Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sk.Shabeer vs The State Of Telangana
2026 Latest Caselaw 779 Tel

Citation : 2026 Latest Caselaw 779 Tel
Judgement Date : 16 April, 2026

[Cites 4, Cited by 0]

Telangana High Court

Sk.Shabeer vs The State Of Telangana on 16 April, 2026

        IN THE HIGH COURT FOR THE STATE OF TELANGANA
                           AT HYDERABAD


  THE HON'BLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH
                                   AND
                THE HON'BLE SRI JUSTICE G.M.MOHIUDDIN


                     WRIT APPEAL No.434 of 2026

                          Dated: 16.04.2026
Between:
Sk. Shabeer
and 2 others.
                                                          ...Appellants
                                   and
The State of Telangana,
Rep. by its Principal Secretary,
Revenue (LA & JA Department),
Secretariat Buildings,
BRKR Bhavan, Hyderabad,
and 7 others.
                                                        ...Respondents


JUDGMENT:

Learned counsel Sri Ch.Ravi Kumar appears for the appellants.

Sri E.Ramesh Chandra Goud, learned Government Pleader for

Land Acquisition, appears for respondents No.1, 2 and 5 to 8.

Sri B.Narasimha Sharma, learned Additional Solicitor General of

India, representing Sri Madishetty Ramu, learned Standing Counsel for

National Highways Authority of India (NHAI), appears for respondents

No.3 and 4.

2. Three of the writ petitioners out of twelve are aggrieved by the

impugned judgment dated 07.04.2023 passed in W.P.No.25680 of 2023,

whereby the learned writ court relegated the writ petitioners to avail the

statutory remedy under Section 3G(5) of the National Highways Act,

1956 (hereinafter referred to as, "the Act of 1956"), while refusing to

entertain the writ petition.

3. The writ petitioners approached the learned writ court for a

declaration that the action of the respondents in not taking steps to

prepare Rehabilitation and Resettlement (R&R) Scheme and passing

award under Section 31 of the Right to Fair Compensation and

Transparency in Land Acquisition, Rehabilitation and Resettlement Act,

2013 (hereinafter referred to as, "the Act of 2013"), though the writ

petitioners belong to the category of project affected and displaced

families in view of the acquisition made for widening of the existing

road from Karimnagar to Warangal section of NH-563, as illegal and

unconstitutional. The writ petitioners also prayed that they are entitled

to R&R Scheme provided in the Second and Third Schedules of the Act

of 2013. In the writ proceedings, there was an interim stay for about a

period of two years from dispossession of the writ petitioners. However,

according to the appellants, immediately after passing of the impugned

judgment, their houses have been demolished and they are on roads.

These appellants do not have any grievance as regards the compensation

awarded in lieu of the acquisition of their land and structures standing

thereupon. They, however, are aggrieved by non-consideration of their

claim for R&R Scheme in terms of the Second and Third Schedules of

the Act of 2013, which applies to acquisitions made under the Act of

1956.

4. In order to buttress the aforesaid point, learned counsel for the

appellants has drawn the attention of this court to the order dated

28.08.2015 issued under Section 113(1) of the Act of 2013 by the

Central Government wherein the benefits available to the landowners

under the Act of 2013 are extended to similarly placed landowners

whose lands are acquired under the 13 enactments specified in the

Fourth Schedule thereunder, which includes the Act of 1956 at serial

No.7. Learned counsel for the appellants has also relied upon the

comprehensive guidelines issued under the Act of 1956 by the Ministry

of Road, Transport and Highways, dated 28.12.2017, specifically

paragraph 4.4 thereof in order to contend that land losers under the

acquisition made under the Act of 1956 are not only entitled to

compensation in accordance with the First Schedule of the Act of 2013,

but also R&R Scheme in accordance with the Second Schedule and the

infrastructural amenities in accordance with the Third Schedule, as the

Act of 1956 is specified at serial No.7 in the Fourth Schedule of the Act

of 2013 with effect from 01.01.2015. Paragraph 4.4 of the said

guidelines reads as under:

"4.4 Following the notification of the aforesaid Ordinances, the Ministry of Road Transport & Highways issued a letter dated

29.04.2015 whereby the select provisions of RFCTLARR Act, 2013 were made applicable to the NH Act, 1956 with effect from 01.01.2015. A conjoint reading of the aforesaid shows that the Ordinance (Amendment) remained in force till 31st August 2015. 'Removal of Difficulties Order' was issued by the Department of Land Resources on 28th August 2015, which took effect from 01.09.2015. However, since the date of application of the selected relevant provisions of the RFCTLARR Act, 2013 to the NH Act, 1956 was 01.01.2015 in terms of the Ordinance (Amendment) No.9 of 2014, it remains an unambiguous and accepted position that the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, relating to the determination of compensation in accordance with the First Schedule, rehabilitation and resettlement in accordance with the Second Schedule and infrastructure amenities in accordance with the Third Schedule have been made applicable to all cases of land acquisition under the NH Act, 1956, i.e. the enactment specified at Sr. No. 7 in the Fourth Schedule to the RFCTLARR Act, with effect from 01.01.2015."

5. It is submitted that the application of the writ petitioners was

examined by the District Collector, Hanumakonda, but on the

clarification from the Project Director, NHAI, PIU, Warangal, he has

denied such claim for R&R Scheme under the Second and Third

Schedules of the Act of 2013 for National Highways Projects vide

memo dated 15.05.2023. This aggrieved the writ petitioners to approach

the learned writ court. However, the learned writ court relegated the

writ petitioners to avail the remedy under Section 3G(5) of the Act of

1956, which, in the instant case, would not arise as there is no award in

respect of the claims to which the writ petitioners are entitled under the

Second and Third Schedules of the Act of 2013. Therefore, being

aggrieved, three of the aggrieved writ petitioners have preferred this

appeal.

6. Learned Additional Solicitor General of India appearing for

respondents No.3 and 4 has fairly submitted that the clarification of the

Project Director, NHAI, PIU, Warangal, referred to in the memo dated

15.05.2023 would not stand the test of legal scrutiny, in view of the

extension of the benefits to the land losers under the Act of 1956 also, as

applicable under the First, Second and Third Schedules of the Act of

2013. It is his submission that respondent No.7, who is the competent

authority, may be directed to consider the claim of the appellants in

accordance with law. It is also submitted that the appellants and others

have got enhanced compensation as against acquisition of their land and

structures standing thereupon and they do not have any grievance as

against it.

7. Learned Government Pleader for Land Acquisition representing

respondent No.7 submits that if a direction is issued upon the competent

authority/Revenue Divisional Officer - cum - Land Acquisition Officer,

Hanumakonda, for consideration of the claim of the appellants towards

R&R Scheme under the Second and Third Schedules of the Act of 2013,

the same shall be considered in accordance with law.

8. Upon hearing the learned counsel for the parties and after taking

note of the facts and circumstances and the legal provisions referred to

hereinabove, we are of the considered view that the land losers under the

acquisition made in exercise of the powers under the Act of 1956 are

entitled to the benefits which are available under the First, Second and

Third Schedules of the Act of 2013, in view of the Government Order

dated 28.08.2015 referred to hereinabove. The Ministry of Road,

Transport and Highways has also issued the comprehensive guidelines

in that regard. However, it appears that this aspect was not pointed out

and missed by the learned writ court while relegating the writ petitioners

to the remedy under Section 3G(5) of the Act of 1956. The remedy

under Section 3G(5) of the Act of 1956 would arise only in case the

affected parties are aggrieved by the award made in respect of their

claims under the Second and Third Schedules of the Act of 2013. In

such circumstances, the impugned judgment warrants interference.

9. Accordingly, the impugned judgment is set aside. The appellants

are granted liberty to approach respondent No.7 with a claim for

entitlement towards R&R Scheme under the Second and Third

Schedules of the Act of 2013. Needless to say, on such application

being made, respondent No.7 would take a decision in accordance with

law within a period of eight weeks from the date of receipt of a copy of

this judgment along with the application. Since the appellants contend

that their houses have been demolished after passing of the impugned

judgment, it would be open for them to seek directions from the

competent authority for providing temporary shelter in the meantime,

which shall also be considered in accordance with law.

10. The instant writ appeal stands disposed of accordingly. There

shall be no order as to costs.

Miscellaneous applications pending, if any, shall stand closed.

______________________________________ APARESH KUMAR SINGH, CJ

______________________________________ G.M.MOHIUDDIN, J 16.04.2026 vs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter