Citation : 2021 Latest Caselaw 981 Tri
Judgement Date : 28 September, 2021
Page - 1 of 9
HIGH COURT OF TRIPURA
AGARTALA
WP(C) No.608/2020
Sri Ashes Deb.
............ Petitioner(s).
- Vs. -
The State of Tripura and Ors.
............ Respondent(s).
WP(C) No.609/2020
Sri Ashes Deb.
............ Petitioner(s).
- Vs. -
The State of Tripura and Ors.
............ Respondent(s).
WP(C) No.611/2020
Sri Ashes Deb.
............ Petitioner(s).
- Vs. -
The State of Tripura and Ors.
............ Respondent(s).
For Petitioner(s) : Mr. Somik Deb, Sr. Advocate,
Ms. Riya Chakraborty, Advocate,
Ms. S Chisim, Advocate.
For Respondent(s) : Mr. S S Dey, Advocate General,
Mr. K De, Additional Govt. Advocate,
Ms. A Chakraborty, Advocate.
HON'BLE THE CHIEF JUSTICE MR. AKIL KURESHI
HON'BLE JUSTICE MR. S G CHATTOPADHYAY
_O_R_D_E_ R_
28/9/2021
(Akil Kureshi, CJ).
These three petitions arise in similar facts involved similar
questions of law and are between the same parties. The petitioner, an
Page - 2 of 9
individual, has prayed for the direction to the Government to release his
unpaid bills for execution of works carried out by him for and on behalf of
the Government. The main opposition of the Government is that whatever be
the petitioner's rightful claim for completion of these works, in relation to
other two contracts namely, agreements No.(1)/2015-16 and 25/2013-14,
there have been substantial overpayments to the petitioner which the
Government has to recover and which the Government has the authority to
set off against the petitioner's present claims.
[2] Facts
may be noted at some length :
In WP(C) No.608/2020, the petitioner was awarded a contract for
maintenance of bailey bridges and certain roads in the Chawmanu Sub-
Division during the year 2016-2017. According to the petitioner, upon
completion of the work, the department had to make a payment of
Rs.7,50,382/-. When the petitioner raised the demand before the department,
on 24th February 2020, the department conveyed to the petitioner that certain
formalities are not fulfilled and until the same is done, the payment cannot
be released. The petitioner at one stage also tried to seek appointment of an
arbitrator by filing an arbitration petition before this Court, however, the
Court was of the opinion that the petitioner had not completed the
formalities under the agreement before an arbitrator could be appointed. Be
that as it may, the petitioner continued his efforts to persuade the department Page - 3 of 9
to release the bills. On 5th June 2020, the department reiterated its stand that
until the petitioner completes the formalities, the payment cannot be made.
On 21st July 2020, the petitioner conveyed to the department that he would
visit the concerned officer on 23rd July 2020 for completing all the
formalities. On 5th August 2020, petitioner again wrote to the Executive
Engineer and pointed out that he had visited him, on 23rd July 2020 and
completed all the formalities despite which the payment has not yet been
made. On 17th July 2020, the Executive Engineer conveyed to the petitioner
as under :
"Dear Sir,
Please refer to the above, the aforesaid letters have been issued in favour of you for deposition of cost difference for an amount of Rs.71,22,966.77 & refund of excess payment for an amount of Rs.2,02,46,249.00 against the agreement No.25/CE/EE/LTV/ PWD/M/2013-14 and refund of excess payment for an amount of Rs.10,90,898.00 against the agreement No.01/CE/SE-V/EE/LTV/ PWD/2015-16, but till today, you have not yet taken any action in this regards.
Therefore, your all dues under this division have been suspended and restricted until deposition of the cost difference and refund of excess payment."
Under this communication thus, the department for the first time
raised the issue of its intention to set off the petitioner's claim arising out of
his contract against department's counter-claims in relation to the past
contracts. At that stage, the petitioner approached the Court.
Page - 4 of 9
[3] In the other two petitions, facts are substantially similar of course
except for the amounts involved. In WP(C) 609/2020, the petitioner's claim
is for a sum of Rs.60,46,447/- and in WP(C) 611/2020, the petitioner's claim
is Rs.60,98,880/-. In these cases also, the department has cited its claims
arising out of agreements No.01/2015-16 and 25/2013-14 to deny the
petitioner's claims.
[4] In response to the notice issued, department has appeared and filed
replies. Grounds taken in their replies are, (i) that there was delay in
execution of the work which would involve a penalty and (ii) that in relation
to the agreements No.01/2015-16 and 25/2013-14, the department has made
substantial overpayments to the petitioner which when adjusted against the
petitioner's present bills, nothing remains payable.
[5] The petitioner has filed rejoinder and additional affidavit in which
it is pointed out that with respect to agreements No.01/2015-16 and 25/2013-
14, the department had never taken the stand of alleged overpayment to the
petitioner till the petitioner raised his bills and when unpaid, sought
appointment of an arbitrator. Once the arbitrator was appointed, the
department in reply to the petitioner's claims before the arbitrator had set off
such counter-claims.
Page - 5 of 9
[6] In background of such facts, learned senior counsel for the
petitioner Mr. Somik Deb vehemently submitted that the department cannot
be allowed to deny the petitioner's claims in the present context on the
ground that in relation to certain other contracts the Government has raised
the ground of overpayments. He submitted that such counter-claims were
raised only after the petitioner resorted to arbitration. The Government's
claims are yet to be examined by the arbitrator. Even before the arbitrator
passes his award the department cannot treat its claim as ascertained claim.
[7] On the other hand, learned Advocate General opposed the
petitions contending that (i) writ petition is not an appropriate remedy for
deciding such disputed questions, (ii) the agreement contains an arbitration
clause and the petitioner may raise an arbitration dispute if aggrieved and
(iii) the petitioner had delayed execution of the work and had also not
completed the formalities despite reminders from the department. On the
ground of equity also, therefore, the petition must be rejected.
[8] Learned Advocate General drew our attention to Clause 39.3.2 of
the agreement which according to him, enables the department to adjust the
overpayments of the earlier contracts against the contractor's present bills.
He submitted that the department has raised two counter-claims against the
petitioner for the past contracts where there were overpayments made.
Page - 6 of 9
[9] In rejoinder, learned senior counsel Mr. Deb made two
clarifications. He firstly stated that the petitioner does not want
quantification of his claims in the present contracts by this Court. Let such
quantification be done by the department. He further stated that without
prejudice to his legal contentions, the petitioner is prepared to offer an
unconditional Bank guarantee while withdrawing the amounts in relation to
the present contracts which may be ascertained by the department.
[10] In view of the statements made by the counsel for the petitioner, we
may examine the facts on record. As noted, the petitioner has completed the
execution of three different contracts and in relation to which the petitioner
has outstanding claims. The petitioner's quantification is not admitted by the
department. However, the department also does not dispute that some
amounts are yet to be paid to the petitioner in relation to these three
contracts. The main ground raised by the department for releasing such
payments even when ascertained is that in relation to the previous
agreements No.01/2015-16 and 25/2013-14, the department has made huge
overpayments to the contractor. In facts of the present case, by taking
appropriate steps for safeguarding the interest of the Government revenue,
the admitted payments to the petitioner in relation to these three contracts
must be made. In other words, the department would not be allowed to
withhold such payments on the ground that it has outstanding counter-claims Page - 7 of 9
against the petitioner in relation to other contracts. This is so for the
following reasons.
[11] Clause 39.3.2 of the agreement reads as under :
"39.3.2. In case of overpayments or wrong payment if any made to the contractor due to wrong interpretation of the provisions of the contract, Contract conditions etc., such unauthorised payment will be deducted in the subsequent bills or final bill for the work or from the bills under any other contracts with the Government or at any time there after from the deposits available with the Government."
As per this clause, it would be open for the department to deduct
from the running bill or the final bill of the contractor for the work, any
overpayments and also from the payments arising out of any other contract
with the Government. We are informed that identical clause was present in
agreements No.01/2015-16 and 25/2013-14 also. In that view of the matter,
for the time being, without concluding this issue, we are prepared to proceed
on the basis that the Government has a right to adjust the payment arising
out of these contracts the Government's claims in relation to past
agreements. However, such claims have to have some ascertainment and
cannot be unilateral assertion of one of the parties to the agreement.
Recognizing any such right into the Government would amount to giving
power of attachment of judgment to a party to the agreement. We have noted
that the claims which the Government now raises against the petitioner in
relation to the past contracts, were for the first time raised by way of Page - 8 of 9
counter-claim in an arbitration proceedings instituted by the petitioner.
Whatever be the outcome of such arbitral proceedings and the acceptance or
rejection of the Government's claims against the petitioner, at this stage, the
Government must release the petitioner's payments arising out of the present
contracts. Perhaps, it was open for the Government to approach the arbitrator
in the pending proceedings and seek interim protection in terms of Section
16 of Arbitration and Conciliation Act, 1996 where the arbitrator enjoys
wide powers. Particularly when the petitioner is prepared to receive such
payments by giving unconditional Bank Guarantee, the Government's
anxiety of not being able to recover the money ultimately found due and
payable by the arbitrator, is taken care of.
[12] The ground of disputed question or availability of the alternate
remedy would not survive. In view of such narrow compass, the issues have
been dealt with in view of the petitioner's concessions. The relevant
concessions we have recorded are that the petitioner does not require
quantification of the claims in these cases at the hands of the Court but
leaves it for the Government to do and the petitioner is prepared to withdraw
the sums so ascertained by the Government by offering unconditional Bank
guarantee.
[13] Under the circumstances, these petitions are disposed of with the
following directions :
Page - 9 of 9
(i) The department shall verify the petitioner's claims of unpaid amounts, arising out of the present agreements and quantify the sums which according to the department are outstanding. This exercise shall be completed within 3(three) months.
(ii) Upon completion of the above exercise, the department shall indicate the sums payable to the petitioner under these agreements. Upon such communication, the amount will be paid over to the petitioner on the petitioner furnishing unconditional Bank guarantee for the whole amount. Such Bank guarantee shall be encashed if in the arbitral proceedings ultimately the department is held entitled to receive such sum or any part thereof.
(iii) The petitioner shall keep such Bank guarantee alive till the arbitral proceedings are completed and for a period of 3(three) months after the arbitrator passes his award.
(iv) With respect to the quantification of the petitioner's claims to be made by the department as provided in Clause (i) above, if the petitioner has any dispute, it will be open for the petitioner to raise the same in accordance with law.
Pending application(s), if any, also stands disposed of.
( S G CHATTOPADHYAY, J ) ( AKIL KURESHI, CJ ) Sukhendu
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!