7. It was further submitted by Learned Counsel for the

appellant/plaintiff that in the main suit, certain documents namely Exhibit

Nos.40, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71 and 72 were produced

and duly proved by the appellant/plaintiff as exhibits regarding claiming of

payment of detention charge of the vehicles, but those exhibited documents

were not considered by the Learned Trial Court which resulted in improper

assessment of the compensation claimed by the appellant/plaintiff.

Finally, referring the evidence on record as well as the documents

relied upon by the appellant/plaintiff, Learned Counsel urged before this court

to allow the appeal filed by the appellant/plaintiff by setting aside the

judgment dated 14.12.2023 and decree dated 19.12.2023 passed by Learned

Judge, District Commercial Court, West Tripura, Agartala in Commercial Suit

No.11 of 2016 and Commercial Suit No.20 of 2016 and also to pass a decree

for recovery of Rs.1,52,52,800/- against the respondents-FCI with interest.

7.8. Further, Learned Counsel submitted that since there was no

clause of "demurrage" in the agreement and since this Court in WA No.25 of

2016 held that the FCI cannot claim any demurrage charges in absence of any

provisions in the contract so, the counterclaim of the respondents-FCI cannot

be sustained as per law.

7.9. Reliance was placed upon one judgment of the Hon'ble Supreme

Court of India in Food Corporation of India & Ors. v. Abhijit Paul1, wherein

in para No.30, Hon'ble the Apex Court has observed as under:

"30. We have every reason to believe that the Corporation, statutorily obligated to procure and distribute foodgrains across the nation, enters into contracts depending on the services it requires. These contracts naturally vary depending on the needs and purposes of the Corporation. With the aid of the provisions in the handling and transport contract from 2010, we are able to understand the intention of the parties while entering into the present road transport contracts. As the present contracts do not involve the task of loading and unloading of foodgrains from the railway wagons as a part of the contractors' responsibility, there is no clause enabling the recovery of demurrages from them by the Corporation. Thus, our interpretation of the expression "charges", as exclusive of liability for demurrages, stands confirmed."

Referring the same, Learned Counsel for the appellant/plaintiff

submitted that the principle of the said judgment also supports the case of the

present appellant-contractor.

8. Arguments made on behalf of the respondents-FCI:

On behalf of the respondents-FCI, Learned Counsel, Mr. Ratan

Datta submitted that the suit filed by the appellant/plaintiff was not

maintainable.

8.1. Learned Counsel further submitted that in the NIT dated

13.09.2011 no period was mentioned regarding claiming of detention charges

of trucks and as such, the appellant-contractor was not entitled to claim for

any detention charge of the vehicles. Rather due to non-supply of trucks by the

appellant-contractor on time, the respondents-FCI had to suffer huge financial

losses and had to pay railway demurrages which are attributable to the

appellant-contractor. Learned Counsel for the respondents-FCI submitted that

the Learned Commercial Court without appreciating the evidence on record,

(2023) 15 SCC 40

has partly decreed the suit in favour of the appellant/plaintiff, rejecting the

counterclaim of the respondents-FCI. It was further submitted that admittedly

due to some laches, no documentary evidences were produced by the

respondents-FCI but, the case of the appellant-contractor does not comes

under the purview of "extraordinary kind" as per the tender agreement. As

such, the appeal preferred by the appellant-contractor is liable to be dismissed.

8.2. Learned Counsel, Mr. Datta further submitted that in this case,

the appellant-contractor was under obligation to supply trucks as per the

indents issued by the FCI from time to time. However, the appellant-

contractor failed to do so, which resulted in huge detention of wagons at the

railway side causing disruption of Public Distribution System in the State. Due

to such poor performance of the appellant-contractor, the respondents-FCI had

to pay huge amount of railway demurrage charges. Learned Counsel

submitted that as per the tender agreement, the appellant-contractor was liable

to compensate the respondents-FCI and the FCI was also entitled to recover

such compensation. Finally, Learned Counsel for the respondents-FCI prayed

before this court to allow the appeal filed by the respondents-FCI and to set

aside the judgment and decree passed by the Learned Trial Court and to grant

a decree in favour of the respondents- FCI.

9. Analysis of evidence on record and observations:

We have heard both the sides at length and also perused the case

record including the plaint, the written statement and the documents submitted

by the parties as well as the judgment and decree delivered by Learned Trial

Court.

9.1. As already stated, Learned District Commercial Court in the main

suit as well as in the counter claim framed issues and decided all the issues

after elaborate discussions. However, in the present appeal filed by the

appellant-contractor Learned Counsel for the appellant-contractor only

confined his argument regarding fixing of cut-off dates as well as non-

consideration of some exhibited documents.

On the other side, Learned Counsel for the respondents-FCI in

addition to his reply against the submissions made by Learned Counsel for the

appellant-contractor confined his argument only to the extent that certain

relevant documents were not produced and proved in this case on behalf of the

respondents-FCI. So, let us confine ourselves to decide those points as raised

by Learned Counsel for the parties.

9.2. Admittedly, in this case, the initial tender for carrying of goods

was for a period of 2(two) years w.e.f. 01.05.2012 to 30.04.2014 which was

later on extended for a further period of 2(two) months. The appellant-

contractor claimed that as per the tender agreement, he has duly supplied

trucks for transportation of food grains/sugar from Dharmanagar to Agartala

from time to time. However, due to lack of storage space, the trucks could not

be unloaded at the respective depots of FCI for which the appellant-contractor

had to detain the trucks for period ranging from 4 days to 20 days on different

occasions. Consequently, the appellant-contractor claimed detention charges

beyond three days at the rate of Rs.800/- per truck along with interest and thus

claimed a total sum of Rs.1,52,52,800/- by filing the suit.

To substantiate the claim on behalf of the appellant-contractor, he

examined himself as PW-1 and relied upon some documents which were

marked as Exhibit Nos.1 to 72.

9.3. On behalf of the respondents-FCI, one witness, Sri Mukesh Pal

was examined as DW-1. However, no documentary evidences were adduced

by the respondents-FCI to contest the suit filed by the appellant-contractor.

In the counterclaim also, on behalf of the respondents-FCI, said

Mukesh Pal was examined as PW-1 and he relied upon certain documentary

evidences which were marked as Exhibit No.1(i) to 1(xxiv) and Exhibit No.2

to 6.

9.4. The appellant-contractor in his examination-in-chief tried to

support his version as set out in the plaint. During his cross-examination by

the respondents-FCI, he stated that as per the NIT, food grains were to be

transported from food go-down, Dharmanagar to food go-down,

Arundhutinagar and that the trucks were placed for carrying of food grains as

per the requisition of respondents-FCI. The appellant-contractor further stated

that as per Clause-XVIII(a)(vi), the contractor is entitled to get detention

charges if such detention is of "extraordinary kind" and the decision of the

General Manager, in this regard, was final. However, he also stated that the

term "extraordinary kind" was not defined in the agreement. Additionally, the

appellant-contractor stated that the rate towards detention charges was not

specified in the agreement and he acknowledged the receipt of letter dated

22.08.2013 (Exhibit No.33). No further material facts emerged from his cross-

examination.

9.5. Similarly, on behalf of the respondents-FCI, as already stated one

Mr. Mukesh Pal was examined as DW-1. He, in his examination-in-chief in

affidavit asserted the same facts as mentioned in the written statement as well

as in the counterclaim filed by the respondents-FCI. However, during cross-

examination by the appellant-contractor he stated that he was appointed as

Manager, FCI in the year 2005 and his first posting was at Muradabad, Uttar

Pradesh. He further stated that he did not know the definition of the term

"cause of action" and also expressed his inability to state who were holding

the post of Divisional Manager/Area Manager at Agartala during the period

from 2012 to 2016. He further deposed that he did not have any personal

knowledge regarding the disputes that arose during the subsistence of contract

during the period from 01.05.2012 to 30.04.2014. DW-1 further stated that the

extension beyond the period of agreement is/was being granted due to non

appointment of new contractor in time. The period of contract involved in the

suit ended on 30.04.2014.

DW-1 admitted that he did not produce the original agreement in

dispute. He further admitted that he has not submitted/furnished the break up

supported by documents to show as to how the respondents-FCI has suffered

loss to the tune of Rs.1,01,00,000/-.

DW-1 also could not say anything regarding the judgment dated

04.12.2015 rendered by this Court in WP(C) No.503 of 2012 and WP(C)

No.505 of 2012 and stated that the appellant-contractor had addressed several

communications to the FCI informing that the loaded trucks were stationed

beside the FCI go-down and accordingly, requested the FCI to arrange

unloading of goods from the truck. He volunteered that on receiving such

letters, the then Area Manager visited the go-down and enquired the matter,

and found the said information to be untrue. However, no such inquiry report

was submitted before the Court and the then Area Manager was also not

examined as witness. It was also stated that the matter in dispute was not

referred to the Grievance Cell Redressal Forum by the FCI.

He further stated that there was no clause in respect of demurrage

charges in the agreement.

In his cross-examination, DW-1 was confronted with a letter

dated 30.12.2013 issued by the then Area Manager namely, B.G. Bhuiya

where it was admitted that the appellant/plaintiff being contractor has

performed satisfactorily for the financial year 2012-13.

It was also stated that nothing was mentioned in the NIT or the

tender agreement in regard to the involvement of railway; and the road

movement permit in favour of the appellant-contractor was issued by the

respondents-FCI. DW-1 further admitted in his cross-examination that the FCI

did never lodge any case either civil or criminal against the appellant-

contractor during the subsistence period of agreement. The bills submitted by

the appellant-contractor contained the particulars such as date of receipt and

dispatch, as well as the delay caused in delivery of the goods and the

respondents-FCI raised no objection in regards to the contents of such

particulars.

DW-1 was again confronted with the letter dated

12.07.2013(Exhibit No.21) issued by the General Manager where he admitted

the contents of the letter.

9.6. At the time of hearing, being asked by this Court, Learned

Counsel for the respondents-FCI fairly submitted that the NIT was issued by

the department and in the NIT no such period was mentioned regarding

detention of trucks. Further, on being asked, Learned Counsel for the

respondents-FCI could not satisfy this Court as to why the respondents-FCI

issued road movement permits in favour of the appellant-contractor without

having any sufficient space/go-down for unloading of the goods carried out by

the appellant-contractor through trucks.

9.7. Learned Trial Court, in para No.26 of the judgment, considering

the evidence on record of DW-1 came to the finding that there was delay in

unloading of trucks of the appellant/plaintiff at the destination point of FCI.

Further, in para Nos.27 and 28, regarding "whether such detention is of

extraordinary kind", Learned Trial Court referred Clause-XVIII(a)(vi) of the

tender agreement which says that a contractor is not entitled to any

compensation in respect of detention of trucks at go-down or any other

loading and unloading points unless such detention is of "extraordinary kind".

In para No.28, Learned Court below described Clause (B) and in

para No.29, Learned Court below referred the exhibited documents bearing

Exhibit Nos.8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 22, 23, 24, 25, 26,

29, 30, 32, 34, and 36 and also referred other exhibits bearing Nos.28, 41, 42,

43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57 and 58 and came to the

observation that on the ground of shortage of storage space in the go-down of

FCI, there may be a reasonably 1 to 3 days delay in unloading of trucks and

for such delay the appellant-contractor cannot be allowed to claim any

detention charge and such delay cannot be said to be extraordinary. So,

regarding the further delay of next three days, excluding the period prescribed

under road movement permits issued by the Depot in-charge, FCI, Court

below held that the appellant-contractor cannot be allowed to complain

regarding unloading of trucks at the destination point for the shortage of

storage space. It held that as per Exhibit No.21 there was shortage of storage

capacity as well as stranding of large numbers of trucks. Learned Trial Court

further came to the observation, the appellant-contractor being a transporter of

food grains might have had knowledge of such delay because at the unloading

point, there ought to have trucks of other contractors also.

In para No.30, the Learned Trial Court gave the following

observation:

"30. The tender agreement nowhere defined the term "extraordinary". When both the parties intentionally agreed for detention charge only in case of extraordinary delay then both the parties carried the idea that delay in unloading for some days was permissible considering the size and location of the unloading point. Here in the present case maximum three days delay can be allowed(excluding the period prescribed under road movement permits issued by the Deport in-charge, FCI) to be called as non- extraordinary. But after such days of delay, the defendant/FCI cannot be allowed to take the plea of Clause-(xviii)(a)(vi) of the tender agreement because for each day's engagement of trucks the plaintiff/Contractor was supposed to pay charges to the truck owners. So from the date of despatch till next six days there cannot be any extraordinary detention. However beyond the period of six days if there is any further delay in unloading of trucks then the same can undoubtedly be termed as extraordinary detention. So, the plaintiff/Contractor here is surely entitled to get compensation for any delay in unloading of trucks beyond the period of six days. The plaintiff/Contractor claimed Rs. 800/- per day for detention of every loaded truck at the destination point. But the plaintiff did not produce any documentary evidence regarding payment of such charge. It is presumed that in 2012-2013 there ought to have been detention charge of Rs.600.00 per day for detention of every loaded truck and so here the plaintiff/Contractor is entitled to get Rs.600.00 per day for detention of every loaded truck."

9.8. Thus, it appears to us that the Learned Trial Court determined

detention charges at the rate of Rs.600/- per day. Regarding this amount,

Learned Counsel for the appellant/plaintiff, at the time of hearing did not raise

any dispute, rather fairly submitted that the appellant-contractor agreed with

the said amount. However, the appellant-contractor raised concern about

determination of six days as cut-off days for detention of trucks for clearing of

loaded goods.

In this regard, we have also gone through the exhibited

documents.

From Exhibit No.21, i.e. the letter dated 12.07.2013 issued by

General Manager, Regional Office, NEFR, Shillong to the Director of Food,

Civil Supplies & Consumer Affairs it appears that by the said communication,

the respondents-FCI admitted that as the FCI has increased its induction for

the State of Tripura since last few months, there is a problem of storing for the

increased food grains as the FCI does not have enough storage capacity and

the matter has been aggravated due to on-going evacuation of stock in

Hapania. For the sake of convenience, let us reproduce hereinbelow the

communication dated 12.07.2013:

THE FOOD CORPORATION OF INDIA REGIONAL OFFICE::NEFR::SHILLONG

No: G.5/NEFR/Genl.Corresp/13 Dated: 12.07.2013

The Director, Food, Civil Supplies & Consumer Affairs, Gopvt.of Tripura, Agartala Sir,

The FCI has increased its induction for the State of Tripura since last few months. There is problem of storing for the increased foodgrains as FCI does not have enough storage capacity. The matter has been aggravated due to on-going evacuation of stock in Hapania.

As per report, about 450 trucks are standing today at different depots in Agartala Complex. More stocks are in the pipeline and are likely to reach Agartala Complex and Chandrapur very soon. The number of stranding trucks will, therefore increase in coming few days.

The contractors namely Abhijit Paul and Subhajit Paul have complained that large numbers of their trucks are standing in Agartala since last many days. The Area Manager, Agartala is not in a position to unload the stocks.

It is therefore, requested to kindly immediately lift the State requirement of stock for the month of August' 13, so that space is created in the godown for unloading of the stranded trucks and stocks in the pipeline.

Yours faithfully,

-Sd illegible"

From the said communication, it is very much clear that the

respondents-FCI themselves admitted that they had no sufficient storage

capacity to keep the food grains. So, it is quite surprising as to how the

respondents-FCI, knowing fully that they had no capacity to unload the trucks

at the respective station, issued road movement permits in favour of the

appellant-contractor from time to time and rather, took the plea that the

appellant-contractor failed to supply the trucks for carrying of goods. This

argument of the respondents-FCI cannot be accepted as valid.

Further, from other exhibited documents relied upon by the

appellant-contractor, it appears that on many occasions, vide communications

dated 01.08.2012, 07.08.2012, 14.08.2012, 21.08.2012, 23.08.2012, 25.08.

2012, 20.11.2012, 30.04.2013, 31.05.2013, 15.06.2013, 25.06.2013,

29.06.2013, 01.07.2013, 15.07.2013, 16.07.2013, 17.07.2013, they have

requested the respondents-Area Manager for making arrangements for

unloading of sugar-loaded trucks. Those letters were marked as exhibits

before the Learned Trial Court by the appellant-contractor. Moreso, by letter

dated 20.07.2013 (Exhibit No.25), the appellant-contractor requested the

respondents-FCI not to issue any indent till the situation improves and urged

the department to utilize the vacant space in go-down at Dharmanagar to avoid

the detention of wagons. Subsequently, by another communication dated

25.07.2013, the appellant-contractor raised its demands towards detention

charges by enclosing their bills which were not considered by the respondents-

FCI.

Thus, after going through the exhibited documents and the

evidence on record, it appears to us that the delay beyond 3(three) days for

detention of trucks at the respective depot was entirely attributable to the

respondents authority.

Admittedly, the term "extraordinary kind" is not defined or

prescribed in the agreement. However, it was the admitted position from the

side of the respondents-authority that they issued road movement permits for

carrying of food grains fixing 3(three) days as limit, but it has been found

from the evidence on record that the loaded trucks were detained at the

respective depot from 4 to 20 days on different dates because of which the

appellant had to pay additional amount as hiring charges of the vehicles. The

respondents-FCI by their act and conduct also admitted that they had no

sufficient space/go-down for unloading of loaded goods and in this regard,

Learned Counsel for the respondents-FCI in course of hearing of argument

failed to satisfy this Court by placing any material to disbelieve the said facts.

Thus, the delay which occurred due to inaction of the respondents-FCI can be

satisfactorily termed as "extraordinary kind".

Thus, it appears that the Learned Trial Court rightly decided all

the issues but the observation of the Learned Trial Court fixing cut-off date for

6(six) days i.e. 3(three) days beyond the initial 3(three) days, was not proper,

which should be limited only for 3(three) days and in our considered view, the

appellant-contractor shall be entitled to claim detention charges for the delay

beyond the initial 3(three) days as per calculation made by the Learned Trial

Court below in the said judgment and decree.

9.9. In course of hearing of arguments, Learned Counsel for the

appellant-contractor drawn the attention of this Court that Learned Trial Court

although exhibited some documents which were marked as exhibit Nos.27, 59,

60, 62, 63, 66, 67, 68, 69, 70, 71, 28, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51,

52, 53, 54, 55, 56, 57, and 78 but those documents were not considered by the

Learned Trial Court at the time of delivery of the judgment and decree

resulting which the Learned Trial Court has determined a very lesser amount

of compensation in favor of the appellant-contractor. Learned Counsel for the

appellant-contractor further submitted that if those exhibited documents are

not taken into consideration, then the appellant-contractor shall suffer huge

financial losses.

9.10. As already stated, Learned Counsel for the respondents-FCI in

course of hearing of argument has totally failed to project their defence, to

rebut the claim of the appellant-contractor and as such, we are of the

considered view that those exhibited documents needs to be re-considered by

the Learned Trial Court.

9.11. Furthermore, regarding demurrage charges, there was no such

clause in the agreement, and in the common judgment and order of this Court

dated 03.10.2016 in W.A. No. 25 of 2016 it was held that FCI could not claim

demurrage charges in absence of provision in the contract, and the same

remained unchallenged. So, the respondents-FCI is not entitled to claim

"demurrage charges" from the appellant-contractor.

In addition to that, in the light of the judgment of the Hon'ble

Supreme Court of India as referred by Learned Counsel for the appellant-

contractor (supra), it is clear that there is no scope to fasten the liability of

demurrage upon the appellant-contractor.

9.12. Moreover, the witness of the respondents-FCI, in course of his

cross-examination very specifically admitted that nothing was mentioned

either in the NIT or in the tender agreement regarding involvement of railway

and also regarding claiming of demurrage charges. As such, the question of

claiming demurrage charges by the respondents-FCI cannot arise and it does

not seem to be a sound proposition to sustain the plea of demurrage in this

case. So, the respondents-FCI are also not entitled to claim any demurrage

from the appellant-contractor.

9.13. In the result, the appeal filed by the appellant-contractor bearing

RFA No.03 of 2024 is hereby partly allowed and the appeals bearing RFA

No.08 of 2024 and RFA No.09 of 2024 filed by the respondents-FCI is hereby

dismissed accordingly.

The judgment dated 14.12.2023 and decree dated 19.12.2023

delivered by Learned Judge, District Commercial Court, West Tripura,

Agartala is hereby partly interfered with. The matter is remanded back to the

Learned Trial Court for the limited purpose of re-determining the amount of

detention charges, fixing cut-off days only for 3(three) days instead of 6(six)

days as determined by Learned Trial Court in para No.30 of the judgment

(wherein it was observed that "So from the date of despatch till next six days

there cannot be any extraordinary detention") and also in para No.32 of the

judgment and, also to consider the exhibited documents bearing Exhibit Nos.

27, 59, 60, 62, 63, 66, 67, 68, 69, 70, 71, 28, 41, 42, 43, 44, 45, 46, 47, 48, 49,

50, 51, 52, 53, 54, 55, 56, 57, and 78 and thereafter to deliver a fresh judgment

within a period of 4(four) months from the date of receipt of a copy of this

judgment and order.

With this observation, the aforesaid appeals are disposed of on

contest with costs in favor of the appellant-contractor.

Send down the records.

Prepare decree

All pending application(s), shall stand closed.

          (BISWAJIT PALIT, J)                      (M.S. RAMACHANDRA RAO, CJ)




Snigdha


SNIGDHA Digitally signed by
        SNIGDHA DAS

DAS     Date: 2026.04.09
        16:12:12 +05'30'
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter