Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mas Cargo Service vs Union Of India
2026 Latest Caselaw 441 Tel

Citation : 2026 Latest Caselaw 441 Tel
Judgement Date : 7 April, 2026

[Cites 4, Cited by 0]

Telangana High Court

Mas Cargo Service vs Union Of India on 7 April, 2026

Author: Nagesh Bheemapaka
Bench: Nagesh Bheemapaka
IN THE HIGH COURT OF JUDICATURE FOR THE STATE OF
                    TELANGANA
     HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

             WRIT PETITION No. 20820 OF 2021

                              07.04.2026
Between:

Mass Cargo Service,
Rep. by its Proprietor M.A. Salam
                                                             ..... Petitioner
And

The Union of India,
Rep. by its General Manager,
South Central Railway,
Rail Nilayam, Secunderabad & others.
                                                      ..... Respondents

O R D E R:

Petitioner is a proprietary concern engaged in the

business of mechanized parcel handling by plying five

contractor-owned battery-operated trucks at the parcel office of

Hyderabad Railway Station, having its office at H.No.

9-4-131/70, Akberbagh, Tolichowki, Hyderabad. They entered

into an Agreement dated 16.11.2018 with Respondents for

mechanized movement of parcels at Hyderabad Railway Station

for ensuring uninterrupted movement of outward and inward

consignments between the parcel office and various

trains/platforms and vice versa. The said contract was for two

years commencing from 17.11.2018 and ending on 16.10.2020.

Pursuant thereto, Petitioner furnished a Bank Guarantee of

Rs.3,29,081/- towards security deposit, valid up to 26.04.2021,

in favour of Respondents. It is further stated that Petitioner

engaged 14 labourers on daily wages for operating the trucks,

including provision of two staff as rest givers, paid their salaries,

maintained statutory registers, and complied with all applicable

labour laws including payment of PF and ESI, and submitted

proof of such compliance to the Respondents from time to time.

1.1. It is stated, petitioner, in terms of the Agreement,

has been regularly submitting monthly bills in triplicate, which

were duly counter-signed by the Chief Parcel Supervisor, and

thereafter submitted to the office of the Senior Divisional

Commercial Manager, Sanchalan Bhavan, Secunderabad

Division, in accordance with the procedure prescribed under the

agreement. As per Clause 18.1 of the Agreement, Respondents

had the right to verify and check the bills, and the same were

duly counter-signed by the Chief Parcel Supervisor before

submission and Petitioner strictly adhered to the said

procedure. Petitioner carried on the contractual work sincerely

and honestly without any complaint from any quarter, and all

bills submitted from the commencement of the contract till June

2020 were paid by the 3rd Respondent without any remark or

objection.

1.2. Petitioner, it is stated, submitted the final bill on

16.10.2020 for Rs.7,90,512.02, duly counter-signed by the

Chief Parcel Supervisor, but the 3rd Respondent paid only

Rs.2,31,921/-, leaving a balance amount of Rs.5,60,742/-

payable to them. The 3rd Respondent, by letter dated

15.02.2021, called upon Petitioner to submit documentary proof

for payment of wages and details of rest givers along with proof

of payment duly counter-signed by CPSR/HYD for the entire

contract period of 24 months. In response thereto, Petitioner

submitted replies dated 16.02.2021, 15.04.2021 and

28.04.2021 furnishing complete details regarding payment of

wages to staff and rest givers, along with proof of ESI and PF

contributions, attendance registers and wage registers, showing

engagement of 14 staff instead of 11 staff, duly counter-signed

by CPSR/HYD.

1.3. Petitioner also is stated to have submitted "No Due

Certificate" and "No Claim Certificate" along with the final bill to

the 3rd Respondent, yet Respondents failed to pay the final two

months' bill amount. At no point of time did Petitioner violate

any provision or condition of the contract Agreement. The 3rd

Respondent, being an instrumentality of the State, is bound to

act in accordance with the terms of the contract and in a fair

and reasonable manner, consistent with the constitutional

mandate under Articles 14, 21 and 311 of the Constitution. The

right to life under Article 21 includes the right to livelihood and

opportunity, and actions of Respondents in withholding

legitimate dues of Petitioner are violative of the fundamental

rights guaranteed under the Constitution. Despite submission

of representations dated 16.02.2021, 15.04.2021 and

28.04.2021, Respondents neither responded nor released the

pending amount of Rs.5,60,742, and such inaction is illegal,

arbitrary, unconstitutional and violative of Articles 14, 21 and

311 of the Constitution.

2. Respondents filed a counter affidavit contending

that petitioner entered into a contract for mechanized movement

of parcels by plying five contractor-owned battery-operated

trucks for operations and maintenance at Hyderabad Railway

Station (Parcel Office) for carrying outward and inward

consignments between the parcel office and different

trains/platforms and vice versa, and such operations were

required to be carried out to the satisfaction of the Railway

Administration. It is stated, the total value of the contract for a

period of two years from 17.10.2018 to 16.10.2020 was

Rs.65,81,616.12/- including 18% GST, and the contract was

awarded in favour of M/s M.A.S Cargo Services subject to

specific terms and conditions stipulated in the Agreement.

2.1. It is also stated, as per the terms of the Agreement,

a minimum of five vehicles were required to be deployed daily

and 11 persons (manpower/truck drivers) were required to be

deployed daily for round-the-clock operation of trucks, and the

contractor was also required to furnish a bank guarantee of

Rs.3,29,081/-. As per para III(1) of the Agreement, the

contractor was required to deploy 11 persons per day for round-

the-clock operation covering 84 hours of service per day in

different shifts, namely from 06:00 hrs to 13:00 hrs (7 hours, 4

trucks, total 28 hours), from 13:00 hrs to 18:00 hrs (5 hours, 4

trucks, total 20 hours), and from 18:00 hrs to 06:00 hrs (12

hours, 3 trucks, total 36 hours), aggregating to 84 hours per

day. Petitioner claimed to have engaged 14 persons including

rest givers, however, as per the agreement, only 11 persons were

required to be deployed per day and payment would be made

only for such prescribed manpower, and merely engaging

additional persons does not entitle the contractor to claim

additional wages.

2.2. From the records and lists submitted by Petitioner,

it is evident that they had not deployed the prescribed 11

persons per day and had not provided the required 84 hours of

service per day, thereby violating the terms and conditions of

the contract. As per the muster particulars submitted by

Petitioner, only 12 employees were shown as engaged on a daily

basis, out of which the attendance of one employee as per

contractual requirement was not met, thereby evidencing

shortage of manpower. Petitioner submitted the bill for the last

three months of the contract period from 17.07.2020 to

16.10.2020 for a total amount of Rs.8,22,702.01/- (at the rate

of Rs.2,74,234/- per month), along with ESI and EPF payment

details and labour particulars.

2.2.1. It is stated, out of the said amount, proportionate

wages amounting to Rs.5,60,742/- were deducted on account of

shortage of manpower, calculated based on man-days actually

worked vis-à-vis man-days required, considering the number of

days rest provided and the applicable wage rate per person.

After further deductions towards Income Tax @ 2% and

Conservancy cess amounting to Rs.30,039/-, the total

deductions aggregated to Rs.5,90,781/-, and the net payable

amount of Rs.2,31,921/- was released to Petitioner. The

amount of Rs.5,60,742/- was retained under deposit due to

deployment of lesser manpower than required under the

contract and in accordance with the contractual terms. As per

the Agreement, if the contractor engages less than the

prescribed number of labour i.e. 11 persons, proportionate

payment is liable to be deducted as per clause II(12) of the

Agreement, and the contractor cannot claim wages merely on

the basis of engaging any number of persons. As per clause

III(1) and clause XX1.2(d) of the Agreement, the contractor was

required to provide weekly rest on a staggered basis and ensure

compliance with labour laws, including provision of rest givers,

however, Petitioner failed to provide rest givers and instead

provided rest to one or two staff daily without engaging

additional personnel.

2.2.2. The wage records submitted by Petitioner indicate

that wages were paid only for 26 days in a month and that

payments for the remaining days, including those relating to

rest givers, were not made as per records. As per the calculation

based on the entire contract period, the required number of

man-days was 7205 (655 days 11 persons), excluding 76

lockdown days, whereas the Petitioner provided only 6191 man-

days, resulting in a shortage of 1014 man-days, and at the

minimum wage rate of Rs.553/- per day per person, the

proportionate deduction of Rs. 5,60,742/- was arrived at.

2.2.3. As per clause XXII(23), the Railway authorities are

empowered to verify attendance registers maintained by the

contractor on a daily basis, and such records revealed non-

compliance with deployment requirements. The unpaid wages

reflected in the muster and wage sheets are the rightful claims

of the outsourced labourers and the 3rd Respondent, being the

principal employer, is under statutory obligation to ensure

payment of such wages, and therefore the corresponding

amounts were withheld.

2.2.4. Petitioner was informed vide letter dated

15.02.2021 to furnish documentary proof of payment of wages

to all staff for full working days or details of rest givers duly

counter-signed by CPSR/HYB for the entire contract period.

The revised muster rolls and wage sheets submitted by

Petitioner vide letter dated 16.02.2021 were contradictory and

not reliable, as (i) initially, Petitioner showed engagement of

11-12 staff for 26 days without details of rest givers, whereas

subsequently claimed engagement of 14 staff, (ii) the revised

muster did not conform to the requirement of providing proof for

shortage of manpower, (iii) the muster periods differed, such as

from 17th of a month to 16th of the next month instead of

calendar months, (iv) the order of workers differed between

documents, and (v) attendance and absence entries were

inconsistent.

2.2.5. Such discrepancies clearly establish that the

records maintained during execution of the contract and those

submitted subsequently for bill clearance are inconsistent and

not tenable. Petitioner himself vide letter dated 28.04.2021,

admitted that the earlier claim regarding non-payment of two

months' bills made in his letter dated 08.04.2021 was due to a

communication mistake between himself and his typist and

tendered an apology for the same, and therefore the present

claim is contradictory and misleading. The deductions made

were strictly in accordance with contractual provisions,

including clauses II(12), II(14), XIII(2) and XV, which permit

proportionate deduction for shortfall in service, deduction of

penal charges, and payment only for actual manpower deployed.

2.2.6. The bills were processed in accordance with clause

XVIII of the agreement, and after scrutiny by the office of the

Senior Divisional Commercial Manager and vetting by the

Senior Divisional Finance Manager, deductions were made upon

finding that the Petitioner had not fulfilled the contractual

obligations. Respondents acted strictly in accordance with the

terms and conditions of the agreement and there is no illegality

in the deductions made or the amount released.

2.2.7. Petitioner vide letters dated 15.04.2021 and

28.04.2021, requested for release of price variation and security

deposit, and accordingly the price variation was paid in July

2021 and the security deposit was released in August 2021

upon submission of no claim/no due certificates on 09.08.2021

and 23.08.2021. The present dispute involves disputed

questions of fact relating to compliance with contractual

obligations, deployment of manpower, and correctness of

records, which cannot be adjudicated in writ jurisdiction. That

the agreement provides for an arbitration mechanism under

clause XI, whereby any dispute arising out of the contract is to

be referred to arbitration to a sole Arbitrator or Arbitral Tribunal

appointed by the General Manager, South Central Railway.

3. Petitioner filed a reply denying the allegations made

in the counter that he failed to mention details of staff engaged

or that he deployed less staff than prescribed, and specifically

denies the allegation that he did not provide 84 hours of service

per day or that there was any non-compliance with the terms

and conditions of the contract. It is denied, he deployed less

manpower and further denies the justification for deduction of

proportionate wages from the final bill by Respondents. As per

the bill for the last three months of the contract period from

17.07.2020 to 16.10.2020, the total bill amount was

Rs.8,22,702.02/-, from which total deductions of Rs.32,190/-

were made, resulting in a net payable amount of

Rs.7,90,512.02/-, out of which only Rs.2,31,921/- was paid,

leaving a balance amount of Rs.5,60,742/-payable to them.

3.1. It is stated, in terms of the contract for the period

from 17.10.2018 to 16.10.2020, Petitioner engaged 14 persons

per day, including two persons per day as rest givers, and

though more persons were engaged, petitioner claimed wages

only for 11 persons per day as per the Agreement. Petitioner

had engaged labour and paid wages to all the members in

accordance with applicable labour laws and statutory

requirements. As per clause II(12) of the Agreement, Petitioner

engaged the required manpower daily and provided 84 hours of

service per day, and the claim for wages was restricted only to

11 persons per day as contemplated under clause III(1) of the

Agreement.

3.2. Petitioner states that they have not violated any

terms and conditions of the Agreement, and in accordance with

the contractual requirement, ensured that manpower/truck

drivers were deployed for round-the-clock operation of trucks

and that all staff, including rest givers, were maintained

properly. Petitioner engaged additional personnel to act as rest

givers and paid wages to them on a daily basis in compliance

with labour laws, while continuing to claim payment only for the

prescribed number of persons under the contract. They had

provided uninterrupted service of 84 hours per day throughout

the contract period from 17.10.2018 to 16.10.2020, and the

same is evidenced by summary records duly endorsed by the

Chief Parcel Supervisor of the Respondent authorities.

3.3. The summary copies submitted to Respondents

clearly demonstrate that 84 hours of service per day was

consistently provided by Petitioner during the entire period of

the contract. The manual attendance registers submitted to

Respondents clearly show that 11 labourers were deployed on

each day during the entire contract period of two years. It is

stated, the discrepancies pointed out by Respondents in the

computerized attendance register for the last three months, i.e.,

from 17.07.2020 to 16.10.2020, occurred due to typographical

mistakes committed by the typist, and the same were brought to

the notice of the Respondents by way of an apology letter dated

28.04.2021.

3.4. Apart from such typographical errors, there is no

actual shortfall in manpower or deficiency in service provided by

the Petitioner. It is stated finally that deductions made by

Respondents towards alleged shortage of manpower are

unjustified, arbitrary and contrary to the actual performance of

the Petitioner under the contract.

4. Heard Sri Nambi Krishna, learned counsel for

petitioner, Sri B. Jithender, learned Central Government

Standing Counsel for Respondent No.1 and Sri T.S.

Venkataramana, learned Standing Counsel for Respondent

No.2.

5. At the outset, the foundational facts are not in

dispute. It is an admitted position that Petitioner entered into a

contract with Respondents for mechanized movement of parcels

at Hyderabad Railway Station by plying five contractor-owned

battery-operated trucks for two years commencing from

17.10.2018 and ending on 16.10.2020. It is also not in dispute

that the said contract specifically stipulated the number of

vehicles to be deployed, the manpower required to be engaged,

the number of hours of service to be rendered on a daily basis,

and the manner in which payments were to be processed and

released.

6. The controversy in the present Writ Petition centers

around the deduction of Rs.5,60,742/- from the final bill

submitted by Petitioner for the period from 17.07.2020 to

16.10.2020, and whether such deduction is arbitrary or

contrary to the terms of the contract so as to warrant

interference under Article 226 of the Constitution. Respondents

have placed before this Court detailed calculations

demonstrating that as against the contractual requirement of

7205 man-days (calculated at 11 persons per day over 655

days, excluding 76 lockdown days), Petitioner had provided only

6191 man-days, resulting in a shortfall of 1014 man-days.

Respondents have further shown that deduction of

Rs.5,60,742/- was computed based on the minimum wage rate

of Rs.553/- per day per person, applied proportionately to the

said shortfall.

7. It is to be seen, such calculation is not a bald

assertion, but is supported by muster rolls, wage records, and

other documents which, according to Respondents, were

themselves submitted by Petitioner during the course of

execution of the contract. Respondents have also pointed out

that Petitioner, instead of deploying the requisite number of

personnel on a daily basis, had provided rest to one or two

employees without engaging additional rest givers, thereby

resulting in effective shortage of manpower in terms of the

contract.

8. Petitioner had sought to controvert the said position

by contending that he had engaged 14 persons including rest

givers and provided 84 hours of service per day, and that the

discrepancies in the records are attributable to typographical

errors in the computerized attendance registers for the last

three months of the contract period. However, the explanation

offered by Petitioner does not satisfactorily reconcile the

material inconsistencies highlighted by Respondents. The

contradictions between the initial muster rolls and the revised

muster rolls, the mismatch in attendance records, and the

variation in the period and details of workers, as pointed out in

the counter affidavit, cannot be brushed aside as mere

typographical errors. Such inconsistencies go to the root of the

matter and directly impact the determination of whether the

contractual obligations relating to deployment of manpower

were fulfilled.

9. Further, it is pertinent to note that the contractual

provisions governing the relationship between the parties

expressly provide for proportionate deduction in the event of

shortfall in manpower or non-compliance with contractual

obligations. Clauses 11(12), II(14), XIII(2) and XV of the

agreement clearly stipulate that payment shall be made only for

the actual manpower deployed, that proportionate deductions

shall be effected for any shortfall in the minimum number of

hours of service rendered, and that penal deductions may be

imposed for failure to comply with the terms of the contract.

10. In the present case, Respondents have

demonstrated that deductions made from the final bill were

effected in accordance with the said contractual provisions.

upon scrutiny and verification of the records by the competent

authorities, including the office of the Senior Divisional

Commercial Manager and the Senior Divisional Finance

Manager. There is nothing on record to indicate that such

deductions were made de hors the contract or in an arbitrary

manner.

11. This Court is also of the considered view that the

dispute raised by Petitioner involves seriously contested

questions of fact, including the actual number of personnel

deployed, the correctness and authenticity of muster rolls and

wage records, and the extent of compliance with the contractual

conditions. Such issues require detailed examination of

evidence and cannot be adjudicated in proceedings under

Article 226 of the Constitution, which are essentially summary

in nature. It is further relevant to note that the Agreement

between the parties provides for an alternative dispute

resolution mechanism by way of arbitration under clause XI. In

the presence of such an efficacious contractual remedy, and

particularly when the dispute pertains to interpretation and

enforcement of contractual terms coupled with disputed

questions of fact, this Court would be slow to exercise its writ

jurisdiction.

12. Insofar as the allegation of violation of Articles 14,

21 and 311 of the Constitution is concerned, this Court finds

that the dispute is essentially rooted in the terms of a

commercial contract entered into between the parties. The

action of Respondents in making deductions strictly in

accordance with the contractual stipulations, based on the

material available on record, cannot be characterized as

arbitrary, unreasonable, or violative of constitutional

guarantees. Mere non-payment of a portion of the claimed

amount, when justified under the terms of the contract, does

not give rise to a constitutional cause of action.

13. In view of the foregoing discussion and for the

reasons stated hereinabove, this Court is of the considered

opinion that Petitioner failed to establish any illegality,

arbitrariness, or violation of statutory or constitutional

provisions warranting interference under Article 226 of the

Constitution. The dispute raised is purely contractual in nature,

involves disputed questions of fact and Respondents have acted

within the four corners of the Agreement.

14. The writ petition is therefore, dismissed. No costs.

15. Consequently, the miscellaneous Applications, if

any shall stand closed.

-------- -----------------------------

NAGESH BHEEMAPAKA, J

07th April 2026

ksld

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter